19220 W LANARK ST 91335

Certificate Information: 19220 W LANARK ST 91335

Application / Permit
19010-20000-06141
Plan Check / Job No.
B19VN22441
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
(N) 57' X 20'-6" DETACHED ACCESSORY LIVING QUARTERS. NFPA-13D FIRE SPRINKLERS REQUIRED. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/27/2020
Issuing Office
Current Status
CofO Issued on 11/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 PARISA ZAHABI
Corrections Issued 1/28/2020 PARISA ZAHABI
Green Plans Picked Up 2/4/2020 APPLICANT
Quality Review Completed 2/12/2020 OMID HEDAYAT
Building Plans Picked Up 2/14/2020 APPLICANT
Applicant returned to address corrections 8/28/2020 PARISA ZAHABI
Applicant returned to address corrections 8/31/2020 PARISA ZAHABI
Plan Check Approved 10/6/2020 PARISA ZAHABI
Issued 10/27/2020 APPLICANT
CofO in Progress 11/16/2021 VINCENT HANLEY
Permit Finaled 11/20/2021 MICHAEL SMITH
CofO Issued 11/20/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/6/2020 GUILLERMO PETRA
Sewer availability Cleared 5/6/2020 GUILLERMO PETRA
Green Code Cleared 7/1/2020 PARISA ZAHABI
Roof/Waste drainage to street Cleared 7/22/2020 GUILLERMO PETRA
Low Impact Development Cleared 8/5/2020 MARTIN FRAGOSO
Hydrant and Access approval Cleared 8/17/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/10/2020 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/17/2020 Approved VINCENT HANLEY
ELECTRICAL-Rough 12/15/2020 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/15/2020 Partial Approval VINCENT HANLEY
HVAC-Rough 12/15/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 12/15/2020 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 1/15/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/15/2021 Approved VINCENT HANLEY
HVAC-Rough 1/15/2021 Approved VINCENT HANLEY
PLUMBING-Rough 1/15/2021 Approved VINCENT HANLEY
Wood Frame 1/15/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/22/2021 Approved VINCENT HANLEY
Green Building Rough 1/22/2021 Approved VINCENT HANLEY
Insulation 1/22/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/22/2021 Approved VINCENT HANLEY
Shower Pan 1/22/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 1/22/2021 Approved VINCENT HANLEY
Drywall Nailing 2/2/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/2/2021 Approved VINCENT HANLEY
Final 10/19/2021 Corrections Issued ROBERT GOLD
Green Building Final 10/19/2021 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 10/19/2021 SGSOV Not Ready ROBERT GOLD
Service/Power Release 10/19/2021 Not Ready for Inspection ROBERT GOLD
Smoke Detectors 10/19/2021 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Not Ready RONALD COWAN
Service/Power Release 11/4/2021 Approved RONALD COWAN
Smoke Detectors 11/4/2021 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Final 11/5/2021 Approved VINCENT HANLEY
Final 11/5/2021 Partial Inspection VINCENT HANLEY
Gas Test 11/5/2021 Approved VINCENT HANLEY
Green Building Final 11/5/2021 Approved VINCENT HANLEY
HVAC-Final 11/5/2021 Approved VINCENT HANLEY
PLUMBING-Final 11/5/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/5/2021 SGSOV Approved VINCENT HANLEY
Sewer 11/5/2021 Approved VINCENT HANLEY
Smoke Detectors 11/5/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/5/2021 Approved VINCENT HANLEY
Final 11/16/2021 OK to Issue CofO VINCENT HANLEY