4835 N ANDASOL AVE 91316

Certificate Information: 4835 N ANDASOL AVE 91316

Application / Permit
19010-20000-05855
Plan Check / Job No.
B19VN22066
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 87'-8" X 57' (2) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/19/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 SELLA BENYAMIN
Green Plans Picked Up 1/6/2020 APPLICANT
Corrections Issued 1/7/2020 SELLA BENYAMIN
Quality Review Completed 1/8/2020 STEVEN KIM
Building Plans Picked Up 1/9/2020 APPLICANT
Plan Check Approved 3/12/2020 SELLA BENYAMIN
Issued 3/16/2020 LADBS
CofO in Progress 1/19/2021 JOSEPH SAGEN
CofO in Progress 1/19/2021 JOSEPH SAGEN
CofO Issued 1/26/2021 DONALD SUNSERI
Permit Finaled 1/26/2021 DONALD SUNSERI

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/24/2020 GEORGE SUCHAND
ZA Case Cleared 2/24/2020 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 2/25/2020 APEKSHYA BAJRACHARYA
Permit Cleared 2/25/2020 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/25/2020 APEKSHYA BAJRACHARYA
Green Code Cleared 2/28/2020 AARON COSTA
Low Impact Development Cleared 2/28/2020 JORGE MEJIA LEMUS
Trees in Parkway Cleared 2/28/2020 ADRIAN SANCHEZ
GPI Written Notices Cleared 3/12/2020 SELLA BENYAMIN
Grading Pre-Inspection Cleared 3/12/2020 SELLA BENYAMIN
Roof/Waste drainage to street Cleared 3/12/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 4/22/2020 Approved STEVEN BACK
Underground Mechanical 4/22/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 4/23/2020 Partial Approval STEVEN BACK
Sewer 4/23/2020 Approved STEVEN BACK
Deputy Reinf. Concrete 4/24/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 4/29/2020 Approved STEVEN BACK
Deputy Steel/Welding 5/8/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Not Ready for Inspection STEVEN BACK
Deputy Steel/Welding 5/20/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/6/2020 Corrections Issued STEVEN BACK
HVAC-Rough 7/6/2020 Approved STEVEN BACK
ELECTRICAL-Rough 7/9/2020 Approved STEVEN BACK
PLUMBING-Rough 7/9/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 7/14/2020 Corrections Issued STEVEN BACK
Green Building Rough 7/14/2020 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 7/14/2020 Not Ready for Inspection STEVEN BACK
Verify Sprinkler Sign Off 7/14/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 7/17/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Approved STEVEN BACK
Green Building Rough 7/17/2020 Approved STEVEN BACK
Interior/Exterior Lathing 7/17/2020 Partial Approval STEVEN BACK
Verify Sprinkler Sign Off 7/17/2020 Approved STEVEN BACK
Shower Pan 7/21/2020 Approved STEVEN BACK
Insulation 7/23/2020 Approved STEVEN BACK
Interior/Exterior Lathing 7/29/2020 Approved STEVEN BACK
Drywall Nailing 8/5/2020 Approved STEVEN BACK
ELECTRICAL-Final 12/7/2020 Corrections Issued STEVEN BACK
HVAC-Final 12/7/2020 Corrections Issued STEVEN BACK
PLUMBING-Final 12/7/2020 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 12/11/2020 Not Ready for Inspection STEVEN BACK
HVAC-Final 12/11/2020 Approved STEVEN BACK
PLUMBING-Final 12/11/2020 Approved STEVEN BACK
Final 1/12/2021 Not Ready for Inspection JOSEPH SAGEN
Green Building Final 1/12/2021 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 1/12/2021 SGSOV Approved JOSEPH SAGEN
Service/Power Release 1/12/2021 Not Ready for Inspection JOSEPH SAGEN
Smoke Detectors 1/12/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Final 1/15/2021 Approved JOSEPH SAGEN
Final 1/15/2021 OK to Issue CofO JOSEPH SAGEN
Gas Test 1/15/2021 Approved JOSEPH SAGEN
Service/Power Release 1/15/2021 Approved JOSEPH SAGEN
Smoke Detectors 1/15/2021 Approved JOSEPH SAGEN