4835 N ANDASOL AVE 91316
Certificate Information: 4835 N ANDASOL AVE 91316
- Application / Permit
- 19010-20000-05856
- Plan Check / Job No.
- B19VN22066
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 12'-6" X 18' REC ROOM (WITH HALF BATH AND SHOWER WITH EXTERIOR ACCESS ONLY)
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | SELLA BENYAMIN |
| Green Plans Picked Up | 1/6/2020 | APPLICANT |
| Corrections Issued | 1/7/2020 | SELLA BENYAMIN |
| Quality Review Completed | 1/8/2020 | STEVEN KIM |
| Building Plans Picked Up | 1/9/2020 | APPLICANT |
| Plan Check Approved | 3/12/2020 | SELLA BENYAMIN |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 1/28/2021 | JOSEPH SAGEN |
| Permit Finaled | 1/29/2021 | DONALD SUNSERI |
| CofO Issued | 1/29/2021 | DONALD SUNSERI |
| Permit Finaled | 1/29/2021 | DONALD SUNSERI |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 2/24/2020 | GEORGE SUCHAND |
| ZA Case | Cleared | 2/24/2020 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 2/25/2020 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 2/28/2020 | AARON COSTA |
| Low Impact Development | Cleared | 2/28/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/12/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 4/22/2020 | Approved | STEVEN BACK |
| Underground Mechanical | 4/22/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 4/23/2020 | Partial Approval | STEVEN BACK |
| Deputy Reinf. Concrete | 4/24/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 4/29/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2020 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 7/6/2020 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 7/13/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 7/13/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/14/2020 | Conditional Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 7/14/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/14/2020 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 7/14/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/17/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Approved | STEVEN BACK |
| Green Building Rough | 7/17/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/17/2020 | Partial Approval | STEVEN BACK |
| Shower Pan | 7/21/2020 | Approved | STEVEN BACK |
| Insulation | 7/23/2020 | Not Ready for Inspection | STEVEN BACK |
| Insulation | 7/24/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 7/29/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 8/5/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/5/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 12/7/2020 | Approved | STEVEN BACK |
| Final | 12/7/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 12/7/2020 | Approved | STEVEN BACK |
| HVAC-Final | 12/7/2020 | Corrections Issued | STEVEN BACK |
| Insulation | 12/7/2020 | Approved | STEVEN BACK |
| PLUMBING-Final | 12/7/2020 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/7/2020 | SGSOV Not Required | STEVEN BACK |
| Service/Power Release | 12/7/2020 | Not Required | STEVEN BACK |
| Smoke Detectors | 12/7/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 12/11/2020 | Approved | STEVEN BACK |
| HVAC-Final | 12/11/2020 | Approved | STEVEN BACK |
| PLUMBING-Final | 12/11/2020 | Approved | STEVEN BACK |
| Final | 1/15/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Gas Test | 1/15/2021 | Approved | JOSEPH SAGEN |
| Final | 1/27/2021 | OK to Issue CofO | JOSEPH SAGEN |