3849 W DON TOMASO DR LOT #4 90008

Certificate Information: 3849 W DON TOMASO DR LOT #4 90008

Application / Permit
19010-20000-06005
Plan Check / Job No.
B19VN22299
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SFD W/ ATTACHED GARAGE, BASMENT & ROOFTOP DECK (NFPA-13R FIRE SPRINKLERS THROUGHOUT) "Small lot subdivision pursuant to Tentative Tract Map No. VTT-82446-SK. A certificate of occupancy (temporary or final) shall not be issued until after the final map has been recorded."
Permit Issued
Issued on 12/28/2022
Issuing Office
Current Status
CofO Issued on 4/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 ALYSSA N NARCISO
Green Plans Picked Up 2/4/2020 APPLICANT
Corrections Issued 2/11/2020 ALYSSA N NARCISO
Quality Review Completed 2/12/2020 CHON CHIO KUO
Building Plans Picked Up 2/14/2020 APPLICANT
Applicant returned to address corrections 5/6/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/6/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 9/29/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/13/2022 NILOOFAR MEHRAIN
Plan Check Approved 12/28/2022 NILOOFAR MEHRAIN
Issued 12/28/2022 APPLICANT
CofO in Progress 4/13/2026 BRENDAN MORELLI
Permit Finaled 4/13/2026 DEROLD HAUFF
CofO Issued 4/13/2026 DEROLD HAUFF
Permit Finaled 4/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/14/2020 RENZ SORIANO
Address approval Cleared 10/22/2020 RENZ SORIANO
Permit Cleared 10/22/2020 RENZ SORIANO
Trees in Parkway Cleared 12/14/2020 JOHN KIM
Hydrant and Access approval Cleared 12/18/2020 MATTHEW CRAIG
Low Impact Development Cleared 2/4/2021 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 3/10/2021 THOMAS LANG
Sewer availability Cleared 3/30/2021 THOMAS LANG
Frnt yard landscape/Water mgmt Cleared 4/29/2021 RICHARD REASER
Miscellaneous Cleared 4/29/2021 RICHARD REASER
Miscellaneous Cleared 4/29/2021 RICHARD REASER
Miscellaneous Cleared 4/29/2021 RICHARD REASER
Miscellaneous Cleared 4/29/2021 RICHARD REASER
Miscellaneous Cleared 4/29/2021 RICHARD REASER
Tract Map conditions Cleared 4/29/2021 RICHARD REASER
ZA Case Cleared 4/29/2021 RICHARD REASER
ZA Case Cleared 4/29/2021 RICHARD REASER
GPI Written Notices Cleared 6/8/2021 ALYSSA N NARCISO
Grading Pre-Inspection Cleared 6/8/2021 ALYSSA N NARCISO
Construction near power lines Cleared 7/26/2022 TORI CHEN
Construction within easement Cleared 7/26/2022 TORI CHEN
Miscellaneous Cleared 12/6/2022 TERRY PHAN

Contact Information

Architect Stockton,, Kenneth; Lic. No.: C19870 26500 W AGOURA RD. PMB # 844      CALABASAS, CA 91302
Contractor Duke Development Inc; Lic. No.: 947587-B 127 N ROBERTSON BLVD      BEVERLY HILLS, CA 90211
Engineer Cai,, Luo B; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Freitas,, Richard Gomes; Lic. No.: C49072 240 COPA DE ORO DR      BREA, CA 92823
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/20/2024 Not Ready for Inspection BRENDAN MORELLI
Deputy Reinf. Concrete 3/21/2024 No Access for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 3/21/2024 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 3/21/2024 Partial Approval JOSEPH MCGARRY
Reinforced Masonry Frame 4/10/2024 Partial Approval BRENDAN MORELLI
Underground Mechanical 5/8/2024 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 5/20/2024 Corrections Issued BRENDAN MORELLI
Grounding or Bonding 5/20/2024 Partial Approval BRENDAN MORELLI
Deputy Reinf. Concrete 5/22/2024 Conditional Approval BRENDAN MORELLI
Footing/Foundation/Slab 5/22/2024 Approved BRENDAN MORELLI
Deputy Wood Construction 6/17/2024 Conditional Approval WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Partial Approval SCOTT FINNILA
Drywall Nailing 6/26/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Not Ready for Inspection BRENDAN MORELLI
Reinforced Concrete Frame 7/8/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval BRENDAN MORELLI
Drywall Nailing 7/22/2024 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 8/2/2024 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Partial Approval SCOTT FINNILA
Drywall Nailing 8/6/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/21/2024 Partial Approval BRENDAN MORELLI
Drywall Nailing 8/23/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Corrections Issued ALIZAH MAYAGOITIA
Deputy Wood Construction 9/6/2024 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 10/21/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 11/4/2024 Not Ready for Inspection BRENDAN MORELLI
Deputy Wood Construction 11/25/2024 No Access for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 12/11/2024 Approved BRENDAN MORELLI
HVAC-Rough 12/11/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 12/11/2024 Conditional Approval BRENDAN MORELLI
Shower Pan 12/11/2024 Not Ready for Inspection BRENDAN MORELLI
BUILDING-Rough-Frame 12/16/2024 Conditional Approval NICHOLAS LOPEZ
Green Building Rough 12/19/2024 Approved NICHOLAS LOPEZ
HVAC-Rough 12/19/2024 Corrections Issued NICHOLAS LOPEZ
Verify Sprinkler Sign Off 12/19/2024 Partial Approval NICHOLAS LOPEZ
Insulation 12/31/2024 Corrections Issued NICHOLAS LOPEZ
HVAC-Rough 1/6/2025 Approved NICHOLAS LOPEZ
Insulation 1/6/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 1/10/2025 Approved BRENDAN MORELLI
Interior/Exterior Lathing 2/7/2025 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 2/11/2025 Approved NICHOLAS LOPEZ
Special/Order Compliance 10/20/2025 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 11/4/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 12/16/2025 Approved NICHOLAS LOPEZ
Service/Power Release 1/8/2026 Approved BRENDAN MORELLI
HVAC-Final 2/6/2026 Approved BRENDAN MORELLI
PLUMBING-Final 2/6/2026 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 3/24/2026 Approved BRENDAN MORELLI
Final 3/24/2026 Not Ready for Inspection BRENDAN MORELLI
Green Building Final 3/24/2026 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV No Gas BRENDAN MORELLI
Smoke Detectors 3/24/2026 Approved BRENDAN MORELLI
Verify Sprinkler Sign Off 3/24/2026 Approved BRENDAN MORELLI
Final 4/13/2026 OK to Issue CofO BRENDAN MORELLI