4203 N SAUGUS AVE 91403
Certificate Information: 4203 N SAUGUS AVE 91403
- Application / Permit
- 19010-20000-05981
- Plan Check / Job No.
- B19VN22274
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODE TO ADD 45' X 88' TO (E) SINGLE FAMILY DWELLING, ADD (N) 21' X 19'-6" ATTACHED GARAGE AND CREATE 40' X 25'-7" 2ND-STORY ADDITION. SPRINKLER REQUIRED NFPA-13D.
- Permit Issued
- Issued on 7/31/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | SERGIO MUNIZ |
| Corrections Issued | 1/24/2020 | SERGIO MUNIZ |
| Quality Review Completed | 1/27/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 1/28/2020 | APPLICANT |
| Green Plans Picked Up | 2/3/2020 | APPLICANT |
| Applicant returned to address corrections | 4/15/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/2/2020 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/24/2020 | SERGIO MUNIZ |
| Plan Check Approved | 7/29/2020 | SERGIO MUNIZ |
| Issued | 7/31/2020 | APPLICANT |
| CofO in Progress | 11/1/2021 | VINCENT HANLEY |
| CofO Issued | 12/9/2021 | MICHAEL SMITH |
| Permit Finaled | 12/9/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 4/9/2020 | MICHAEL AYERS |
| BHO/Hillside ordinance | Cleared | 6/2/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 6/2/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 6/2/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 6/2/2020 | LEE GUILBEAUX |
| Permit | Cleared | 6/2/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/4/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 6/4/2020 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 6/11/2020 | JOHN KIM |
| Low Impact Development | Cleared | 6/17/2020 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 6/22/2020 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 6/23/2020 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 7/2/2020 | SERGIO MUNIZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vahdat,, Shahram; Lic. No.: C47934 | 4333 EMPRESS AVE ENCINO, CA 91436 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2021 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 2/4/2021 | Approved | CHARLES POWELL |
| Wood Frame | 2/4/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 4/5/2021 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 4/14/2021 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2021 | Partial Approval | CHARLES POWELL |
| ELECTRICAL-Rough | 4/16/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 6/2/2021 | Approved | MARK JOHNSON |
| Green Building Rough | 6/2/2021 | Approved | MARK JOHNSON |
| HVAC-Rough | 6/2/2021 | Approved | MARK JOHNSON |
| MERV13>=Rough | 6/2/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 6/2/2021 | Approved | MARK JOHNSON |
| Verify Sprinkler Sign Off | 6/2/2021 | Approved | MARK JOHNSON |
| Shower Pan | 6/8/2021 | Approved | CHARLES POWELL |
| Insulation | 6/10/2021 | Approved | CHARLES POWELL |
| Drywall Nailing | 6/17/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/17/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 6/25/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 7/2/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 9/22/2021 | Conditional Approval | MISAEL ESPARZA |
| HVAC-Final | 9/27/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 9/29/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 9/29/2021 | Approved | MISAEL ESPARZA |
| Final | 10/25/2021 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 10/25/2021 | Approved | JACK KARGODORIAN |
| MERV13>=Final | 10/25/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/25/2021 | SGSOV Approved | JACK KARGODORIAN |
| SUSMP-Std. Urban Storm Water | 10/25/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 10/25/2021 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/29/2021 | Approved | VINCENT HANLEY |
| Final | 10/29/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Final | 11/1/2021 | OK to Issue CofO | VINCENT HANLEY |
| SUSMP-Std. Urban Storm Water | 11/1/2021 | Approved | VINCENT HANLEY |
| Service/Power Release | 11/1/2021 | Approved | VINCENT HANLEY |