538 N SPOLETO DR 90272

Certificate Information: 538 N SPOLETO DR 90272

Application / Permit
19010-20000-06054
Plan Check / Job No.
B19VN22334
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 76.75' x 79'8" irregular shape 2-story w/1-level basement dwelling, sprinkler req'd throughout, interior 3-stop elevator and attached 2-car garage, patio cover/trellises
Permit Issued
Issued on 3/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 ALDOUS CHIC
Corrections Issued 1/13/2020 ALDOUS CHIC
Quality Review Completed 1/14/2020 ABDUL CHEGENI
Building Plans Picked Up 1/15/2020 APPLICANT
Green Plans Picked Up 1/15/2020 APPLICANT
Applicant returned to address corrections 2/14/2020 ALDOUS CHIC
Applicant returned to address corrections 2/25/2020 ALDOUS CHIC
Plan Check Approved 3/5/2020 ALDOUS CHIC
Issued 3/6/2020 LADBS
CofO in Progress 10/20/2021 JOHN KIDWELL
Permit Finaled 11/24/2021 RONALD MYRICK
CofO Issued 11/24/2021 RONALD MYRICK
Permit Finaled 11/24/2021 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/30/2019 ALDOUS CHIC
Trees in Parkway Cleared 1/16/2020 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 2/4/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 2/4/2020 GUILLERMO PETRA
BHO/Hillside ordinance Cleared 2/4/2020 GUILLERMO PETRA
Highway dedication Cleared 2/4/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 2/4/2020 GEORGE SUCHAND
Permit Cleared 2/4/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/19/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/19/2020 MARKOS PEREZ-BRAN
Low Impact Development Cleared 2/21/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/21/2020 THOMAS LANG
GPI Written Notices Cleared 2/25/2020 ALDOUS CHIC
Green Code Cleared 2/25/2020 MICHAEL AYERS
Disturb/Remove Protected Trees Cleared 3/2/2020 STEPHEN DUPREY
Hold Cleared 4/22/2020 JEREMY CORONEL

Contact Information

Contractor Sky Remodeling Inc; Lic. No.: 955109-B 12439 MAGNOLIA BLVD #245      VALLEY VILLAGE, CA 91607
Engineer Daneshfar,, Kourosh Dan; Lic. No.: C68377 19722 ARMINTA ST      WINNETKA, CA 91306
Engineer Tran,, Quang Tai; Lic. No.: C70929 355 N LANTANA ST 333      CAMARILLO, CA 93010
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302
Geologist Feffer,, Joshua Rafael; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2020 Approved DANNY TOLENTINO
PLUMBING-Rough 4/23/2020 Partial Approval DANNY TOLENTINO
Underground Mechanical 4/23/2020 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 5/8/2020 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 5/26/2020 Partial Approval ANDREW NAVE
Deputy Other (see comments) 5/27/2020 Conditional Approval DANNY TOLENTINO
BUILDING-Rough-Frame 7/13/2020 Partial Inspection JOHN KIDWELL
Deputy Reinf. Concrete 7/13/2020 Approved ROBERT SHELLY
Footing/Foundation/Slab 7/13/2020 Partial Inspection JOHN KIDWELL
Green Building Rough 7/13/2020 Partial Inspection JOHN KIDWELL
Verify Sprinkler Sign Off 7/13/2020 Partial Inspection JOHN KIDWELL
Deputy Reinf. Concrete 7/17/2020 Approved ROBERT SHELLY
Deputy Steel/Welding 7/27/2020 Corrections Issued ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/10/2020 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/11/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 9/10/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 9/10/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 9/15/2020 Approved JOHN KIDWELL
PLUMBING-Rough 9/15/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 9/16/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 9/18/2020 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 10/8/2020 Approved JOHN KIDWELL
Structural Steel Frame 10/8/2020 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 10/21/2020 Approved JOHN KIDWELL
Green Building Rough 10/21/2020 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 10/21/2020 Approved JOHN KIDWELL
Drywall Nailing 11/13/2020 Approved JOHN KIDWELL
Gas Test 11/13/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 11/13/2020 Partial Approval JOHN KIDWELL
Shower Pan 11/13/2020 Approved JOHN KIDWELL
PLUMBING-Rough 12/18/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Pre-Inspection 1/20/2021 Partial Inspection JOHN KIDWELL
Gas Test 3/30/2021 Partial Inspection JUAN VALENZUELA
Gas Test 5/24/2021 Not Ready for Inspection JOHN KIDWELL
Gas Test 6/1/2021 Approved JOHN KIDWELL
Service/Power Release 6/17/2021 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 6/30/2021 Partial Inspection JOHN KIDWELL
ELECTRICAL-Final 7/14/2021 Approved JOHN KIDWELL
HVAC-Final 8/6/2021 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 8/6/2021 Approved JOHN KIDWELL
HVAC-Final 8/16/2021 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 8/16/2021 Approved JOHN KIDWELL
HVAC-Final 10/5/2021 Approved JOHN KIDWELL
Final 10/14/2021 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 10/14/2021 Approved JOHN KIDWELL
Green Building Final 10/14/2021 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved JOHN KIDWELL
Smoke Detectors 10/14/2021 Approved JOHN KIDWELL
Final 10/20/2021 OK to Issue CofO JOHN KIDWELL