538 N SPOLETO DR 90272
Certificate Information: 538 N SPOLETO DR 90272
- Application / Permit
- 19010-20000-06054
- Plan Check / Job No.
- B19VN22334
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 76.75' x 79'8" irregular shape 2-story w/1-level basement dwelling, sprinkler req'd throughout, interior 3-stop elevator and attached 2-car garage, patio cover/trellises
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | ALDOUS CHIC |
| Corrections Issued | 1/13/2020 | ALDOUS CHIC |
| Quality Review Completed | 1/14/2020 | ABDUL CHEGENI |
| Building Plans Picked Up | 1/15/2020 | APPLICANT |
| Green Plans Picked Up | 1/15/2020 | APPLICANT |
| Applicant returned to address corrections | 2/14/2020 | ALDOUS CHIC |
| Applicant returned to address corrections | 2/25/2020 | ALDOUS CHIC |
| Plan Check Approved | 3/5/2020 | ALDOUS CHIC |
| Issued | 3/6/2020 | LADBS |
| CofO in Progress | 10/20/2021 | JOHN KIDWELL |
| Permit Finaled | 11/24/2021 | RONALD MYRICK |
| CofO Issued | 11/24/2021 | RONALD MYRICK |
| Permit Finaled | 11/24/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/30/2019 | ALDOUS CHIC |
| Trees in Parkway | Cleared | 1/16/2020 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 2/4/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 2/4/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 2/4/2020 | GUILLERMO PETRA |
| Highway dedication | Cleared | 2/4/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 2/4/2020 | GEORGE SUCHAND |
| Permit | Cleared | 2/4/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 2/19/2020 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 2/21/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/21/2020 | THOMAS LANG |
| GPI Written Notices | Cleared | 2/25/2020 | ALDOUS CHIC |
| Green Code | Cleared | 2/25/2020 | MICHAEL AYERS |
| Disturb/Remove Protected Trees | Cleared | 3/2/2020 | STEPHEN DUPREY |
| Hold | Cleared | 4/22/2020 | JEREMY CORONEL |
Contact Information
| Contractor | Sky Remodeling Inc; Lic. No.: 955109-B | 12439 MAGNOLIA BLVD #245 VALLEY VILLAGE, CA 91607 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Tran,, Quang Tai; Lic. No.: C70929 | 355 N LANTANA ST 333 CAMARILLO, CA 93010 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/10/2020 | Approved | DANNY TOLENTINO |
| PLUMBING-Rough | 4/23/2020 | Partial Approval | DANNY TOLENTINO |
| Underground Mechanical | 4/23/2020 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 5/8/2020 | Partial Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 5/26/2020 | Partial Approval | ANDREW NAVE |
| Deputy Other (see comments) | 5/27/2020 | Conditional Approval | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 7/13/2020 | Partial Inspection | JOHN KIDWELL |
| Deputy Reinf. Concrete | 7/13/2020 | Approved | ROBERT SHELLY |
| Footing/Foundation/Slab | 7/13/2020 | Partial Inspection | JOHN KIDWELL |
| Green Building Rough | 7/13/2020 | Partial Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 7/13/2020 | Partial Inspection | JOHN KIDWELL |
| Deputy Reinf. Concrete | 7/17/2020 | Approved | ROBERT SHELLY |
| Deputy Steel/Welding | 7/27/2020 | Corrections Issued | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2020 | Corrections Issued | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2020 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 9/10/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 9/10/2020 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 9/15/2020 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 9/15/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/16/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/18/2020 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2020 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 10/8/2020 | Approved | JOHN KIDWELL |
| Structural Steel Frame | 10/8/2020 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/21/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 10/21/2020 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 10/21/2020 | Approved | JOHN KIDWELL |
| Drywall Nailing | 11/13/2020 | Approved | JOHN KIDWELL |
| Gas Test | 11/13/2020 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 11/13/2020 | Partial Approval | JOHN KIDWELL |
| Shower Pan | 11/13/2020 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 12/18/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pre-Inspection | 1/20/2021 | Partial Inspection | JOHN KIDWELL |
| Gas Test | 3/30/2021 | Partial Inspection | JUAN VALENZUELA |
| Gas Test | 5/24/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Gas Test | 6/1/2021 | Approved | JOHN KIDWELL |
| Service/Power Release | 6/17/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 6/30/2021 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 7/14/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 8/6/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 8/6/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 8/16/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Service/Power Release | 8/16/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 10/5/2021 | Approved | JOHN KIDWELL |
| Final | 10/14/2021 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/14/2021 | Approved | JOHN KIDWELL |
| Green Building Final | 10/14/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 10/14/2021 | Approved | JOHN KIDWELL |
| Final | 10/20/2021 | OK to Issue CofO | JOHN KIDWELL |