1759 N GOWER ST 1-28 90028
Certificate Information: 1759 N GOWER ST 1-28 90028
- Application / Permit
- 19010-20000-05995
- Plan Check / Job No.
- B19VN22295
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 142'1-1/2" X 80'7", 4-STORY, 28-UNIT APARTMENT (TYPE III B CONSTRUCTION ) OVER BASEMENT PARKING GARAGE (TYPE IA ) ; NFPA-13 FIRE SPRINKLERS REQ'D THROUGH-OUT. ( TOC, TIER 3 INCLUDING 3 EXTREME LOW INCOME UNITS, ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | RARES BODEA |
| Corrections Issued | 1/30/2020 | RARES BODEA |
| Quality Review Completed | 2/6/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/7/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 2/7/2020 | APPLICANT |
| Green Plans Picked Up | 2/7/2020 | APPLICANT |
| Applicant returned to address corrections | 10/5/2020 | RARES BODEA |
| Applicant returned to address corrections | 3/14/2022 | RARES BODEA |
| Plan Check Approved | 3/18/2022 | RARES BODEA |
| No Progress | 3/24/2022 | RARES BODEA |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 2/22/2024 | GREGORY POMISH |
| Permit Finaled | 3/5/2024 | ADAM BURGESS |
| CofO Issued | 3/5/2024 | ADAM BURGESS |
| Permit Finaled | 3/5/2024 | ADAM BURGESS |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2020 | CECILIO NAVARRO |
| Hydrant and Access approval | Cleared | 11/5/2020 | MATTHEW CRAIG |
| Fire Marshall Fire Life Safety | Cleared | 3/12/2021 | VIDAL GARCIA |
| Green Code | Cleared | 3/23/2021 | MICHAEL AYERS |
| DAS Clearance | Cleared | 4/1/2021 | RARES BODEA |
| Low Impact Development | Cleared | 9/21/2021 | ORVAL HERNANDEZ-MARCI |
| Density Bonus 12.22.A.31 | Cleared | 10/12/2021 | LOUIE MILLER |
| Trees in Parkway | Cleared | 10/12/2021 | ADALBERTO VERA |
| Highway dedication | Cleared | 10/27/2021 | CHRISTOPHER ROCHA |
| Permit | Cleared | 10/27/2021 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 10/29/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 11/3/2021 | CHRISTOPHER ROCHA |
| "Q" conditions | Cleared | 11/24/2021 | PABLO ESTRADA |
| Frnt yard landscape/Water mgmt | Cleared | 11/24/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 11/24/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 11/24/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 11/24/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 11/24/2021 | PABLO ESTRADA |
| Miscellaneous | Cleared | 11/24/2021 | PABLO ESTRADA |
| Opn space landscape/Water mgmt | Cleared | 11/24/2021 | PABLO ESTRADA |
| Redevelopment Project Area | Cleared | 11/24/2021 | PABLO ESTRADA |
| ZI | Cleared | 11/24/2021 | PABLO ESTRADA |
| ZI | Cleared | 11/24/2021 | PABLO ESTRADA |
| Work Adjacent to Public Way | Cleared | 2/14/2022 | ARMEN SARKISIAN |
| Grading Pre-Inspection | Cleared | 2/18/2022 | PATRICK MISCHLICH |
| Building over 3-story or 36-ft | Cleared | 3/14/2022 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 3/14/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/5/2022 | RARES BODEA |
Contact Information
| Architect | Albert,, Stephen M; Lic. No.: C9412 | 2032 STONER AVE LOS ANGELES, CA 90025 |
| Contractor | Summerland Partners Inc; Lic. No.: 865002-B | 23622 CALABASAS ROAD SUITE 121 CALABASAS, CA 91302 |
| Engineer | Fischer,, Kurt Mark; Lic. No.: S5432 | PO BOX 809 POWAY, CA 92074 |
| Engineer | Hoffmayer,, Joseph Julian; Lic. No.: S3935 | 5043 EVANWOOD AVENUE OAK PARK, CA 91377 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
| Engineer | Wilson,, Lawrence Craig; Lic. No.: L6712 | 1406 E MARYMONT CIRCLE FLAGSTAFF, AZ 86004 |
| Engineer | Zweigler,, Robert Ingraham; Lic. No.: GE2120 | 1461 E. CHEVY CHASE DR. #200 GLENDALE, CA 91206 |
| Geologist | Hoek,, Johan; Lic. No.: EG2544 | 3333 VILLA GROVE DR ALTADENA, CA 91001 |
| Geologist | Zweigler,, Robert Ingraham; Lic. No.: EG1210 | 196 DIRT ROAD THOUSAND OAKS, CA 91361 |
Inspector Information
| DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/27/2022 | Approved | DAVID BURKHEAD |
| Footing/Foundation/Slab | 6/29/2022 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 7/26/2022 | Partial Approval | DAVID BURKHEAD |
| Footing/Foundation/Slab | 8/4/2022 | Partial Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 8/8/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Reinf. Concrete | 8/17/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 8/17/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Reinf. Concrete | 8/18/2022 | Approved | DAVID BURKHEAD |
| Deputy Shotcrete | 8/18/2022 | Approved | DAVID BURKHEAD |
| Green Building Rough | 8/18/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Reinforced Concrete Frame | 8/18/2022 | Partial Approval | DAVID BURKHEAD |
| Verify Sprinkler Sign Off | 8/18/2022 | Not Ready for Inspection | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 8/19/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 8/19/2022 | Conditional Approval | ERNESTO CORRAL |
| Deputy Shotcrete | 8/22/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Shotcrete | 8/23/2022 | Conditional Approval | WINSTON DUNNING |
| Green Building Rough | 8/23/2022 | Partial Approval | TED RIES |
| Reinforced Concrete Frame | 8/23/2022 | Partial Approval | TED RIES |
| Verify Sprinkler Sign Off | 8/23/2022 | Not Ready for Inspection | TED RIES |
| Deputy Shotcrete | 8/24/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Reinf. Concrete | 8/25/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Reinf. Concrete | 8/26/2022 | Conditional Approval | WINSTON DUNNING |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Partial Inspection | GREGORY POMISH |
| Green Building Rough | 10/8/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 10/8/2022 | Partial Approval | EDWIN GREGORYONA |
| Verify Sprinkler Sign Off | 10/8/2022 | Not Ready for Inspection | EDWIN GREGORYONA |
| Deputy Wood Construction | 11/3/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2022 | Partial Inspection | DAVID BURKHEAD |
| Deputy Wood Construction | 11/22/2022 | Approved | DAVID BURKHEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Approval | DAVID BURKHEAD |
| Deputy Wood Construction | 12/9/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Partial Approval | DAVID BURKHEAD |
| Deputy Wood Construction | 12/16/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Partial Approval | GREGORY POMISH |
| Deputy Wood Construction | 1/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 1/26/2023 | Partial Approval | GREGORY POMISH |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2023 | Partial Approval | GREGORY POMISH |
| Deputy Wood Construction | 4/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Wood Frame | 4/17/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 4/20/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 5/3/2023 | Partial Inspection | GREGORY POMISH |
| Insulation | 5/4/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 5/15/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 5/17/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 5/30/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 6/6/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 7/17/2023 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 8/2/2023 | Partial Inspection | GREGORY POMISH |
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Partial Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 11/6/2023 | Partial Inspection | GREGORY POMISH |
| Final | 1/16/2024 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 1/16/2024 | Approved | GREGORY POMISH |
| Green Building Final | 1/16/2024 | Approved | GREGORY POMISH |
| Green Building Rough | 1/16/2024 | Approved | GREGORY POMISH |
| Reinforced Concrete Frame | 1/16/2024 | Approved | GREGORY POMISH |
| Reinforced Masonry Frame | 1/16/2024 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Approved | GREGORY POMISH |
| Smoke Detectors | 1/16/2024 | Partial Inspection | GREGORY POMISH |
| Verify Sprinkler Sign Off | 1/16/2024 | Approved | GREGORY POMISH |
| Final | 2/14/2024 | OK to Issue CofO | GREGORY POMISH |
| Smoke Detectors | 2/14/2024 | Approved | GREGORY POMISH |