4923 N RHODES AVE 91607
Certificate Information: 4923 N RHODES AVE 91607
- Application / Permit
- 19010-20000-05922
- Plan Check / Job No.
- B19VN22198
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 36' X 63' SFD WITH 21' X 19'GARAGE AND 19'6" X 7'6" AND 17' X 5" TRELLIS. NFPA -13D FIRE SPRINKLER THRU-OUT.
- Permit Issued
- Issued on 8/25/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | PINANK PATEL |
| Corrections Issued | 1/8/2020 | PINANK PATEL |
| Quality Review Completed | 1/9/2020 | ABDUL CHEGENI |
| Green Plans Picked Up | 1/9/2020 | APPLICANT |
| Building Plans Picked Up | 1/16/2020 | APPLICANT |
| Applicant returned to address corrections | 4/30/2020 | PINANK PATEL |
| Plan Check Approved | 8/6/2020 | PINANK PATEL |
| Issued | 8/25/2020 | APPLICANT |
| CofO in Progress | 9/20/2021 | CHRISTOPHE COCHRAN |
| Permit Finaled | 9/21/2021 | MICHAEL SMITH |
| CofO Issued | 9/21/2021 | MICHAEL SMITH |
| Permit Finaled | 9/21/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/31/2020 | ORVAL HERNANDEZ-MARCIAL |
| Hydrant and Access approval | Cleared | 2/7/2020 | GEORGE SUCHAND |
| Address approval | Cleared | 2/11/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2020 | JOHN LIN |
| Permit | Cleared | 2/11/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 2/11/2020 | JOHN LIN |
| Sewer availability | Cleared | 2/11/2020 | JOHN LIN |
| Green Code | Cleared | 2/21/2020 | MICHAEL AYERS |
| Specific Plan | Cleared | 7/31/2020 | OLGA AYALA |
| ZI | Cleared | 7/31/2020 | LAUREN PADICK |
Contact Information
| Architect | Janev,, Valentine S; Lic. No.: C19379 | 19261 WELLS DRIVE TARZANA, CA 91356 |
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2020 | Conditional Approval | ARAM AVEDISIAN |
| Underground Mechanical | 10/19/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/20/2020 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 10/23/2020 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/29/2020 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2020 | Partial Approval | BEAU COLLINS |
| BUILDING-Rough-Frame | 11/9/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 11/9/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 11/9/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 11/17/2020 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 11/17/2020 | Approved | BRENDAN LOONEY |
| Pre-Inspection | 11/17/2020 | Partial Inspection | BRENDAN LOONEY |
| Sewer | 11/19/2020 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/3/2020 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 12/3/2020 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Conditional Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/7/2020 | Conditional Approval | BRENDAN LOONEY |
| Shower Pan | 12/7/2020 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 12/11/2020 | Approved | BRENDAN LOONEY |
| Final | 12/11/2020 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/11/2020 | Approved | BRENDAN LOONEY |
| Gas Test | 2/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Final | 2/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Special/Order Compliance | 2/1/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 2/3/2021 | Approved | BRENDAN LOONEY |
| HVAC-Final | 2/3/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 2/23/2021 | Approved | BRENDAN LOONEY |
| Final | 2/23/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 2/23/2021 | Approved | BRENDAN LOONEY |
| Gas Test | 2/23/2021 | Approved | BRENDAN LOONEY |
| Green Building Final | 2/23/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 2/23/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 2/23/2021 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 2/23/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 2/23/2021 | Approved | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 2/23/2021 | Approved | BRENDAN LOONEY |
| Final | 9/20/2021 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 9/20/2021 | Approved | CHRISTOPHE COCHRAN |