5261 N RAINIER WAY 91607
Certificate Information: 5261 N RAINIER WAY 91607
- Application / Permit
- 19010-20000-05781
- Plan Check / Job No.
- B19VN21894
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SFD W/ ATTACHED 2-CAR GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT) **** SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE TRACT MAP NO. VTT-73704-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED ****
- Permit Issued
- Issued on 5/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/31/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/7/2020 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 1/7/2020 | APPLICANT |
| Quality Review Completed | 1/10/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 1/10/2020 | APPLICANT |
| Applicant returned to address corrections | 1/31/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 3/12/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 4/21/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/21/2020 | NILOOFAR MEHRAIN |
| Issued | 5/5/2020 | LADBS |
| CofO in Progress | 9/26/2021 | JOSEPH SAGEN |
| CofO Issued | 9/28/2021 | MICHAEL SMITH |
| Permit Finaled | 9/28/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 1/31/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 2/11/2020 | JEREMY CARTER |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 3/5/2020 | ORVAL HERNANDEZ-MARCI |
| "Q" conditions | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Specific Plan | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| ZI | Cleared | 3/9/2020 | RUBEN VASQUEZ |
| Address approval | Cleared | 3/10/2020 | GUILLERMO PETRA |
| Miscellaneous | Cleared | 3/10/2020 | GUILLERMO PETRA |
| Permit | Cleared | 3/10/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/10/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/10/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Williams Homes Inc; Lic. No.: 734097-B | 21080 CENTRE POINTE PARKWAY #101 SANTA CLARITA, CA 91350 |
| Engineer | Forbes,, Dale Loren; Lic. No.: C30407 | 1800 E 16TH ST UNIT 3 C/O ESI/FME, INC. SANTA ANA, CA 92701 |
| Engineer | Minas,, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| JOSEPH SAGEN, (818) 774-4353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 6/15/2020 | No Access for Inspection | THOMAS FINNILA |
| Underground Mechanical | 6/15/2020 | No Access for Inspection | THOMAS FINNILA |
| Sewer | 6/16/2020 | Approved | JOSEPH SAGEN |
| Underground Mechanical | 6/16/2020 | Partial Approval | JOSEPH SAGEN |
| Footing/Foundation/Slab | 6/30/2020 | Approved | JOSEPH SAGEN |
| Underground Mechanical | 8/21/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2021 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2021 | Partial Approval | JOSEPH SAGEN |
| BUILDING-Rough-Frame | 2/25/2021 | Approved | JOSEPH SAGEN |
| ELECTRICAL-Rough | 2/25/2021 | Approved | JOSEPH SAGEN |
| Green Building Rough | 2/25/2021 | Approved | JOSEPH SAGEN |
| HVAC-Rough | 2/25/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Rough | 2/25/2021 | Approved | JOSEPH SAGEN |
| Verify Sprinkler Sign Off | 2/25/2021 | Approved | JOSEPH SAGEN |
| Drywall Nailing | 3/12/2021 | Approved | JOSEPH SAGEN |
| Interior/Exterior Lathing | 3/12/2021 | Partial Approval | JOSEPH SAGEN |
| Gas Test | 4/21/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Service/Power Release | 4/21/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Gas Test | 4/27/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Service/Power Release | 4/27/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Gas Test | 4/28/2021 | Approved | JOSEPH SAGEN |
| Service/Power Release | 4/28/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Service/Power Release | 4/30/2021 | Approved | JOSEPH SAGEN |
| SGSOV-Seismic Gas S/O Valve | 6/1/2021 | SGSOV Approved | JOSEPH SAGEN |
| Final | 9/23/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Green Building Final | 9/23/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| Smoke Detectors | 9/23/2021 | Not Ready for Inspection | JOSEPH SAGEN |
| ELECTRICAL-Final | 9/24/2021 | Approved | JOSEPH SAGEN |
| Final | 9/24/2021 | OK to Issue CofO | JOSEPH SAGEN |
| Green Building Final | 9/24/2021 | Approved | JOSEPH SAGEN |
| HVAC-Final | 9/24/2021 | Approved | JOSEPH SAGEN |
| PLUMBING-Final | 9/24/2021 | Approved | JOSEPH SAGEN |
| Smoke Detectors | 9/24/2021 | Approved | JOSEPH SAGEN |
| Special/Order Compliance | 9/24/2021 | Approved | JOSEPH SAGEN |