2078 W 30TH ST 90018
Certificate Information: 2078 W 30TH ST 90018
- Application / Permit
- 19010-20000-05890
- Plan Check / Job No.
- B19VN22150
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU . Construction per the Wood Frame Prescriptive Provisions.
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | ALBERT SERVIN |
| Green Plans Picked Up | 1/8/2020 | APPLICANT |
| Corrections Issued | 1/14/2020 | ALBERT SERVIN |
| Quality Review Completed | 1/17/2020 | KEN GILL |
| Building Plans Picked Up | 1/23/2020 | APPLICANT |
| Plan Check Approved | 2/4/2020 | ALBERT SERVIN |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 10/23/2020 | ROBERT MCDOWELL |
| Permit Finaled | 8/6/2021 | DEROLD HAUFF |
| CofO Issued | 8/6/2021 | DEROLD HAUFF |
| Permit Finaled | 8/6/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 1/24/2020 | GEORGE SUCHAND |
| Address approval | Cleared | 1/27/2020 | ELENA LOPEZ |
| Community Plan Implem. Overlay | Cleared | 1/27/2020 | MAX LODER |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | ELENA LOPEZ |
| HPOZ | Cleared | 1/27/2020 | MAX LODER |
| Sewer availability | Cleared | 1/27/2020 | ELENA LOPEZ |
| Green Code | Cleared | 1/30/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 1/30/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/30/2020 | JEANIE LAM |
Contact Information
| Contractor | Paredes Alejandro Construction; Lic. No.: 726733-B | 19156 LIGGETT ST NORTHRIDGE, CA 91324 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/6/2020 | Partial Approval | ROBERT MCDOWELL |
| Pre-Inspection | 2/6/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Barrier | 2/7/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Rough | 2/7/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Subgrade | 2/7/2020 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 2/10/2020 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 2/11/2020 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 2/11/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 2/18/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Sewer | 2/18/2020 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 2/18/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 3/2/2020 | Corrections Issued | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 3/2/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 3/2/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 3/2/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Rough | 3/2/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 3/2/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 3/2/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 3/6/2020 | Not Ready for Inspection | HORACE FULTZ |
| Insulation | 3/10/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Insulation | 3/11/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 3/11/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 3/16/2020 | Approved | ROBERT MCDOWELL |
| Shower Pan | 3/16/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/28/2020 | Conditional Approval | ROBERT MCDOWELL |
| ELECTRICAL-Final | 5/28/2020 | Approved | ROBERT MCDOWELL |
| Final | 5/28/2020 | Partial Inspection | ROBERT MCDOWELL |
| Gas Test | 5/28/2020 | Approved | ROBERT MCDOWELL |
| Green Building Final | 5/28/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/28/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 5/28/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 5/28/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 5/28/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 5/28/2020 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 5/28/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/28/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 9/16/2020 | Partial Inspection | ROBERT MCDOWELL |
| Final | 9/16/2020 | Partial Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 9/16/2020 | Partial Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 10/21/2020 | Approved | ROBERT MCDOWELL |
| Final | 10/21/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 10/21/2020 | Approved | ROBERT MCDOWELL |