4923 N RHODES AVE 91607

Certificate Information: 4923 N RHODES AVE 91607

Application / Permit
19010-20000-05922
Plan Check / Job No.
B19VN22198
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 36' X 63' SFD WITH 21' X 19'GARAGE AND 19'6" X 7'6" AND 17' X 5" TRELLIS. NFPA -13D FIRE SPRINKLER THRU-OUT.
Permit Issued
Issued on 8/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 PINANK PATEL
Corrections Issued 1/8/2020 PINANK PATEL
Quality Review Completed 1/9/2020 ABDUL CHEGENI
Green Plans Picked Up 1/9/2020 APPLICANT
Building Plans Picked Up 1/16/2020 APPLICANT
Applicant returned to address corrections 4/30/2020 PINANK PATEL
Plan Check Approved 8/6/2020 PINANK PATEL
Issued 8/25/2020 APPLICANT
CofO in Progress 9/20/2021 CHRISTOPHE COCHRAN
Permit Finaled 9/21/2021 MICHAEL SMITH
CofO Issued 9/21/2021 MICHAEL SMITH
Permit Finaled 9/21/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 1/31/2020 ORVAL HERNANDEZ-MARCIAL
Hydrant and Access approval Cleared 2/7/2020 GEORGE SUCHAND
Address approval Cleared 2/11/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 2/11/2020 JOHN LIN
Permit Cleared 2/11/2020 JOHN LIN
Roof/Waste drainage to street Cleared 2/11/2020 JOHN LIN
Sewer availability Cleared 2/11/2020 JOHN LIN
Green Code Cleared 2/21/2020 MICHAEL AYERS
Specific Plan Cleared 7/31/2020 OLGA AYALA
ZI Cleared 7/31/2020 LAUREN PADICK

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 19261 WELLS DRIVE      TARZANA, CA 91356
Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/19/2020 Conditional Approval ARAM AVEDISIAN
Underground Mechanical 10/19/2020 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 10/20/2020 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 10/23/2020 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 10/29/2020 Partial Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 11/2/2020 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 11/9/2020 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Corrections Issued BRENDAN LOONEY
Green Building Rough 11/9/2020 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 11/9/2020 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 11/17/2020 Approved BRENDAN LOONEY
PLUMBING-Rough 11/17/2020 Approved BRENDAN LOONEY
Pre-Inspection 11/17/2020 Partial Inspection BRENDAN LOONEY
Sewer 11/19/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 12/3/2020 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 12/3/2020 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Conditional Approval BRENDAN LOONEY
Interior/Exterior Lathing 12/7/2020 Conditional Approval BRENDAN LOONEY
Shower Pan 12/7/2020 Approved BRENDAN LOONEY
Drywall Nailing 12/11/2020 Approved BRENDAN LOONEY
Final 12/11/2020 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 12/11/2020 Approved BRENDAN LOONEY
Gas Test 2/1/2021 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 2/1/2021 Not Ready for Inspection BRENDAN LOONEY
Special/Order Compliance 2/1/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 2/3/2021 Approved BRENDAN LOONEY
HVAC-Final 2/3/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 2/23/2021 Approved BRENDAN LOONEY
Final 2/23/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 2/23/2021 Approved BRENDAN LOONEY
Gas Test 2/23/2021 Approved BRENDAN LOONEY
Green Building Final 2/23/2021 Approved BRENDAN LOONEY
Green Building Rough 2/23/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Approved BRENDAN LOONEY
Service/Power Release 2/23/2021 Not Ready for Inspection BRENDAN LOONEY
Smoke Detectors 2/23/2021 Approved BRENDAN LOONEY
Verify Sprinkler Sign Off 2/23/2021 Approved BRENDAN LOONEY
Final 9/20/2021 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 9/20/2021 Approved CHRISTOPHE COCHRAN