926 N ILIFF ST 90272

Certificate Information: 926 N ILIFF ST 90272

Application / Permit
19010-20000-05912
Plan Check / Job No.
B19VN22193
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (73'-0"x 38'-0") 2-STORY SINGLE FAMILY DWELLING W/BASEMENT AND ATT. TWO CAR GARAGE. NFPA-13D FIRE SPRINKLER THRUOUT. WORK PER ENGINEER.
Permit Issued
Issued on 3/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 TROY DEGUZMAN
Corrections Issued 1/4/2020 TROY DEGUZMAN
Quality Review Completed 1/21/2020 CHON CHIO KUO
Building Plans Picked Up 1/24/2020 APPLICANT
Green Plans Picked Up 1/24/2020 APPLICANT
Plan Check Approved 2/26/2020 TROY DEGUZMAN
Issued 3/4/2020 LADBS
CofO in Progress 3/24/2022 JOHN KIDWELL
Permit Finaled 4/11/2022 DANIEL ORRANTE
CofO Issued 4/11/2022 DANIEL ORRANTE
Permit Finaled 4/11/2022 DANIEL ORRANTE

Permit Application Clearance Information

Green Code Cleared 2/7/2020 MICHAEL AYERS
Address approval Cleared 2/12/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/12/2020 THOMAS LANG
Hydrant and Access approval Cleared 2/12/2020 JOHN CONNEALLY
Low Impact Development Cleared 2/12/2020 MITESH PATEL
Sewer availability Cleared 2/12/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 2/14/2020 JOHN LIN
GPI Written Notices Cleared 2/26/2020 TROY DEGUZMAN
Grading Pre-Inspection Cleared 2/26/2020 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/11/2020 Conditional Approval JOHN KIDWELL
Special/Order Compliance 10/9/2020 No Access for Inspection JOHN KIDWELL
Footing/Foundation/Slab 10/16/2020 Conditional Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 11/12/2020 Partial Approval JOHN KIDWELL
Underground Mechanical 12/3/2020 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 12/7/2020 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 12/21/2020 Partial Approval KENNETH NAGLE
Masonry Wall/Backfill 1/5/2021 Partial Approval ANDREW NAVE
Masonry Wall/Backfill 1/12/2021 Approved JOHN KIDWELL
Footing/Foundation/Slab 1/20/2021 Approved JOHN KIDWELL
Special/Order Compliance 2/4/2021 Partial Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/10/2021 Conditional Approval JOHN KIDWELL
Deputy Wood Construction 2/23/2021 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Not Ready for Inspection JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 4/27/2021 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 4/29/2021 Conditional Approval JOHN KIDWELL
HVAC-Rough 4/29/2021 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 5/7/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/24/2021 Not Ready for Inspection JOHN KIDWELL
Green Building Rough 5/24/2021 Not Ready for Inspection JOHN KIDWELL
Shower Pan 5/24/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 5/24/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 5/26/2021 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 5/26/2021 Approved JOHN KIDWELL
Green Building Rough 5/26/2021 Approved JOHN KIDWELL
HVAC-Rough 5/26/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 5/26/2021 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/27/2021 Approved JOHN KIDWELL
Green Building Rough 5/27/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 5/27/2021 Approved JOHN KIDWELL
Wood Frame 5/27/2021 Approved JOHN KIDWELL
Insulation 6/1/2021 Approved JOHN KIDWELL
Drywall Nailing 6/11/2021 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/11/2021 Partial Approval JOHN KIDWELL
Verify Rec and Parks Fee Memo 6/25/2021 Partial Approval JOHN KIDWELL
Underground Mechanical 10/21/2021 Partial Approval JOHN KIDWELL
Sewer 10/27/2021 Not Ready for Inspection JOHN KIDWELL
Sewer 11/2/2021 Approved RYAN SALAZAR
Gas Test 11/16/2021 Approved RYAN SALAZAR
HVAC-Final 2/8/2022 Corrections Issued JOHN KIDWELL
ELECTRICAL-Final 2/10/2022 Corrections Issued ANDREW NAVE
Final 2/10/2022 Not Ready for Inspection ANDREW NAVE
Green Building Final 2/10/2022 Not Ready for Inspection ANDREW NAVE
PLUMBING-Final 2/10/2022 Not Ready for Inspection ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved ANDREW NAVE
Service/Power Release 2/10/2022 Not Ready for Inspection ANDREW NAVE
Smoke Detectors 2/10/2022 Not Ready for Inspection ANDREW NAVE
Pre-Inspection 3/10/2022 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 3/14/2022 Approved JOHN KIDWELL
Smoke Detectors 3/14/2022 Approved JOHN KIDWELL
Final 3/23/2022 OK to Issue CofO JOHN KIDWELL
Green Building Final 3/23/2022 Approved JOHN KIDWELL
Service/Power Release 3/23/2022 Approved JOHN KIDWELL