1437 S WESTMORELAND AVE 90006

Certificate Information: 1437 S WESTMORELAND AVE 90006

Application / Permit
19010-20000-05978
Plan Check / Job No.
B19VN22268
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW(19'-0"x 33'-9") 3-STORY SINGLE FAMILY DWELLING WITH ATT GARAGE, NFPA-13D FIRE SRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 9/8/2020
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 TROY DEGUZMAN
Corrections Issued 1/12/2020 TROY DEGUZMAN
Quality Review Completed 1/29/2020 CHON CHIO KUO
Building Plans Picked Up 1/29/2020 APPLICANT
Green Plans Picked Up 1/29/2020 APPLICANT
Applicant returned to address corrections 8/24/2020 TROY DEGUZMAN
Applicant returned to address corrections 9/1/2020 TROY DEGUZMAN
Plan Check Approved 9/8/2020 TROY DEGUZMAN
Issued 9/8/2020 APPLICANT
CofO in Progress 4/19/2022 KATHRYN BUTTERWORTH
Permit Finaled 4/28/2022 DEROLD HAUFF
CofO Issued 4/28/2022 DEROLD HAUFF
Permit Finaled 4/28/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/30/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/30/2020 JEANETTE VONG
Highway dedication Cleared 1/30/2020 JEANETTE VONG
Sewer availability Cleared 1/30/2020 JEANETTE VONG
Green Code Cleared 3/5/2020 MICHAEL AYERS
Frnt yard landscape/Water mgmt Cleared 4/2/2020 DANIEL CORONADO
Hydrant and Access approval Cleared 4/2/2020 ROBERT DUFF
Low Impact Development Cleared 5/28/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 7/17/2020 THOMAS LANG

Contact Information

Contractor Moreno Chris; Lic. No.: 973501-B 1158 W 126TH STREET      LOS ANGELES, CA 90044
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 26851 GRAYSLAKE ROAD      RANCHO PALOS VERDES, CA 90275

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/2/2021 No Access for Inspection KATHRYN BUTTERWORTH
Underground Mechanical 3/17/2021 Partial Inspection ROBERT VORHIS
Footing/Foundation/Slab 3/26/2021 Approved KATHRYN BUTTERWORTH
Deputy Reinf. Concrete 3/30/2021 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/26/2021 Partial Inspection OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/16/2021 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 7/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 7/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 7/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 7/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 7/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/23/2021 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/23/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 7/23/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 7/23/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 7/23/2021 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 7/23/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 7/27/2021 Approved KATHRYN BUTTERWORTH
Green Building Rough 7/27/2021 Approved KATHRYN BUTTERWORTH
HVAC-Rough 7/27/2021 Approved KATHRYN BUTTERWORTH
Insulation 8/2/2021 Approved JESUS PINEDA
Drywall Nailing 8/9/2021 Conditional Approval CALEB MEISTER
Interior/Exterior Lathing 8/11/2021 No Access for Inspection KATHRYN BUTTERWORTH
Interior/Exterior Lathing 8/16/2021 Partial Approval KATHRYN BUTTERWORTH
Sewer 10/4/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Not Ready KATHRYN BUTTERWORTH
ELECTRICAL-Final 3/24/2022 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Final 3/24/2022 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Final 3/24/2022 Approved KATHRYN BUTTERWORTH
Drywall Nailing 3/30/2022 Approved KATHRYN BUTTERWORTH
Green Building Final 3/30/2022 Approved KATHRYN BUTTERWORTH
HVAC-Final 3/30/2022 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 3/30/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 3/30/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 4/1/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 4/1/2022 Corrections Issued KATHRYN BUTTERWORTH
Service/Power Release 4/1/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 4/13/2022 OK to Issue CofO KATHRYN BUTTERWORTH
Service/Power Release 4/13/2022 Approved KATHRYN BUTTERWORTH