6059 N RIVERTON AVE 91606
Certificate Information: 6059 N RIVERTON AVE 91606
- Application / Permit
- 19010-20000-05999
- Plan Check / Job No.
- B19VN22301
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED ADU.
- Permit Issued
- Issued on 10/27/2020
- Issuing Office
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Green Plans Picked Up | 1/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | JOE VO |
| Corrections Issued | 2/3/2020 | JOE VO |
| Quality Review Completed | 2/5/2020 | KEN GILL |
| Applicant returned to address corrections | 6/1/2020 | JOE VO |
| Building Plans Picked Up | 6/4/2020 | APPLICANT |
| Plan Check Approved | 10/13/2020 | JOE VO |
| Issued | 10/27/2020 | APPLICANT |
| CofO in Progress | 2/3/2023 | JOHN HAYES |
| CofO Issued | 4/26/2023 | MICHAEL SMITH |
| Permit Finaled | 4/26/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 6/18/2020 | AARON COSTA |
| Low Impact Development | Cleared | 8/19/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/31/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/8/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/23/2020 | Partial Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 12/2/2020 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 12/16/2020 | Approved | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Partial Approval | DANIEL DREW |
| Green Building Rough | 2/22/2021 | Not Ready for Inspection | DANIEL DREW |
| Verify Sprinkler Sign Off | 2/22/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 5/6/2021 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 5/6/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Rough | 5/6/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 5/6/2021 | Not Ready for Inspection | DANIEL DREW |
| PLUMBING-Rough | 5/6/2021 | Approved | DANIEL DREW |
| Verify Sprinkler Sign Off | 5/6/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 6/14/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 7/15/2021 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 7/15/2021 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/26/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 8/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 8/26/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 8/26/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 9/16/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 9/24/2021 | Partial Approval | LILIANA PORTILLO |
| Green Building Rough | 9/24/2021 | Approved | LILIANA PORTILLO |
| Insulation | 9/24/2021 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 10/21/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 3/15/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 3/29/2022 | Corrections Issued | DAVID MATSON |
| BUILDING-Rough-Frame | 4/14/2022 | Approved | JACK KARGODORIAN |
| Final | 4/14/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/14/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Not Ready | JACK KARGODORIAN |
| Service/Power Release | 4/14/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 4/14/2022 | Approved | JACK KARGODORIAN |
| Final | 4/19/2022 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 4/19/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 1/18/2023 | No Access for Inspection | JOHN HAYES |
| Green Building Final | 1/18/2023 | No Access for Inspection | JOHN HAYES |
| Service/Power Release | 1/18/2023 | No Access for Inspection | JOHN HAYES |
| Final | 2/3/2023 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 2/3/2023 | Approved | JOHN HAYES |
| Service/Power Release | 2/3/2023 | Approved | JOHN HAYES |