2683-2683 1/2 E ROSEVIEW AVE 90065

Certificate Information: 2683-2683 1/2 E ROSEVIEW AVE 90065

Application / Permit
19010-20000-06160
Plan Check / Job No.
B19VN22459
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(2 OF 2) (N) 3-STORY 60'-8" X 28'-0" DUPLEX AT REAR OF LOT (PARKING ON 1ST FLOOR). NFPA 13D FIRE SPRINKLERS REQ'D
Permit Issued
Issued on 9/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 MARVEL DELACRUZ
Corrections Issued 1/11/2020 MARVEL DELACRUZ
Quality Review Completed 1/15/2020 GUANG MIN TUNG
Building Plans Picked Up 1/16/2020 APPLICANT
Green Plans Picked Up 1/16/2020 APPLICANT
Applicant returned to address corrections 10/20/2020 MARVEL DELACRUZ
Applicant returned to address corrections 6/4/2021 MARVEL DELACRUZ
Applicant returned to address corrections 9/24/2021 MARVEL DELACRUZ
Applicant returned to address corrections 10/8/2021 MARVEL DELACRUZ
Applicant returned to address corrections 2/17/2022 MARVEL DELACRUZ
Plan Check Approved 5/4/2022 RAPHAEL ROSAS
Issued 9/23/2022 APPLICANT
CofO in Progress 6/4/2024 OSVALDO PARAMO
Permit Finaled 6/10/2024 DEROLD HAUFF
CofO Issued 6/10/2024 DEROLD HAUFF
Permit Finaled 6/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/17/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 1/17/2020 JUAN ASHTON
Highway dedication Cleared 1/17/2020 JUAN ASHTON
Sewer availability Cleared 1/17/2020 JUAN ASHTON
Grading Pre-Inspection Cleared 1/29/2020 PATRICK MISCHLICH
Hydrant and Access approval Cleared 2/18/2021 MATTHEW CRAIG
Green Code Cleared 3/3/2021 DAVID MATSON
Low Impact Development Cleared 9/2/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/8/2021 STEVE MELGAR
Frnt yard landscape/Water mgmt Cleared 4/25/2022 JASON CHAN
Supp. Use District POD/CDO/TDO Cleared 4/25/2022 JASON CHAN
ZI Cleared 4/25/2022 JASON CHAN
ZI Cleared 4/25/2022 JASON CHAN
GPI Written Notices Cleared 5/4/2022 MARVEL DELACRUZ

Contact Information

Contractor Marc'S Construction Inc; Lic. No.: 1074627-B 5690 FULLERTON AVE APT 2      BUENA PARK, CA 90621
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/20/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 10/20/2022 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 11/16/2022 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 11/16/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 2/9/2023 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 5/26/2023 Conditional Approval OSVALDO PARAMO
ELECTRICAL-Rough 6/7/2023 Partial Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/7/2023 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/7/2023 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/26/2023 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 7/24/2023 Not Ready for Inspection RUBEN SALAS
HVAC-Rough 7/24/2023 Not Ready for Inspection RUBEN SALAS
Interior/Exterior Lathing 7/24/2023 Partial Approval RUBEN SALAS
PLUMBING-Rough 7/24/2023 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Rough 8/2/2023 Approved BRIAN SULLIVAN
HVAC-Rough 8/2/2023 Partial Approval BRIAN SULLIVAN
Insulation 8/2/2023 Not Ready for Inspection BRIAN SULLIVAN
PLUMBING-Rough 8/2/2023 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/3/2023 Approved BRIAN SULLIVAN
Green Building Rough 8/3/2023 Approved BRIAN SULLIVAN
HVAC-Rough 8/3/2023 Approved BRIAN SULLIVAN
Verify Sprinkler Sign Off 8/3/2023 Approved BRIAN SULLIVAN
Insulation 8/9/2023 Approved ALIZAH MAYAGOITIA
Deputy Wood Construction 8/15/2023 Conditional Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Approved OSVALDO PARAMO
Drywall Nailing 8/25/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 10/18/2023 Approved OSVALDO PARAMO
Shower Pan 10/18/2023 Approved OSVALDO PARAMO
Sewer 10/26/2023 Approved OSVALDO PARAMO
PLUMBING-Rough 11/2/2023 Partial Approval OSVALDO PARAMO
ELECTRICAL-Final 3/13/2024 Corrections Issued OSVALDO PARAMO
PLUMBING-Final 3/13/2024 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Final 3/20/2024 Conditional Approval OSVALDO PARAMO
Gas Test 3/20/2024 Approved OSVALDO PARAMO
PLUMBING-Final 3/20/2024 Approved OSVALDO PARAMO
ELECTRICAL-Final 4/24/2024 Approved JOSEPH MCGARRY
Final 4/24/2024 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 4/24/2024 Approved JOSEPH MCGARRY
Green Building Final 4/24/2024 Approved JOSEPH MCGARRY
HVAC-Final 4/24/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/24/2024 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 4/24/2024 Approved JOSEPH MCGARRY
Smoke Detectors 4/24/2024 Approved JOSEPH MCGARRY
Final 5/29/2024 OK to Issue CofO OSVALDO PARAMO