6754 W 86TH PL 90045
Certificate Information: 6754 W 86TH PL 90045
- Application / Permit
- 19010-20000-06101
- Plan Check / Job No.
- B19VN22399
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 43' X 20' (2) STORY SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | SELLA BENYAMIN |
| Green Plans Picked Up | 1/9/2020 | APPLICANT |
| Corrections Issued | 1/13/2020 | SELLA BENYAMIN |
| Quality Review Completed | 1/13/2020 | STEVEN KIM |
| Building Plans Picked Up | 1/14/2020 | APPLICANT |
| Plan Check Approved | 3/17/2020 | SELLA BENYAMIN |
| Issued | 8/24/2020 | APPLICANT |
| CofO in Progress | 8/9/2021 | PIERRE VEGA |
| CofO in Progress | 8/9/2021 | PIERRE VEGA |
| CofO Issued | 8/10/2021 | VINCENT COTTON |
| Permit Finaled | 8/10/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 2/11/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 2/11/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/11/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/11/2020 | JOHN TRIANTAFYLLOS |
| "Q" conditions | Cleared | 2/12/2020 | VINCENT QUITORIANO |
| Hydrant and Access approval | Cleared | 2/12/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 2/13/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/14/2020 | Partial Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 9/23/2020 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/23/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 9/24/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Special/Order Compliance | 9/24/2020 | Partial Inspection | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 10/1/2020 | Corrections Issued | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 10/2/2020 | Approved | PIERRE VEGA |
| Footing/Foundation/Slab | 10/2/2020 | Partial Approval | PIERRE VEGA |
| Footing/Foundation/Slab | 10/9/2020 | Approved | JUAN VALENZUELA |
| Sewer | 10/14/2020 | Approved | JUAN VALENZUELA |
| Special/Order Compliance | 10/14/2020 | Partial Approval | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Partial Approval | JUAN VALENZUELA |
| Special/Order Compliance | 11/9/2020 | Partial Inspection | PIERRE VEGA |
| PLUMBING-Rough | 11/23/2020 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 11/24/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 11/25/2020 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 11/25/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2020 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Rough | 12/7/2020 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Approved | JUAN VALENZUELA |
| Gas Test | 12/7/2020 | Partial Inspection | JUAN VALENZUELA |
| PLUMBING-Rough | 12/7/2020 | Approved | JUAN VALENZUELA |
| Shower Pan | 12/7/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Insulation | 12/9/2020 | Corrections Issued | DAVID HEINE |
| Drywall Nailing | 12/14/2020 | Partial Inspection | JUAN VALENZUELA |
| Insulation | 12/14/2020 | Partial Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/15/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/12/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 2/12/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/12/2021 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 2/12/2021 | Approved | JUAN VALENZUELA |
| Gas Test | 3/16/2021 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 3/16/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 3/31/2021 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 3/31/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 3/31/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Final | 4/6/2021 | Approved | BRENDAN LOONEY |
| Final | 4/29/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 4/29/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 4/29/2021 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 4/29/2021 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 4/29/2021 | Approved | BRENDAN LOONEY |
| Final | 6/14/2021 | Corrections Issued | RICHARD ROBLES |
| Green Building Final | 6/14/2021 | Order to Comply Issued | RICHARD ROBLES |
| Final | 8/9/2021 | OK to Issue CofO | PIERRE VEGA |
| Green Building Final | 8/9/2021 | Approved | PIERRE VEGA |