10035 S WESTERN AVE #1-8 90047

Certificate Information: 10035 S WESTERN AVE #1-8 90047

Application / Permit
19010-20000-05939
Plan Check / Job No.
B19VN22218
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 3-STORY TYPE V-A 8-UNIT APARTMENT BUILDING OVER TYPE I-A PARKING GARAGE (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 8/10/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 NILOOFAR MEHRAIN
Green Plans Picked Up 1/29/2020 APPLICANT
Corrections Issued 2/5/2020 NILOOFAR MEHRAIN
Quality Review Completed 2/5/2020 GUANG MIN TUNG
Building Plans Picked Up 2/6/2020 APPLICANT
Disabled Access Plans Picked Up 2/6/2020 APPLICANT
Applicant returned to address corrections 7/31/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/12/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/4/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 11/9/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 2/11/2022 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/31/2022 NILOOFAR MEHRAIN
Plan Check Approved 7/12/2022 JON BLAINE
Issued 8/10/2022 APPLICANT
CofO in Progress 9/4/2025 JAMES POWERS
Permit Finaled 9/5/2025 ERNESTO CORRAL
CofO Issued 9/5/2025 ERNESTO CORRAL
Permit Finaled 9/5/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/5/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/5/2020 GUILLERMO PETRA
Community Plan Implem. Overlay Cleared 3/6/2020 THOMAS LANG
Highway dedication Cleared 3/6/2020 THOMAS LANG
Permit Cleared 3/6/2020 THOMAS LANG
Green Code Cleared 4/22/2020 MICHAEL AYERS
Building over 3-story or 36-ft Cleared 7/31/2020 CALOSHA APPROVED
Hydrant and Access approval Cleared 10/8/2020 MATTHEW CRAIG
Low Impact Development Cleared 10/23/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 11/12/2020 THOMAS LANG
Frnt yard landscape/Water mgmt Cleared 12/16/2020 RICHARD REASER
Opn space landscape/Water mgmt Cleared 12/16/2020 RICHARD REASER
Trees in Parkway Cleared 1/7/2021 JOHN KIM
Fire Marshall Fire Life Safety Cleared 1/15/2021 PEJMAN NOORI
Community Plan Implem. Overlay Cleared 1/28/2021 HELEN JADALI
ZI Cleared 1/28/2021 HELEN JADALI
Sewer availability Cleared 8/3/2021 JEANIE LAM
Bicycle Parking Cleared 10/13/2021 JEREMY CHOK
DAS Clearance Cleared 5/11/2022 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,
Engineer Husain,, Shahzain; Lic. No.: C62744 1843 MONTGOMERY RD      THOUSAND OAKS, CA 91360

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/7/2022 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 12/13/2022 Not Ready for Inspection JAMES POWERS
Pre-Inspection 12/13/2022 Approved JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/28/2022 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/28/2022 Partial Approval JAMES POWERS
METHANE-Barrier 12/28/2022 Approved JAMES POWERS
METHANE-Subgrade 12/28/2022 Approved JAMES POWERS
Deputy Reinf. Concrete 1/3/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 2/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/9/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 2/16/2023 Partial Approval JAMES POWERS
METHANE-Rough 2/16/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/16/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/16/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 2/22/2023 Partial Approval JAMES POWERS
Green Building Rough 2/22/2023 Not Ready for Inspection JAMES POWERS
METHANE-Rough 2/22/2023 Approved JAMES POWERS
Reinforced Concrete Frame 2/22/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/22/2023 Not Ready for Inspection JAMES POWERS
Green Building Rough 3/17/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/17/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/17/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 3/23/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 3/30/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/30/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/30/2023 Not Ready for Inspection JAMES POWERS
Green Building Rough 4/19/2023 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 4/19/2023 Partial Approval GREGORY POMISH
Verify Sprinkler Sign Off 4/19/2023 Not Ready for Inspection GREGORY POMISH
Deputy Reinf. Concrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 6/13/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 6/13/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/14/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/14/2023 Partial Approval JAMES POWERS
Green Building Rough 8/4/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/4/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 8/4/2023 Not Ready for Inspection JAMES POWERS
Wall Anchors 8/4/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/8/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/9/2023 Partial Approval JAMES POWERS
Green Building Rough 8/14/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/14/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 8/14/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 8/22/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/22/2023 Partial Approval JAMES POWERS
Insulation 2/27/2024 Partial Approval JAMES POWERS
Green Building Rough 5/10/2024 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/10/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 5/10/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/28/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/21/2024 Approved JAMES POWERS
Green Building Rough 6/28/2024 Approved JAMES POWERS
Light Gage Steel Frame 6/28/2024 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 6/28/2024 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 7/15/2024 Partial Approval JAMES POWERS
Insulation 10/9/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/15/2024 Partial Approval LARRY ARNICK
Drywall Nailing 10/23/2024 Partial Approval LARRY ARNICK
Insulation 11/20/2024 Approved JAMES POWERS
Deputy Drilled-In Anchors 12/11/2024 Partial Approval JAMES POWERS
Pre-Inspection 2/4/2025 Partial Approval JAMES POWERS
Final 4/24/2025 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 4/24/2025 Not Ready for Inspection LARRY ARNICK
Green Building Final 4/24/2025 Not Ready for Inspection LARRY ARNICK
Pre-Inspection 4/24/2025 Partial Inspection LARRY ARNICK
Reinforced Concrete Frame 4/24/2025 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 4/24/2025 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 4/24/2025 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 4/24/2025 Not Ready for Inspection LARRY ARNICK
Wood Frame 4/24/2025 Not Ready for Inspection LARRY ARNICK
Final 7/1/2025 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/1/2025 Approved JAMES POWERS
Green Building Final 7/1/2025 Approved JAMES POWERS
Reinforced Concrete Frame 7/1/2025 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/1/2025 SGSOV Approved JAMES POWERS
Smoke Detectors 7/1/2025 Approved JAMES POWERS
Verify Rec and Parks Fee Memo 7/1/2025 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 7/1/2025 Approved JAMES POWERS
Wood Frame 7/1/2025 Approved JAMES POWERS
Final 7/29/2025 Corrections Issued DARRYL ARNOLD
Verify Rec and Parks Fee Memo 7/29/2025 Conditional Approval DARRYL ARNOLD
Final 8/27/2025 OK for TCO JAMES POWERS
Final 9/3/2025 OK to Issue CofO JAMES POWERS