4670 W BEVERLY BLVD 90004

Certificate Information: 4670 W BEVERLY BLVD 90004

Application / Permit
19010-20000-05800
Plan Check / Job No.
B19VN21960
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(N) 116'6"X41'10" 6-STORY (TYPE IIIA), 30-UNIT WITH BASEMENT AND 1ST FLOOR (TYPE IA). PARKING AT (131'4"X51'6") BASEMENT AND FIRST FLOOR WITH COMMON RECREATION ROOM AT 2ND FLOOR, AND MEZZANINE AT 6TH FLOOR. NFPA 13 FIRE SPRINKLERS THROUGHOUT [TOC TIER 3 PAR 2019-4142-TOC] COMPLY WITH DEPARTMENT ORDER effective date07/26/2011. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 4/24/2024
Issuing Office
Current Status
Issued on 4/24/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 ALYSSA N NARCISO
Plans on Hold 1/21/2020 ALYSSA N NARCISO
Hold Released 1/28/2020 ALYSSA N NARCISO
Disabled Access Plans Picked Up 1/28/2020 APPLICANT
Green Plans Picked Up 1/28/2020 APPLICANT
Corrections Issued 1/31/2020 ALYSSA N NARCISO
Quality Review Completed 2/12/2020 CHON CHIO KUO
Building Plans Picked Up 2/14/2020 APPLICANT
Applicant returned to address corrections 8/11/2021 MARVEL DELACRUZ
Applicant returned to address corrections 6/9/2022 RAPHAEL ROSAS
Applicant returned to address corrections 9/30/2022 MARVEL DELACRUZ
Applicant returned to address corrections 1/24/2023 MARVEL DELACRUZ
Applicant returned to address corrections 4/28/2023 MARVEL DELACRUZ
Applicant returned to address corrections 5/10/2023 MARVEL DELACRUZ
Applicant returned to address corrections 8/24/2023 MARVEL DELACRUZ
Plan Check Approved 8/30/2023 MARVEL DELACRUZ
Plan Check Approved 4/24/2024 MARVEL DELACRUZ
Issued 4/24/2024 APPLICANT

Permit Application Clearance Information

Hold Cleared 1/28/2020 LOURDES RAMIRO
Building over 3-story or 36-ft Cleared 1/7/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/7/2021 CALOSHA APPROVED
Address approval Cleared 5/26/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 5/26/2021 THOMAS LANG
Trees in Parkway Cleared 6/2/2021 JOHN KIM
Sewer availability Cleared 7/16/2021 CECILIO NAVARRO
Hydrant and Access approval Cleared 11/2/2021 KURT CORRAL
Green Code Cleared 11/18/2021 DAVID MATSON
DAS Clearance Cleared 11/30/2021 ALYSSA N NARCISO
Highway dedication Cleared 1/19/2022 JEANETTE VONG
Permit Cleared 2/15/2022 JEANETTE VONG
Driveway location Cleared 3/18/2022 MOHAMMAD HASAN
Low Impact Development Cleared 3/30/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/12/2022 JEANETTE VONG
Fire Marshall Fire Life Safety Cleared 4/28/2022 MENOA AGHAJANI
Density Bonus 12.22.A.31 Cleared 7/22/2022 DORIS KWOK
Frnt yard landscape/Water mgmt Cleared 9/21/2022 NATHAN ROMINE
Miscellaneous Cleared 9/21/2022 NATHAN ROMINE
Miscellaneous Cleared 9/21/2022 NATHAN ROMINE
Opn space landscape/Water mgmt Cleared 9/21/2022 NATHAN ROMINE
ZA Case Cleared 9/21/2022 NATHAN ROMINE
ZA Case Cleared 9/21/2022 NATHAN ROMINE
ZA Case Cleared 9/21/2022 NATHAN ROMINE
ZA Case Cleared 9/21/2022 NATHAN ROMINE
Miscellaneous Cleared 7/20/2023 NATHAN ROMINE
Miscellaneous Cleared 7/20/2023 NATHAN ROMINE
Miscellaneous Cleared 7/20/2023 NATHAN ROMINE
Opn space landscape/Water mgmt Cleared 7/20/2023 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/6/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/6/2025 Not Ready for Inspection EDWIN GREGORYONA
Footing/Foundation/Slab 3/6/2025 Not Ready for Inspection EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/7/2025 Not Ready for Inspection RAFAEL ESPINOZA
Footing/Foundation/Slab 3/7/2025 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 3/17/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/17/2025 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 3/20/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 3/20/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 4/22/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 4/22/2025 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/12/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/12/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/16/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/28/2025 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/30/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 5/30/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 6/23/2025 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 7/1/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 7/30/2025 Partial Approval JOEY BUCHANAN
Floor/Roof Diaphrgm/Shear Wall 8/13/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 8/26/2025 Partial Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 9/16/2025 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 9/16/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 11/20/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Partial Approval MARTIN TAVITIAN
Wood Frame 12/8/2025 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 12/19/2025 Partial Approval EDWIN GREGORYONA
Drywall Nailing 1/20/2026 Partial Inspection JEFFREY FULTON
Insulation 1/20/2026 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/26/2026 Partial Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 1/30/2026 Partial Approval MARTIN TAVITIAN
Insulation 1/30/2026 Partial Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 2/10/2026 Partial Approval MARTIN TAVITIAN
Wood Frame 2/24/2026 Partial Approval MARTIN TAVITIAN
Wood Frame 3/23/2026 Partial Approval MARTIN TAVITIAN
Insulation 4/16/2026 Partial Approval MARTIN TAVITIAN
Drywall Nailing 4/20/2026 Partial Approval MARTIN TAVITIAN
Green Building Rough 4/20/2026 Approved MARTIN TAVITIAN
Structural Steel Frame 4/20/2026 Approved MARTIN TAVITIAN
Wood Frame 4/22/2026 Partial Inspection MARTIN TAVITIAN
Wood Frame 4/27/2026 Partial Approval MARTIN TAVITIAN
Interior/Exterior Lathing 4/29/2026 Partial Approval MARTIN TAVITIAN
Drywall Nailing 4/30/2026 Partial Approval MARTIN TAVITIAN
Wood Frame 5/6/2026 Partial Approval MARTIN TAVITIAN
Drywall Nailing 5/13/2026 Partial Approval MARTIN TAVITIAN
Drywall Nailing 5/22/2026 Partial Approval MARTIN TAVITIAN
Drywall Nailing 6/5/2026 No Result Entered MARTIN TAVITIAN