9618 N GEYSER AVE 91324
Certificate Information: 9618 N GEYSER AVE 91324
- Application / Permit
- 19010-20000-05886
- Plan Check / Job No.
- B19VN22144
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1 STORY ADU.
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- Valley
- Current Status
- Issued on 12/17/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | JOE VO |
| Corrections Issued | 1/13/2020 | JOE VO |
| Quality Review Completed | 1/16/2020 | KEN GILL |
| Green Plans Picked Up | 1/17/2020 | APPLICANT |
| Plan Check Approved | 11/23/2020 | JOE VO |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Issued | 12/17/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2020 | JEANIE LAM |
| Sewer availability | Cleared | 4/24/2020 | JEANIE LAM |
| Green Code | Cleared | 5/8/2020 | MICHAEL AYERS |
| Flood clearance | Cleared | 5/20/2020 | RAYMOND LAM |
| Low Impact Development | Cleared | 8/6/2020 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 10/19/2020 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2021 | Corrections Issued | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2021 | Partial Approval | JEFFREY PARD |
| Drywall Nailing | 2/19/2021 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 2/19/2021 | Partial Approval | JEFFREY PARD |
| Wood Frame | 3/8/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/11/2021 | Not Ready for Inspection | JEFFREY PARD |
| FLOOD-Proofing Certificate | 3/11/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 3/11/2021 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 3/11/2021 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 3/18/2021 | Corrections Issued | JEFFREY PARD |
| FLOOD-Proofing Certificate | 3/18/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 3/18/2021 | Not Ready for Inspection | JEFFREY PARD |
| Verify Sprinkler Sign Off | 3/18/2021 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 3/24/2021 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 4/5/2021 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 4/5/2021 | Approved | JEFFREY PARD |
| Sewer | 4/5/2021 | Approved | JEFFREY PARD |
| HVAC-Rough | 4/7/2021 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 4/12/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 4/12/2021 | Not Ready for Inspection | JEFFREY PARD |
| Interior/Exterior Lathing | 4/12/2021 | Approved | JEFFREY PARD |
| Verify Sprinkler Sign Off | 4/12/2021 | Approved | JEFFREY PARD |
| Drywall Nailing | 4/20/2021 | Approved | JEFFREY PARD |
| Insulation | 4/20/2021 | Approved | JEFFREY PARD |
| Shower Pan | 4/22/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Rough | 4/27/2021 | Approved | JEFFREY PARD |
| Shower Pan | 4/27/2021 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 4/30/2021 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 5/18/2021 | Approved | JEFFREY PARD |
| Gas Test | 5/18/2021 | Approved | JEFFREY PARD |
| HVAC-Final | 5/18/2021 | Approved | JEFFREY PARD |
| PLUMBING-Final | 5/18/2021 | Approved | JEFFREY PARD |
| Final | 5/21/2021 | Not Ready for Inspection | JEFFREY PARD |
| Footing/Foundation/Slab | 5/21/2021 | Approved | JEFFREY PARD |
| Green Building Final | 5/21/2021 | Not Ready for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Not Ready | JEFFREY PARD |
| Service/Power Release | 5/21/2021 | Not Ready for Inspection | JEFFREY PARD |
| Smoke Detectors | 5/21/2021 | Not Ready for Inspection | JEFFREY PARD |
| Green Building Final | 6/2/2021 | Approved | JEFFREY PARD |