7444 N FALLBROOK AVE 91307
Certificate Information: 7444 N FALLBROOK AVE 91307
- Application / Permit
- 19010-20000-05913
- Plan Check / Job No.
- B19VN22194
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETTACHED TWO STORY ADU AT REAR OF LOT.
- Permit Issued
- Issued on 2/25/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Green Plans Picked Up | 1/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | JOE VO |
| Corrections Issued | 1/13/2020 | JOE VO |
| Quality Review Completed | 1/16/2020 | KEN GILL |
| Building Plans Picked Up | 1/17/2020 | APPLICANT |
| Plan Check Approved | 2/24/2020 | JOE VO |
| Plan Check Approved | 2/25/2020 | ALDO UBAU |
| Issued | 2/25/2020 | LADBS |
| CofO in Progress | 3/4/2021 | DAVID STEPANYAN |
| Permit Finaled | 3/4/2021 | JOHN JANSON |
| CofO Issued | 3/4/2021 | JOHN JANSON |
| Permit Finaled | 3/4/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 2/4/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/4/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 2/4/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 2/4/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 2/11/2020 | DAVID MATSON |
Contact Information
| Contractor | Pnr Builders Inc; Lic. No.: 1028148-B | 21226 VENTURA BLVD #250 WOODLAND HILLS, CA 91364 |
| Engineer | Rogers,, Mark Alan; Lic. No.: C42848 | 1305 LA CULEBRA CIR CAMARILLO, CA 93012 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/10/2020 | Partial Approval | DAVID STEPANYAN |
| Underground Mechanical | 7/10/2020 | Approved | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 7/16/2020 | Corrections Issued | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 7/20/2020 | Approved | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2020 | Partial Approval | DAVID STEPANYAN |
| Deputy Wood Construction | 8/10/2020 | Conditional Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2020 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 9/23/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 9/23/2020 | Corrections Issued | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 9/23/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 9/23/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 9/23/2020 | Partial Approval | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 9/23/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/1/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/1/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 10/1/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 10/1/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/13/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 10/13/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 10/13/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 10/21/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 10/21/2020 | Approved | DAVID STEPANYAN |
| Insulation | 10/21/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 10/21/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 10/28/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 10/28/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/2/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 11/2/2020 | Approved | DAVID STEPANYAN |
| Sewer | 11/16/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 11/16/2020 | Approved | DAVID STEPANYAN |
| Final | 2/12/2021 | Corrections Issued | DAVID STEPANYAN |
| Gas Test | 2/12/2021 | Approved | DAVID STEPANYAN |
| HVAC-Final | 2/12/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 2/12/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2021 | SGSOV Approved | DAVID STEPANYAN |
| Smoke Detectors | 2/12/2021 | Approved | DAVID STEPANYAN |
| Final | 2/24/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 2/24/2021 | Approved | DAVID STEPANYAN |
| Green Building Final | 2/24/2021 | Approved | DAVID STEPANYAN |
| Service/Power Release | 2/24/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Final | 3/3/2021 | Approved | DAVID STEPANYAN |
| Final | 3/3/2021 | OK to Issue CofO | DAVID STEPANYAN |