1759 N GOWER ST 1-28 90028

Certificate Information: 1759 N GOWER ST 1-28 90028

Application / Permit
19010-20000-05995
Plan Check / Job No.
B19VN22295
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 142'1-1/2" X 80'7", 4-STORY, 28-UNIT APARTMENT (TYPE III B CONSTRUCTION ) OVER BASEMENT PARKING GARAGE (TYPE IA ) ; NFPA-13 FIRE SPRINKLERS REQ'D THROUGH-OUT. ( TOC, TIER 3 INCLUDING 3 EXTREME LOW INCOME UNITS, ALL WORK PER ENGINEERING - SEE COMMENTS
Permit Issued
Issued on 4/21/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 RARES BODEA
Corrections Issued 1/30/2020 RARES BODEA
Quality Review Completed 2/6/2020 GUANG MIN TUNG
Building Plans Picked Up 2/7/2020 APPLICANT
Disabled Access Plans Picked Up 2/7/2020 APPLICANT
Green Plans Picked Up 2/7/2020 APPLICANT
Applicant returned to address corrections 10/5/2020 RARES BODEA
Applicant returned to address corrections 3/14/2022 RARES BODEA
Plan Check Approved 3/18/2022 RARES BODEA
No Progress 3/24/2022 RARES BODEA
Issued 4/21/2022 APPLICANT
CofO in Progress 2/22/2024 GREGORY POMISH
Permit Finaled 3/5/2024 ADAM BURGESS
CofO Issued 3/5/2024 ADAM BURGESS
Permit Finaled 3/5/2024 ADAM BURGESS

Permit Application Clearance Information

Address approval Cleared 5/27/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 5/27/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 11/5/2020 MATTHEW CRAIG
Fire Marshall Fire Life Safety Cleared 3/12/2021 VIDAL GARCIA
Green Code Cleared 3/23/2021 MICHAEL AYERS
DAS Clearance Cleared 4/1/2021 RARES BODEA
Low Impact Development Cleared 9/21/2021 ORVAL HERNANDEZ-MARCI
Density Bonus 12.22.A.31 Cleared 10/12/2021 LOUIE MILLER
Trees in Parkway Cleared 10/12/2021 ADALBERTO VERA
Highway dedication Cleared 10/27/2021 CHRISTOPHER ROCHA
Permit Cleared 10/27/2021 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 10/29/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 11/3/2021 CHRISTOPHER ROCHA
"Q" conditions Cleared 11/24/2021 PABLO ESTRADA
Frnt yard landscape/Water mgmt Cleared 11/24/2021 PABLO ESTRADA
Miscellaneous Cleared 11/24/2021 PABLO ESTRADA
Miscellaneous Cleared 11/24/2021 PABLO ESTRADA
Miscellaneous Cleared 11/24/2021 PABLO ESTRADA
Miscellaneous Cleared 11/24/2021 PABLO ESTRADA
Miscellaneous Cleared 11/24/2021 PABLO ESTRADA
Opn space landscape/Water mgmt Cleared 11/24/2021 PABLO ESTRADA
Redevelopment Project Area Cleared 11/24/2021 PABLO ESTRADA
ZI Cleared 11/24/2021 PABLO ESTRADA
ZI Cleared 11/24/2021 PABLO ESTRADA
Work Adjacent to Public Way Cleared 2/14/2022 ARMEN SARKISIAN
Grading Pre-Inspection Cleared 2/18/2022 PATRICK MISCHLICH
Building over 3-story or 36-ft Cleared 3/14/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/14/2022 CALOSHA APPROVED
GPI Written Notices Cleared 4/5/2022 RARES BODEA

Contact Information

Architect Albert,, Stephen M; Lic. No.: C9412 2032 STONER AVE      LOS ANGELES, CA 90025
Contractor Summerland Partners Inc; Lic. No.: 865002-B 23622 CALABASAS ROAD SUITE 121      CALABASAS, CA 91302
Engineer Fischer,, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074
Engineer Hoffmayer,, Joseph Julian; Lic. No.: S3935 5043 EVANWOOD AVENUE      OAK PARK, CA 91377
Engineer Walter,, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401
Engineer Wilson,, Lawrence Craig; Lic. No.: L6712 1406 E MARYMONT CIRCLE      FLAGSTAFF, AZ 86004
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Geologist Hoek,, Johan; Lic. No.: EG2544 3333 VILLA GROVE DR      ALTADENA, CA 91001
Geologist Zweigler,, Robert Ingraham; Lic. No.: EG1210 196 DIRT ROAD      THOUSAND OAKS, CA 91361

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/27/2022 Approved DAVID BURKHEAD
Footing/Foundation/Slab 6/29/2022 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 7/26/2022 Partial Approval DAVID BURKHEAD
Footing/Foundation/Slab 8/4/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 8/8/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 8/17/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 8/17/2022 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 8/18/2022 Approved DAVID BURKHEAD
Deputy Shotcrete 8/18/2022 Approved DAVID BURKHEAD
Green Building Rough 8/18/2022 Not Ready for Inspection DAVID BURKHEAD
Reinforced Concrete Frame 8/18/2022 Partial Approval DAVID BURKHEAD
Verify Sprinkler Sign Off 8/18/2022 Not Ready for Inspection DAVID BURKHEAD
Deputy Reinf. Concrete 8/19/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 8/19/2022 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 8/22/2022 Conditional Approval WINSTON DUNNING
Deputy Shotcrete 8/23/2022 Conditional Approval WINSTON DUNNING
Green Building Rough 8/23/2022 Partial Approval TED RIES
Reinforced Concrete Frame 8/23/2022 Partial Approval TED RIES
Verify Sprinkler Sign Off 8/23/2022 Not Ready for Inspection TED RIES
Deputy Shotcrete 8/24/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 8/25/2022 Conditional Approval WINSTON DUNNING
Deputy Reinf. Concrete 8/26/2022 Conditional Approval WINSTON DUNNING
Excavation/Setback/Form/Re-Bar 9/7/2022 Partial Inspection GREGORY POMISH
Green Building Rough 10/8/2022 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 10/8/2022 Partial Approval EDWIN GREGORYONA
Verify Sprinkler Sign Off 10/8/2022 Not Ready for Inspection EDWIN GREGORYONA
Deputy Wood Construction 11/3/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/4/2022 Partial Inspection DAVID BURKHEAD
Deputy Wood Construction 11/22/2022 Approved DAVID BURKHEAD
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 12/9/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Partial Approval DAVID BURKHEAD
Deputy Wood Construction 12/16/2022 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/4/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 1/9/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 1/11/2023 Partial Approval GREGORY POMISH
Drywall Nailing 1/26/2023 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Partial Approval GREGORY POMISH
Deputy Wood Construction 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Wood Frame 4/17/2023 Partial Approval GREGORY POMISH
Drywall Nailing 4/20/2023 Partial Approval GREGORY POMISH
Drywall Nailing 5/3/2023 Partial Inspection GREGORY POMISH
Insulation 5/4/2023 Partial Approval GREGORY POMISH
Drywall Nailing 5/15/2023 Partial Approval GREGORY POMISH
Drywall Nailing 5/17/2023 Partial Approval GREGORY POMISH
Drywall Nailing 5/30/2023 Partial Approval GREGORY POMISH
Drywall Nailing 6/6/2023 Partial Approval GREGORY POMISH
Drywall Nailing 7/17/2023 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 8/2/2023 Partial Inspection GREGORY POMISH
Excavation/Setback/Form/Re-Bar 9/6/2023 Partial Approval GREGORY POMISH
Footing/Foundation/Slab 11/6/2023 Partial Inspection GREGORY POMISH
Final 1/16/2024 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 1/16/2024 Approved GREGORY POMISH
Green Building Final 1/16/2024 Approved GREGORY POMISH
Green Building Rough 1/16/2024 Approved GREGORY POMISH
Reinforced Concrete Frame 1/16/2024 Approved GREGORY POMISH
Reinforced Masonry Frame 1/16/2024 Approved GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Approved GREGORY POMISH
Smoke Detectors 1/16/2024 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 1/16/2024 Approved GREGORY POMISH
Final 2/14/2024 OK to Issue CofO GREGORY POMISH
Smoke Detectors 2/14/2024 Approved GREGORY POMISH