10523 W PENROSE ST 91352
Certificate Information: 10523 W PENROSE ST 91352
- Application / Permit
- 19010-20000-06192
- Plan Check / Job No.
- B19VN22484
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ONE STORY ACCESSORY DWELLING UNIT (49'-0"x24'-4") all works per wfpp
- Permit Issued
- Issued on 12/16/2020
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/5/2020 | MOHAMMAD ESMAILI |
| Green Plans Picked Up | 2/6/2020 | APPLICANT |
| Quality Review Completed | 2/13/2020 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/8/2020 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/9/2020 | MOHAMMAD ESMAILI |
| Issued | 12/16/2020 | APPLICANT |
| Building Plans Picked Up | 12/22/2020 | APPLICANT |
| CofO in Progress | 10/25/2022 | DAVID ANDERSON |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/16/2020 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 6/8/2020 | BRIAN MILLER |
| Green Code | Cleared | 7/2/2020 | AARON COSTA |
| Specific Plan | Cleared | 8/14/2020 | PEGGY MALONE-BROWN |
| Low Impact Development | Cleared | 9/9/2020 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 9/29/2020 | MATTHEW CRAIG |
| GPI Written Notices | Cleared | 11/23/2020 | MOHAMMAD ESMAILI |
| Roof/Waste drainage to street | Cleared | 11/23/2020 | MIKE KOUYOUMDJIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/30/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 6/30/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/30/2021 | Partial Approval | JOHN HAYES |
| Sewer | 6/30/2021 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 6/30/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 7/8/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/3/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2021 | Partial Inspection | WILLIAM KUEHN |
| Green Building Rough | 8/3/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 8/3/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2021 | Partial Approval | WILLIAM KUEHN |
| Sewer | 8/24/2021 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 8/24/2021 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 9/7/2021 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 9/7/2021 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 9/7/2021 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 9/7/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 9/9/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 9/9/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 9/9/2021 | Approved | WILLIAM KUEHN |
| HVAC-Rough | 9/9/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 9/9/2021 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 9/9/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 9/9/2021 | Approved | WILLIAM KUEHN |
| Insulation | 9/13/2021 | Conditional Approval | JUSTIN HAWLEY |
| Drywall Nailing | 9/16/2021 | Approved | JUSTIN HAWLEY |
| Insulation | 9/16/2021 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/30/2021 | Partial Inspection | WILLIAM KUEHN |
| ELECTRICAL-Final | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 4/15/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 10/17/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 10/17/2022 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 10/17/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 10/17/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 10/24/2022 | Approved | DAVID ANDERSON |
| Final | 10/24/2022 | OK to Issue CofO | DAVID ANDERSON |
| Gas Test | 10/24/2022 | Approved | DAVID ANDERSON |
| Green Building Final | 10/24/2022 | Approved | DAVID ANDERSON |
| HVAC-Final | 10/24/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 10/24/2022 | Approved | DAVID ANDERSON |
| Service/Power Release | 10/24/2022 | Approved | DAVID ANDERSON |