6754 W 86TH PL 90045

Certificate Information: 6754 W 86TH PL 90045

Application / Permit
19010-20000-06101
Plan Check / Job No.
B19VN22399
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 43' X 20' (2) STORY SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 SELLA BENYAMIN
Green Plans Picked Up 1/9/2020 APPLICANT
Corrections Issued 1/13/2020 SELLA BENYAMIN
Quality Review Completed 1/13/2020 STEVEN KIM
Building Plans Picked Up 1/14/2020 APPLICANT
Plan Check Approved 3/17/2020 SELLA BENYAMIN
Issued 8/24/2020 APPLICANT
CofO in Progress 8/9/2021 PIERRE VEGA
CofO in Progress 8/9/2021 PIERRE VEGA
CofO Issued 8/10/2021 VINCENT COTTON
Permit Finaled 8/10/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 2/11/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/11/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 2/11/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/11/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/11/2020 JOHN TRIANTAFYLLOS
"Q" conditions Cleared 2/12/2020 VINCENT QUITORIANO
Hydrant and Access approval Cleared 2/12/2020 GEORGE SUCHAND
Green Code Cleared 2/13/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 9/14/2020 Partial Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/23/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 9/23/2020 Not Ready for Inspection JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/24/2020 Not Ready for Inspection JUAN VALENZUELA
Special/Order Compliance 9/24/2020 Partial Inspection PIERRE VEGA
Excavation/Setback/Form/Re-Bar 10/1/2020 Corrections Issued PIERRE VEGA
Excavation/Setback/Form/Re-Bar 10/2/2020 Approved PIERRE VEGA
Footing/Foundation/Slab 10/2/2020 Partial Approval PIERRE VEGA
Footing/Foundation/Slab 10/9/2020 Approved JUAN VALENZUELA
Sewer 10/14/2020 Approved JUAN VALENZUELA
Special/Order Compliance 10/14/2020 Partial Approval PIERRE VEGA
Floor/Roof Diaphrgm/Shear Wall 10/21/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval JUAN VALENZUELA
Special/Order Compliance 11/9/2020 Partial Inspection PIERRE VEGA
PLUMBING-Rough 11/23/2020 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 11/24/2020 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 11/25/2020 Corrections Issued JUAN VALENZUELA
HVAC-Rough 11/25/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 12/7/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Approved JUAN VALENZUELA
Gas Test 12/7/2020 Partial Inspection JUAN VALENZUELA
PLUMBING-Rough 12/7/2020 Approved JUAN VALENZUELA
Shower Pan 12/7/2020 Not Ready for Inspection JUAN VALENZUELA
Insulation 12/9/2020 Corrections Issued DAVID HEINE
Drywall Nailing 12/14/2020 Partial Inspection JUAN VALENZUELA
Insulation 12/14/2020 Partial Inspection JUAN VALENZUELA
Interior/Exterior Lathing 1/15/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 2/12/2021 Approved JUAN VALENZUELA
Green Building Rough 2/12/2021 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/12/2021 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 2/12/2021 Approved JUAN VALENZUELA
Gas Test 3/16/2021 Approved JUAN VALENZUELA
Underground Mechanical 3/16/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 3/31/2021 Corrections Issued BRENDAN LOONEY
HVAC-Final 3/31/2021 Approved BRENDAN LOONEY
PLUMBING-Final 3/31/2021 Approved BRENDAN LOONEY
ELECTRICAL-Final 4/6/2021 Approved BRENDAN LOONEY
Final 4/29/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 4/29/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 4/29/2021 SGSOV Approved BRENDAN LOONEY
Service/Power Release 4/29/2021 Approved BRENDAN LOONEY
Smoke Detectors 4/29/2021 Approved BRENDAN LOONEY
Final 6/14/2021 Corrections Issued RICHARD ROBLES
Green Building Final 6/14/2021 Order to Comply Issued RICHARD ROBLES
Final 8/9/2021 OK to Issue CofO PIERRE VEGA
Green Building Final 8/9/2021 Approved PIERRE VEGA