18031 W BULLOCK ST 91316
Certificate Information: 18031 W BULLOCK ST 91316
- Application / Permit
- 19010-20000-06002
- Plan Check / Job No.
- B19VN22309
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached Accessory Dwelling Unit.
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | ALBERT SERVIN |
| Corrections Issued | 1/14/2020 | ALBERT SERVIN |
| Quality Review Completed | 1/17/2020 | KEN GILL |
| Building Plans Picked Up | 1/23/2020 | APPLICANT |
| Green Plans Picked Up | 1/30/2020 | APPLICANT |
| Plan Check Approved | 2/5/2020 | ALBERT SERVIN |
| Plan Check Approved | 2/6/2020 | HAYATO TSUCHIYA |
| Issued | 2/6/2020 | LADBS |
| CofO in Progress | 2/12/2021 | STEVEN BACK |
| Permit Finaled | 2/17/2021 | DONALD SUNSERI |
| CofO Issued | 2/17/2021 | DONALD SUNSERI |
| Permit Finaled | 2/17/2021 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2020 | MARKOS PEREZ-BRAN |
| Hold | Cleared | 1/31/2020 | LOURDES RAMIRO |
| Low Impact Development | Cleared | 1/31/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/31/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/31/2020 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 2/3/2020 | GEORGE SUCHAND |
| Supp. Use District POD/CDO/TDO | Cleared | 2/3/2020 | VINCENT QUITORIANO |
| Green Code | Cleared | 2/4/2020 | DAVID MATSON |
Contact Information
| Contractor | Vision Construction; Lic. No.: 759147-B | 12740 CALIFA STREET VALLEY VILLAGE, CA 91607 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/6/2020 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 3/18/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/22/2020 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 5/22/2020 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 5/22/2020 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 5/22/2020 | Approved | STEVEN BACK |
| Sewer | 5/22/2020 | Approved | STEVEN BACK |
| Underground Mechanical | 5/22/2020 | Corrections Issued | STEVEN BACK |
| Verify Sprinkler Sign Off | 5/22/2020 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 5/27/2020 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 5/27/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 5/27/2020 | Corrections Issued | STEVEN BACK |
| Verify Sprinkler Sign Off | 5/27/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 6/3/2020 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 6/3/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/12/2020 | Approved | STEVEN BACK |
| Green Building Rough | 6/12/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 6/12/2020 | Approved | STEVEN BACK |
| Insulation | 6/22/2020 | Approved | STEVEN BACK |
| Shower Pan | 6/22/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 7/7/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/7/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 10/19/2020 | Corrections Issued | STEVEN BACK |
| Underground Mechanical | 10/19/2020 | Approved | STEVEN BACK |
| Final | 11/18/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 11/18/2020 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/18/2020 | SGSOV Not Ready | STEVEN BACK |
| Service/Power Release | 11/18/2020 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 11/18/2020 | Corrections Issued | STEVEN BACK |
| Final | 11/30/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 11/30/2020 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/30/2020 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 11/30/2020 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 11/30/2020 | Approved | STEVEN BACK |
| Final | 2/4/2021 | Not Ready for Inspection | STEVEN BACK |
| Service/Power Release | 2/4/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 2/12/2021 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 2/12/2021 | Approved | STEVEN BACK |