20787 W LIANA CT 91326
Certificate Information: 20787 W LIANA CT 91326
- Application / Permit
- 19010-20000-06207
- Plan Check / Job No.
- B19VN22494
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 2 STORY SFD WITH ATTACHED GARAGE_STANDARD PLAN #651_PLAN 3BR_BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
- Permit Issued
- Issued on 9/8/2020
- Issuing Office
- Current Status
- CofO Issued on 7/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | DAWN MC NULTY |
| Green Plans Picked Up | 1/16/2020 | APPLICANT |
| Corrections Issued | 1/21/2020 | DAWN MC NULTY |
| Quality Review Completed | 1/21/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/28/2020 | APPLICANT |
| Plan Check Approved | 7/31/2020 | DAWN MC NULTY |
| Issued | 9/8/2020 | APPLICANT |
| CofO in Progress | 7/14/2021 | SEAN WIRCH |
| Permit Finaled | 7/14/2021 | MICHAEL SMITH |
| CofO Issued | 7/14/2021 | MICHAEL SMITH |
| Permit Finaled | 7/14/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| "T" removal | Cleared | 4/17/2020 | DENZEL HENDERSON |
| CPC | Cleared | 4/17/2020 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 4/17/2020 | DENZEL HENDERSON |
| Specific Plan | Cleared | 4/17/2020 | DENZEL HENDERSON |
| Tract Map conditions | Cleared | 4/17/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/17/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 4/17/2020 | DENZEL HENDERSON |
| Address approval | Cleared | 4/20/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2020 | LEE GUILBEAUX |
| Permit | Cleared | 4/20/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/20/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/20/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/20/2020 | LEE GUILBEAUX |
| Public Works-Open Permits | Cleared | 4/20/2020 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 6/3/2020 | AMMAR ELTAWIL |
| Hydrant and Access approval | Cleared | 6/8/2020 | MATTHEW CRAIG |
| Green Code | Cleared | 7/17/2020 | MICHAEL AYERS |
Contact Information
| Architect | Swift,, Daniel R; Lic. No.: C32860 | 4601 WESTOWN PARKWAY SUITE 208 WEST DES MOINES, IA 50266 |
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Van, Gaale, Mark Allan; Lic. No.: C58680 | 26772 DESERT LOCUST ST MURRIETA, CA 92562 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/19/2020 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 11/2/2020 | Approved | SEAN WIRCH |
| Sewer | 11/17/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Partial Approval | SEAN WIRCH |
| Deputy Wood Construction | 2/11/2021 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2021 | Partial Approval | SEAN WIRCH |
| HVAC-Rough | 2/22/2021 | Not Ready for Inspection | SEAN WIRCH |
| ELECTRICAL-Rough | 3/10/2021 | Approved | SEAN WIRCH |
| HVAC-Rough | 3/10/2021 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2021 | No Access for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 3/23/2021 | Approved | SEAN WIRCH |
| Green Building Rough | 3/23/2021 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 3/23/2021 | Approved | SEAN WIRCH |
| Drywall Nailing | 4/1/2021 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 4/9/2021 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 4/16/2021 | Partial Approval | SEAN WIRCH |
| Shower Pan | 4/16/2021 | Approved | SEAN WIRCH |
| Gas Test | 4/22/2021 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 5/11/2021 | SGSOV Approved | SEAN WIRCH |
| Service/Power Release | 6/7/2021 | Corrections Issued | SEAN WIRCH |
| PLUMBING-Final | 6/9/2021 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 6/15/2021 | Approved | SEAN WIRCH |
| HVAC-Final | 6/15/2021 | Approved | SEAN WIRCH |
| Service/Power Release | 6/22/2021 | Approved | SEAN WIRCH |
| Final | 6/28/2021 | Not Ready for Inspection | SEAN WIRCH |
| Green Building Final | 6/28/2021 | Approved | SEAN WIRCH |
| Smoke Detectors | 6/28/2021 | Approved | SEAN WIRCH |
| Final | 7/15/2021 | OK to Issue CofO | SEAN WIRCH |