1040 E MONTECITO DR 90031

Certificate Information: 1040 E MONTECITO DR 90031

Application / Permit
19010-20000-06154
Plan Check / Job No.
B19VN22452
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/27/2025
Issuing Office
Metro
Current Status
Issued on 2/27/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 SELLA BENYAMIN
Corrections Issued 1/13/2020 SELLA BENYAMIN
Quality Review Completed 1/16/2020 STEVEN KIM
Building Plans Picked Up 1/16/2020 APPLICANT
Green Plans Picked Up 1/16/2020 APPLICANT
Applicant returned to address corrections 2/16/2024 SELLA BENYAMIN
Applicant returned to address corrections 6/6/2024 SELLA BENYAMIN
Plan Check Approved 9/17/2024 SELLA BENYAMIN
Issued 2/27/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/17/2020 JEANIE LAM
BHO/Hillside ordinance Cleared 1/17/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/17/2020 JEANIE LAM
Hydrant and Access approval Cleared 7/6/2021 KURT CORRAL
Low Impact Development Cleared 7/27/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/29/2021 THOMAS LANG
"D" conditions Cleared 4/20/2023 DALIA MOKAYED
"Q" conditions Cleared 4/20/2023 DALIA MOKAYED
BHO/Hillside ordinance Cleared 1/19/2024 ARMEN MEHRABIAN
Sewer availability Cleared 1/19/2024 ARMEN MEHRABIAN
Green Code Cleared 2/16/2024 SELLA BENYAMIN
GPI Written Notices Cleared 6/6/2024 SELLA BENYAMIN
Grading Pre-Inspection Cleared 6/6/2024 SELLA BENYAMIN

Contact Information

Contractor Atp Development & Construction; Lic. No.: 1092130-B 1720 LA CRESTA DR      PASADENA, CA 91103

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 4/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Piling/Pier/Caisson 4/14/2025 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 5/16/2025 Corrections Issued LILIANA PORTILLO
Deputy Other (see comments) 5/19/2025 Conditional Approval LILIANA PORTILLO
Deputy Reinf. Concrete 5/19/2025 Conditional Approval LILIANA PORTILLO
Deputy Reinf. Concrete 5/29/2025 Conditional Approval LILIANA PORTILLO
Piling/Pier/Caisson 5/30/2025 Corrections Issued LILIANA PORTILLO
Piling/Pier/Caisson 6/26/2025 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 7/11/2025 Approved LILIANA PORTILLO
Deputy Reinf. Concrete 7/11/2025 No Access for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 7/11/2025 Corrections Issued LILIANA PORTILLO
Deputy Reinf. Concrete 7/14/2025 Conditional Approval REGINA MENDEZ
Footing/Foundation/Slab 7/23/2025 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 8/20/2025 Approved LILIANA PORTILLO
Deputy Reinf. Concrete 8/20/2025 Conditional Approval LILIANA PORTILLO
Masonry Wall/Backfill 8/21/2025 Partial Approval LILIANA PORTILLO
Piling/Pier/Caisson 8/21/2025 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 8/25/2025 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 9/9/2025 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 9/10/2025 Approved REGINA MENDEZ
Masonry Wall/Backfill 9/22/2025 Partial Approval LILIANA PORTILLO
Deputy Reinf. Concrete 9/24/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/2/2025 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/7/2025 Partial Approval DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/9/2026 Partial Approval LILIANA PORTILLO
Deputy Other (see comments) 2/23/2026 Approved LILIANA PORTILLO
Special/Order Compliance 2/23/2026 Partial Inspection LILIANA PORTILLO
Wood Frame 3/3/2026 Not Ready for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 3/23/2026 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 4/1/2026 Conditional Approval GEM DE OCAMPO
Floor/Roof Diaphrgm/Shear Wall 4/3/2026 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/15/2026 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 4/23/2026 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/23/2026 Approved LILIANA PORTILLO
PLUMBING-Rough 4/23/2026 Approved LILIANA PORTILLO
ELECTRICAL-Rough 4/27/2026 Approved ALIZAH MAYAGOITIA
HVAC-Rough 4/27/2026 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 4/30/2026 Corrections Issued LILIANA PORTILLO
Masonry Wall/Backfill 4/30/2026 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 5/4/2026 Corrections Issued DAVID WILLIAMS
BUILDING-Rough-Frame 5/7/2026 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 5/7/2026 Partial Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 5/7/2026 Approved LILIANA PORTILLO
HVAC-Rough 6/3/2026 Approved LILIANA PORTILLO