9375 N ILEX AVE 91352

Certificate Information: 9375 N ILEX AVE 91352

Application / Permit
19010-20000-06015
Plan Check / Job No.
B19VN22325
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 10/15/2024
Issuing Office
Metro
Current Status
Issued on 10/15/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 VIVIAN LAO
Corrections Issued 1/30/2020 GARO TELMI
Quality Review Completed 2/3/2020 KEN GILL
Building Plans Picked Up 2/6/2020 APPLICANT
Green Plans Picked Up 2/6/2020 APPLICANT
Applicant returned to address corrections 4/13/2023 GARO TELMI
Applicant returned to address corrections 11/3/2023 DANIEL YIP
Plan Check Approved 2/12/2024 DANIEL YIP
Issued 10/15/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/12/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/17/2020 MARKOS PEREZ-BRAN
Hydrant and Access approval Cleared 3/17/2020 ROBERT DUFF
Green Code Cleared 7/23/2020 AARON COSTA
Low Impact Development Cleared 8/10/2020 MITESH PATEL
Private sewage disp. approval Cleared 7/31/2023 DANIEL YIP
Roof/Waste drainage to street Cleared 12/7/2023 ADRIAN SANCHEZ
Clean Up Green Up Cleared 1/23/2024 JAZMIN ROQUE

Contact Information

Contractor Owner-Builder       ,
Engineer Esmaily-Radvar,, Shahrokh; Lic. No.: C66139 5 HODGENVILLE      IRVINE, CA 92620

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/24/2024 Corrections Issued MATTHEW NELSON
Pre-Inspection 12/26/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 12/30/2024 Corrections Issued MATTHEW NELSON
Special/Order Compliance 1/7/2025 Approved DAVID MATSON
Footing/Foundation/Slab 4/8/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 5/19/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 6/9/2025 Partial Approval MATTHEW NELSON
PLUMBING-Rough 6/9/2025 Partial Approval MATTHEW NELSON
Drywall Nailing 7/16/2025 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 7/16/2025 Approved MATTHEW NELSON
Green Building Rough 7/16/2025 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 7/16/2025 Not Ready for Inspection MATTHEW NELSON
Insulation 7/16/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 7/16/2025 Approved MATTHEW NELSON
Wood Frame 7/16/2025 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 7/24/2025 Partial Approval MATTHEW NELSON
Deputy Wood Construction 7/24/2025 Conditional Approval JUAN VALENZUELA
HVAC-Rough 7/24/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 8/6/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Final 8/6/2025 Approved MATTHEW NELSON
Green Building Rough 8/6/2025 Approved MATTHEW NELSON
HVAC-Rough 8/6/2025 Approved MATTHEW NELSON
PLUMBING-Rough 8/6/2025 Approved MATTHEW NELSON
Pre-Inspection 8/18/2025 Not Ready for Inspection MATTHEW NELSON
Shower Pan 8/29/2025 Approved MATTHEW NELSON
Underground Mechanical 9/15/2025 Partial Approval MATTHEW NELSON