4326 N BEEMAN AVE 91604
Certificate Information: 4326 N BEEMAN AVE 91604
- Application / Permit
- 19010-20000-05763
- Plan Check / Job No.
- B19VN21936
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 64'-6" X 58'-0" (IRREGULAR SHAPED) FULLY SPRINKLERED TWO STORY SFD WITH TWO CAR GARAGE & OPEN TRELLIS.
- Permit Issued
- Issued on 6/9/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 12/29/2019 | ARTIN ZARUKIAN |
| Quality Review Completed | 1/2/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 1/6/2020 | APPLICANT |
| Green Plans Picked Up | 1/6/2020 | APPLICANT |
| Plan Check Approved | 4/23/2020 | ARTIN ZARUKIAN |
| Issued | 6/9/2020 | LADBS |
| CofO in Progress | 4/10/2021 | DANIEL ORRANTE |
| CofO Issued | 4/10/2021 | DANIEL ORRANTE |
| Permit Finaled | 4/10/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/31/2020 | ORVAL HERNANDEZ-MARCIAL |
| Hydrant and Access approval | Cleared | 2/7/2020 | GEORGE SUCHAND |
| Address approval | Cleared | 2/11/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2020 | JOHN LIN |
| Permit | Cleared | 2/11/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 2/11/2020 | JOHN LIN |
| Sewer availability | Cleared | 2/11/2020 | JOHN LIN |
| ZI | Cleared | 2/11/2020 | HERMINIGILDO AGUSTIN |
| Green Code | Cleared | 2/21/2020 | MICHAEL AYERS |
| Trees in Parkway | Cleared | 3/27/2020 | JOHN KIM |
Contact Information
| Architect | Janev,, Valentine S; Lic. No.: C19379 | 19261 WELLS DRIVE TARZANA, CA 91356 |
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/3/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/5/2020 | Corrections Issued | MATTHEW NELSON |
| Sewer | 8/5/2020 | Partial Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/6/2020 | Partial Inspection | WILLIAM KUEHN |
| Sewer | 8/6/2020 | Approved | WILLIAM KUEHN |
| Footing/Foundation/Slab | 8/12/2020 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2020 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/24/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/25/2020 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 10/9/2020 | No Access for Inspection | JENNIFER RABUCHIN |
| Shower Pan | 10/9/2020 | No Access for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 10/15/2020 | No Access for Inspection | ARAM AVEDISIAN |
| Shower Pan | 10/15/2020 | No Access for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/20/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/20/2020 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 10/20/2020 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 10/20/2020 | Approved | ARAM AVEDISIAN |
| Shower Pan | 10/20/2020 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 10/20/2020 | Approved | ARAM AVEDISIAN |
| Insulation | 10/29/2020 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 11/6/2020 | Approved | DANIEL ORRANTE |
| Interior/Exterior Lathing | 11/9/2020 | Approved | DANIEL ORRANTE |
| ELECTRICAL-Final | 3/4/2021 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 3/4/2021 | Corrections Issued | ARAM AVEDISIAN |
| Final | 3/10/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 3/10/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/10/2021 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 3/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 3/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 4/7/2021 | OK to Issue CofO | DANIEL ORRANTE |
| Green Building Final | 4/7/2021 | Approved | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 4/7/2021 | SGSOV Approved | DANIEL ORRANTE |
| Service/Power Release | 4/7/2021 | Approved | DANIEL ORRANTE |
| Smoke Detectors | 4/7/2021 | Approved | DANIEL ORRANTE |