4253 N COSTELLO AVE 91423

Certificate Information: 4253 N COSTELLO AVE 91423

Application / Permit
19010-20000-05898
Plan Check / Job No.
B19VN22164
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 13’-7” X 18’-2” DETACHED RECREATION ROOM W/ WET BAR AND FULL BATH WITH SHOWER (EXTERIOR ACCESS ONLY). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 JENNIFER LEE
Corrections Issued 1/6/2020 JENNIFER LEE
Quality Review Completed 1/8/2020 STEVEN KIM
Building Plans Picked Up 1/8/2020 APPLICANT
Green Plans Picked Up 1/8/2020 APPLICANT
Applicant returned to address corrections 2/11/2020 JENNIFER LEE
Plan Check Approved 3/4/2020 JENNIFER LEE
Issued 8/5/2020 APPLICANT
CofO in Progress 5/28/2021 CHARLES POWELL
Permit Finaled 6/8/2021 MICHAEL SMITH
CofO Issued 6/8/2021 MICHAEL SMITH
Permit Finaled 6/8/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2020 CELINA MORENO
Sewer availability Cleared 2/11/2020 CELINA MORENO
Construction near power lines Cleared 2/20/2020 TORI CHEN
Green Code Cleared 2/27/2020 MICHAEL AYERS
Low Impact Development Cleared 2/27/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/27/2020 GUILLERMO PETRA
GPI Written Notices Cleared 3/4/2020 JENNIFER LEE
Grading Pre-Inspection Cleared 3/4/2020 JENNIFER LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/17/2020 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 9/23/2020 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 10/1/2020 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Approved CHARLES POWELL
PLUMBING-Rough 10/20/2020 Approved CHARLES POWELL
HVAC-Rough 11/2/2020 Approved ARAM AVEDISIAN
Shower Pan 11/2/2020 Approved ARAM AVEDISIAN
Underground Mechanical 11/2/2020 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 11/9/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 12/1/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 12/1/2020 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Approved CHARLES POWELL
Green Building Rough 12/1/2020 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 12/1/2020 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 12/11/2020 Approved CHARLES POWELL
Insulation 12/17/2020 Approved CHARLES POWELL
Drywall Nailing 12/29/2020 Approved BRENDAN LOONEY
Green Building Rough 12/29/2020 Approved BRENDAN LOONEY
HVAC-Final 4/9/2021 Approved CHARLES POWELL
PLUMBING-Final 4/9/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 4/28/2021 Approved CHARLES POWELL
Final 4/28/2021 Corrections Issued CHARLES POWELL
Green Building Final 4/28/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Approved CHARLES POWELL
Service/Power Release 4/28/2021 Approved CHARLES POWELL
Smoke Detectors 4/28/2021 Approved CHARLES POWELL
Verify Sprinkler Sign Off 4/28/2021 Approved CHARLES POWELL
Final 5/5/2021 Not Ready for Inspection CHARLES POWELL
Final 5/28/2021 OK to Issue CofO CHARLES POWELL