10218 N FERNGLEN AVE 91042

Certificate Information: 10218 N FERNGLEN AVE 91042

Application / Permit
19010-20000-05792
Plan Check / Job No.
B19VN21939
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
(1 OF 3) (N) 107'10"X51'0" 3-STORY FULLY SPRINKLERED (NFPA-13) 10-UNIT (INCLUDING 1 VERY LOW INCOME UNIT PER LAMC 12.22 A.25) APARTMENT WITH 19-CAR GARAGE BASEMENT. HEIGHT INCENTIVE PER 12.22 A.25 REQUESTED. SEE COMMENTS
Permit Issued
Issued on 9/23/2021
Issuing Office
Current Status
CofO Issued on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Application Withdrawn 12/18/2019 APPLICANT
Re-Activate Applicaton 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 MARVEL DELACRUZ
Green Plans Picked Up 1/24/2020 APPLICANT
Corrections Issued 1/28/2020 MARVEL DELACRUZ
Disabled Access Plans Picked Up 1/28/2020 APPLICANT
Quality Review Completed 1/29/2020 STEVEN KIM
Building Plans Picked Up 1/30/2020 APPLICANT
Applicant returned to address corrections 5/1/2020 MARVEL DELACRUZ
Applicant returned to address corrections 12/1/2020 MARVEL DELACRUZ
Applicant returned to address corrections 12/3/2020 MARVEL DELACRUZ
Applicant returned to address corrections 2/3/2021 MARVEL DELACRUZ
Applicant returned to address corrections 9/1/2021 MARVEL DELACRUZ
Plan Check Approved 9/1/2021 MARVEL DELACRUZ
Issued 9/23/2021 APPLICANT
CofO in Progress 6/26/2025 RICKEY JACKSON
Permit Finaled 6/26/2025 RICKEY JACKSON
CofO Issued 6/26/2025 RICKEY JACKSON
Permit Finaled 6/26/2025 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 2/11/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/11/2020 JOHN TRIANTAFYLLOS
Excavation more than 5-ft deep Cleared 4/29/2020 CALOSHA APPROVED
Miscellaneous Cleared 9/16/2020 GABRIEL ROBLES
Building over 3-story or 36-ft Cleared 9/22/2020 CALOSHA APPROVED
Hydrant and Access approval Cleared 10/14/2020 KURT CORRAL
Density Bonus 12.22.A.25 Cleared 10/28/2020 DORIS KWOK
Trees in Parkway Cleared 11/19/2020 JOHN KIM
Fire Marshall Fire Life Safety Cleared 2/19/2021 VIDAL GARCIA
Frnt yard landscape/Water mgmt Cleared 3/17/2021 LAUREN PADICK
Opn space landscape/Water mgmt Cleared 3/17/2021 LAUREN PADICK
Specific Plan Cleared 3/17/2021 LAUREN PADICK
Specific Plan Cleared 6/10/2021 KORA MCNAUGHTON
ZI Cleared 6/10/2021 KORA MCNAUGHTON
Sewer availability Cleared 6/24/2021 ADRIAN CASTRO
DAS Clearance Cleared 7/6/2021 MARVEL DELACRUZ
Low Impact Development Cleared 7/26/2021 MITESH PATEL
Highway dedication Cleared 8/10/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 8/16/2021 GABRIEL ROBLES
Green Code Cleared 8/17/2021 MICHAEL AYERS
Permit Cleared 8/18/2021 GABRIEL ROBLES
GPI Written Notices Cleared 9/1/2021 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 9/1/2021 MARVEL DELACRUZ

Contact Information

Contractor Razmik Construction Inc; Lic. No.: 544544-B 3571 E CHEVY CHASE DR      GLENDALE, CA 91206
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/15/2021 No Access for Inspection DANNY RODRIGUEZ
Pre-Inspection 11/16/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 5/2/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/4/2022 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/9/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Shotcrete 5/31/2022 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 5/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 5/31/2022 Corrections Issued DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 6/6/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 6/6/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/6/2022 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 6/7/2022 Partial Approval DANNY RODRIGUEZ
Deputy Shotcrete 6/10/2022 Conditional Approval DANNY RODRIGUEZ
Reinforced Concrete Frame 6/10/2022 Partial Approval DANNY RODRIGUEZ
Deputy Shotcrete 7/22/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 8/31/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Shotcrete 9/1/2022 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/2/2022 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 9/26/2022 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 9/28/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 9/30/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/8/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 12/12/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 12/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/12/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 12/13/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 2/6/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 2/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 2/23/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Corrections Issued DANNY RODRIGUEZ
Green Building Rough 3/28/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/28/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/30/2023 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 4/5/2023 Conditional Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Corrections Issued DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/28/2023 Partial Approval DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/28/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/1/2023 Not Ready for Inspection ANDREW DORSO
Masonry Wall/Backfill 6/1/2023 Partial Inspection ANDREW DORSO
Verify Sprinkler Sign Off 6/1/2023 Not Ready for Inspection ANDREW DORSO
Deputy Wood Construction 6/23/2023 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 6/27/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 6/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 6/27/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 6/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 6/27/2023 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 7/13/2023 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 7/24/2023 Partial Approval JOHN KITCKO
Green Building Rough 7/24/2023 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/24/2023 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/24/2023 Not Ready for Inspection JOHN KITCKO
Green Building Rough 7/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/26/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 7/26/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 8/10/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/10/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 8/10/2023 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 8/14/2023 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 8/16/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/16/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 8/16/2023 Partial Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 8/24/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 8/24/2023 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 9/11/2023 Partial Approval VAHE KELEDJIAN
Wood Frame 9/11/2023 Conditional Approval VAHE KELEDJIAN
Green Building Rough 9/20/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 9/20/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/20/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 9/20/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 9/26/2023 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 9/26/2023 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/26/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 9/26/2023 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 9/29/2023 Approved DANNY RODRIGUEZ
Green Building Rough 9/29/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/29/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 9/29/2023 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 10/5/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 10/5/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/5/2023 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 10/12/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/12/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 10/12/2023 Corrections Issued DANNY RODRIGUEZ
Drywall Nailing 10/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 10/25/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 10/25/2023 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 11/2/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 11/2/2023 Partial Approval DANNY RODRIGUEZ
Insulation 11/6/2023 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 11/8/2023 Partial Approval DANNY RODRIGUEZ
Green Building Rough 11/8/2023 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 12/15/2023 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 12/15/2023 Partial Inspection DANNY RODRIGUEZ
Wood Frame 12/15/2023 Corrections Issued DANNY RODRIGUEZ
Wood Frame 12/20/2023 Partial Approval DANNY RODRIGUEZ
Insulation 1/3/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/5/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/10/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/10/2024 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 1/10/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 1/19/2024 Partial Approval DANNY RODRIGUEZ
Green Building Rough 1/19/2024 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/31/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 1/31/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/7/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/13/2024 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 2/13/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/27/2024 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 3/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/12/2024 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/12/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/20/2024 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/9/2024 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 4/16/2024 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 9/30/2024 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 10/8/2024 No Access for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/9/2024 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 10/23/2024 Partial Inspection DANNY RODRIGUEZ
Pre-Inspection 10/25/2024 Partial Inspection DANNY RODRIGUEZ
Special/Order Compliance 1/24/2025 Not Ready for Inspection DANNY RODRIGUEZ
Special/Order Compliance 3/11/2025 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 3/21/2025 Not Ready for Inspection DANNY RODRIGUEZ
Final 3/21/2025 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/21/2025 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Final 3/21/2025 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 3/21/2025 Not Ready for Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Approved DANNY RODRIGUEZ
Smoke Detectors 3/21/2025 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/21/2025 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/21/2025 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 4/23/2025 Not Ready for Inspection DANNY RODRIGUEZ
Final 4/23/2025 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/23/2025 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Concrete Frame 4/23/2025 Not Ready for Inspection DANNY RODRIGUEZ
Smoke Detectors 4/23/2025 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/23/2025 Approved DANNY RODRIGUEZ
Wood Frame 4/23/2025 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 4/30/2025 Approved DANNY RODRIGUEZ
Final 4/30/2025 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 4/30/2025 Approved DANNY RODRIGUEZ
Reinforced Concrete Frame 4/30/2025 Approved DANNY RODRIGUEZ
Wood Frame 4/30/2025 Approved DANNY RODRIGUEZ
Final 6/26/2025 OK to Issue CofO RICKEY JACKSON