2683-2683 1/2 E ROSEVIEW AVE 90065
Certificate Information: 2683-2683 1/2 E ROSEVIEW AVE 90065
- Application / Permit
- 19010-20000-06160
- Plan Check / Job No.
- B19VN22459
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (2 OF 2) (N) 3-STORY 60'-8" X 28'-0" DUPLEX AT REAR OF LOT (PARKING ON 1ST FLOOR). NFPA 13D FIRE SPRINKLERS REQ'D
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | MARVEL DELACRUZ |
| Corrections Issued | 1/11/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 1/15/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 1/16/2020 | APPLICANT |
| Green Plans Picked Up | 1/16/2020 | APPLICANT |
| Applicant returned to address corrections | 10/20/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 6/4/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 9/24/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 10/8/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 2/17/2022 | MARVEL DELACRUZ |
| Plan Check Approved | 5/4/2022 | RAPHAEL ROSAS |
| Issued | 9/23/2022 | APPLICANT |
| CofO in Progress | 6/4/2024 | OSVALDO PARAMO |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
| CofO Issued | 6/10/2024 | DEROLD HAUFF |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/17/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 1/17/2020 | JUAN ASHTON |
| Highway dedication | Cleared | 1/17/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 1/17/2020 | JUAN ASHTON |
| Grading Pre-Inspection | Cleared | 1/29/2020 | PATRICK MISCHLICH |
| Hydrant and Access approval | Cleared | 2/18/2021 | MATTHEW CRAIG |
| Green Code | Cleared | 3/3/2021 | DAVID MATSON |
| Low Impact Development | Cleared | 9/2/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | STEVE MELGAR |
| Frnt yard landscape/Water mgmt | Cleared | 4/25/2022 | JASON CHAN |
| Supp. Use District POD/CDO/TDO | Cleared | 4/25/2022 | JASON CHAN |
| ZI | Cleared | 4/25/2022 | JASON CHAN |
| ZI | Cleared | 4/25/2022 | JASON CHAN |
| GPI Written Notices | Cleared | 5/4/2022 | MARVEL DELACRUZ |
Contact Information
| Contractor | Marc'S Construction Inc; Lic. No.: 1074627-B | 5690 FULLERTON AVE APT 2 BUENA PARK, CA 90621 |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/20/2022 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 10/20/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 11/16/2022 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 11/16/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 2/9/2023 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2023 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Partial Approval | OSVALDO PARAMO |
| Deputy Wood Construction | 5/26/2023 | Conditional Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/7/2023 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Partial Inspection | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2023 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/24/2023 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Rough | 7/24/2023 | Not Ready for Inspection | RUBEN SALAS |
| Interior/Exterior Lathing | 7/24/2023 | Partial Approval | RUBEN SALAS |
| PLUMBING-Rough | 7/24/2023 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Rough | 8/2/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 8/2/2023 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 8/2/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/2/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 8/3/2023 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 8/3/2023 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 8/3/2023 | Approved | BRIAN SULLIVAN |
| Insulation | 8/9/2023 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 8/15/2023 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 8/25/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/18/2023 | Approved | OSVALDO PARAMO |
| Shower Pan | 10/18/2023 | Approved | OSVALDO PARAMO |
| Sewer | 10/26/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 11/2/2023 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Final | 3/13/2024 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 3/13/2024 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 3/20/2024 | Conditional Approval | OSVALDO PARAMO |
| Gas Test | 3/20/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 3/20/2024 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 4/24/2024 | Approved | JOSEPH MCGARRY |
| Final | 4/24/2024 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/24/2024 | Approved | JOSEPH MCGARRY |
| Green Building Final | 4/24/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 4/24/2024 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/24/2024 | SGSOV Approved | JOSEPH MCGARRY |
| Service/Power Release | 4/24/2024 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 4/24/2024 | Approved | JOSEPH MCGARRY |
| Final | 5/29/2024 | OK to Issue CofO | OSVALDO PARAMO |