15342 W LEADWELL ST 91406
Certificate Information: 15342 W LEADWELL ST 91406
- Application / Permit
- 19010-20000-05744
- Plan Check / Job No.
- B19VN21849
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED NEW ACCESSORY DWELLING UNIT (26'X20'8") PER AB 494 & SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/5/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | HAYATO TSUCHIYA |
| Corrections Issued | 12/30/2019 | HAYATO TSUCHIYA |
| Quality Review Completed | 12/31/2019 | ABDUL CHEGENI |
| Green Plans Picked Up | 1/2/2020 | APPLICANT |
| Building Plans Picked Up | 1/7/2020 | APPLICANT |
| Plan Check Approved | 1/27/2020 | HAYATO TSUCHIYA |
| Issued | 1/27/2020 | LADBS |
| CofO in Progress | 11/24/2020 | DAVID MATSON |
| CofO in Progress | 11/24/2020 | DAVID MATSON |
| Permit Finaled | 12/5/2020 | MICHAEL SMITH |
| CofO Issued | 12/5/2020 | MICHAEL SMITH |
| Permit Finaled | 12/5/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 1/13/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 1/13/2020 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/13/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/14/2020 | Approved | WILLIAM KUEHN |
| Underground Mechanical | 2/14/2020 | Partial Inspection | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Partial Inspection | WILLIAM KUEHN |
| Gas Test | 3/6/2020 | Partial Inspection | WILLIAM KUEHN |
| Underground Mechanical | 3/6/2020 | Partial Inspection | WILLIAM KUEHN |
| ELECTRICAL-Rough | 3/19/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 3/19/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Sewer | 3/19/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 4/6/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 4/6/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 4/6/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 4/6/2020 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 4/6/2020 | Approved | WILLIAM KUEHN |
| Insulation | 4/13/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 4/13/2020 | Partial Inspection | WILLIAM KUEHN |
| Drywall Nailing | 4/15/2020 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 4/15/2020 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 5/29/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/29/2020 | Corrections Issued | JOHN HAYES |
| Green Building Final | 5/29/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/29/2020 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 5/29/2020 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 5/29/2020 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 7/7/2020 | Approved | WILLIAM KUEHN |
| Final | 7/7/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Final | 7/7/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2020 | SGSOV Approved | WILLIAM KUEHN |
| Service/Power Release | 7/7/2020 | Not Required | WILLIAM KUEHN |
| Smoke Detectors | 7/7/2020 | Approved | WILLIAM KUEHN |
| Final | 11/24/2020 | OK to Issue CofO | DAVID MATSON |