3849 W DON TOMASO DR LOT #9 90008
Certificate Information: 3849 W DON TOMASO DR LOT #9 90008
- Application / Permit
- 19010-20000-06010
- Plan Check / Job No.
- B19VN22299
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SFD W/ ATTACHED GARAGE, BASMENT & ROOFTOP DECK (NFPA-13R FIRE SPRINKLERS THROUGHOUT) "Small lot subdivision pursuant to Tentative Tract Map No. VTT-82446-SK. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded."
- Permit Issued
- Issued on 12/28/2022
- Issuing Office
- Current Status
- CofO Issued on 4/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | ALYSSA N NARCISO |
| Green Plans Picked Up | 2/4/2020 | APPLICANT |
| Corrections Issued | 2/11/2020 | ALYSSA N NARCISO |
| Quality Review Completed | 2/12/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 2/14/2020 | APPLICANT |
| Applicant returned to address corrections | 5/6/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/6/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 9/29/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/13/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/25/2022 | NILOOFAR MEHRAIN |
| Issued | 12/28/2022 | APPLICANT |
| CofO in Progress | 4/13/2026 | BRENDAN MORELLI |
| Permit Finaled | 4/13/2026 | DEROLD HAUFF |
| CofO Issued | 4/13/2026 | DEROLD HAUFF |
| Permit Finaled | 4/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | RENZ SORIANO |
| Address approval | Cleared | 10/22/2020 | RENZ SORIANO |
| Permit | Cleared | 10/22/2020 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 12/18/2020 | MATTHEW CRAIG |
| Trees in Parkway | Cleared | 12/21/2020 | JOHN KIM |
| Low Impact Development | Cleared | 2/4/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 3/10/2021 | THOMAS LANG |
| Sewer availability | Cleared | 3/30/2021 | THOMAS LANG |
| Frnt yard landscape/Water mgmt | Cleared | 4/29/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 4/29/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 4/29/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 4/29/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 4/29/2021 | RICHARD REASER |
| Miscellaneous | Cleared | 4/29/2021 | RICHARD REASER |
| Tract Map conditions | Cleared | 4/29/2021 | RICHARD REASER |
| ZA Case | Cleared | 4/29/2021 | RICHARD REASER |
| ZA Case | Cleared | 4/29/2021 | RICHARD REASER |
| GPI Written Notices | Cleared | 6/8/2021 | ALYSSA N NARCISO |
| Grading Pre-Inspection | Cleared | 6/8/2021 | ALYSSA N NARCISO |
| Construction near power lines | Cleared | 7/26/2022 | TORI CHEN |
| Construction within easement | Cleared | 7/26/2022 | TORI CHEN |
| Miscellaneous | Cleared | 12/6/2022 | TERRY PHAN |
Contact Information
| Architect | Stockton,, Kenneth; Lic. No.: C19870 | 26500 W AGOURA RD. PMB # 844 CALABASAS, CA 91302 |
| Contractor | Duke Development Inc; Lic. No.: 947587-B | 127 N ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Freitas,, Richard Gomes; Lic. No.: C49072 | 240 COPA DE ORO DR BREA, CA 92823 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/6/2023 | Conditional Approval | BRENDAN MORELLI |
| Grounding or Bonding | 10/6/2023 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 10/6/2023 | Corrections Issued | BRENDAN MORELLI |
| Deputy Reinf. Concrete | 10/10/2023 | Conditional Approval | BRENDAN MORELLI |
| Reinforced Concrete Frame | 10/26/2023 | Corrections Issued | BRENDAN MORELLI |
| Reinforced Concrete Frame | 10/31/2023 | Partial Approval | BRENDAN MORELLI |
| Reinforced Concrete Frame | 11/17/2023 | Corrections Issued | BRENDAN MORELLI |
| Reinforced Masonry Frame | 11/27/2023 | Corrections Issued | BRENDAN MORELLI |
| Reinforced Masonry Frame | 12/14/2023 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 2/13/2024 | Partial Approval | BRENDAN MORELLI |
| Footing/Foundation/Slab | 2/23/2024 | Approved | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2024 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 3/14/2024 | Partial Approval | BRENDAN MORELLI |
| Wood Frame | 4/10/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 11/15/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Partial Approval | NICHOLAS LOPEZ |
| Drywall Nailing | 2/27/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Partial Approval | NICHOLAS LOPEZ |
| Drywall Nailing | 3/14/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 3/26/2025 | Partial Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | NICHOLAS LOPEZ |
| Deputy Wood Construction | 5/6/2025 | Conditional Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 5/30/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 5/30/2025 | Approved | NICHOLAS LOPEZ |
| Deputy Wood Construction | 6/3/2025 | Conditional Approval | BRENDAN MORELLI |
| Insulation | 6/10/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 6/10/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Shower Pan | 6/10/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 6/11/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 6/11/2025 | Partial Approval | NICHOLAS LOPEZ |
| Drywall Nailing | 6/17/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Drywall Nailing | 6/20/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 7/15/2025 | Approved | BRENDAN MORELLI |
| Special/Order Compliance | 10/20/2025 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Rough | 11/4/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 12/19/2025 | Approved | NICHOLAS LOPEZ |
| Service/Power Release | 1/8/2026 | Approved | BRENDAN MORELLI |
| HVAC-Final | 2/5/2026 | No Access for Inspection | BRENDAN MORELLI |
| PLUMBING-Final | 2/5/2026 | No Access for Inspection | BRENDAN MORELLI |
| HVAC-Final | 2/11/2026 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 2/11/2026 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/25/2026 | Approved | BRENDAN MORELLI |
| Final | 3/25/2026 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Final | 3/25/2026 | Approved | BRENDAN MORELLI |
| Green Building Rough | 3/25/2026 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 3/25/2026 | SGSOV No Gas | BRENDAN MORELLI |
| Smoke Detectors | 3/25/2026 | Approved | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 3/25/2026 | Approved | BRENDAN MORELLI |
| Final | 4/13/2026 | OK to Issue CofO | BRENDAN MORELLI |