2131 S RIMPAU BLVD 90016

Certificate Information: 2131 S RIMPAU BLVD 90016

Application / Permit
19010-20000-05989
Plan Check / Job No.
B19VN22281
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 3-STORY SFD WITH ATT. AGARAGE (bldng #1) <SPRINKLERS REQ'D THROUGHOUT>
Permit Issued
Issued on 11/18/2020
Issuing Office
Current Status
CofO Issued on 6/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 ABDUL CHEGENI
Corrections Issued 1/6/2020 ABDUL CHEGENI
Quality Review Completed 1/7/2020 STEVEN KIM
Building Plans Picked Up 1/8/2020 APPLICANT
Green Plans Picked Up 1/8/2020 APPLICANT
Applicant returned to address corrections 7/29/2020 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/16/2020 MOHAMMAD ESMAILI
Plan Check Approved 11/6/2020 MOHAMMAD ESMAILI
Issued 11/18/2020 APPLICANT
CofO in Progress 5/6/2022 STUART CHAPMAN
Permit Finaled 6/1/2022 DEROLD HAUFF
CofO Issued 6/1/2022 DEROLD HAUFF
Permit Finaled 6/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 4/3/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 5/4/2020 MATTHEW CRAIG
Low Impact Development Cleared 6/10/2020 ORVAL HERNANDEZ-MARCIAL
Address approval Cleared 7/10/2020 EMIL KYUPELYAN
Highway dedication Cleared 7/10/2020 EMIL KYUPELYAN
Permit Cleared 7/10/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 7/16/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 7/16/2020 EMIL KYUPELYAN
Sewer availability Cleared 7/16/2020 EMIL KYUPELYAN
Miscellaneous Cleared 11/6/2020 ABDUL CHEGENI

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 26851 GRAYSLAKE ROAD      RANCHO PALOS VERDES, CA 90275

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/21/2021 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 2/8/2021 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 4/16/2021 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 5/18/2021 Corrections Issued STUART CHAPMAN
Deputy Reinf. Concrete 5/26/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 6/18/2021 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 8/23/2021 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 10/12/2021 Approved STUART CHAPMAN
Final 10/12/2021 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Approved STUART CHAPMAN
HVAC-Rough 10/12/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 10/12/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/18/2021 Approved STUART CHAPMAN
Green Building Rough 10/18/2021 Approved STUART CHAPMAN
Insulation 10/18/2021 Approved STUART CHAPMAN
MERV13>=Rough 10/18/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 10/18/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 10/19/2021 Partial Approval STUART CHAPMAN
Drywall Nailing 10/26/2021 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 10/26/2021 Approved STUART CHAPMAN
Drywall Nailing 10/29/2021 Approved STUART CHAPMAN
Special/Order Compliance 12/16/2021 Approved STUART CHAPMAN
Special/Order Compliance 2/3/2022 Approved MICHAEL LEWIS
ELECTRICAL-Final 3/10/2022 Corrections Issued STUART CHAPMAN
Final 3/10/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 3/10/2022 Approved STUART CHAPMAN
Green Building Final 3/10/2022 Approved STUART CHAPMAN
HVAC-Final 3/10/2022 Corrections Issued STUART CHAPMAN
MERV13>=Final 3/10/2022 Approved STUART CHAPMAN
PLUMBING-Final 3/10/2022 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 3/10/2022 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 3/10/2022 Approved STUART CHAPMAN
Final 3/14/2022 Corrections Issued STUART CHAPMAN
Service/Power Release 3/14/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 3/29/2022 Approved STUART CHAPMAN
Final 3/29/2022 Corrections Issued STUART CHAPMAN
Service/Power Release 3/29/2022 Not Ready for Inspection STUART CHAPMAN
Final 4/15/2022 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 4/15/2022 Not Ready for Inspection STUART CHAPMAN
Final 5/2/2022 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 5/2/2022 Not Ready for Inspection STUART CHAPMAN
Final 5/5/2022 Partial Approval STUART CHAPMAN
Service/Power Release 5/5/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 5/6/2022 Approved STUART CHAPMAN
Final 5/6/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 5/6/2022 Approved STUART CHAPMAN
PLUMBING-Final 5/6/2022 Approved STUART CHAPMAN