7366 S OSAGE AVE 90045
Certificate Information: 7366 S OSAGE AVE 90045
- Application / Permit
- 19010-20000-05739
- Plan Check / Job No.
- B19VN21844
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- NEW 194'6-3/4" X 140'4-1/4"' THREE STORY STORAGE BUILDING (TYPE II B CONSTRUCTION ) OVER THREE STORY STORAGE BASEMENT (TYPE I A CONSTRUCTION) , FULLY SPRINKLERED NFPA-13 PER ZA-2018-4795-CU-ZV-ZAA-ZAD , ALL WORK PER ENGINEERING - SEE COMMENTS
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | RARES BODEA |
| Corrections Issued | 1/16/2020 | RARES BODEA |
| Quality Review Completed | 1/22/2020 | GUANG MIN TUNG |
| Green Plans Picked Up | 1/24/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 1/31/2020 | APPLICANT |
| Applicant returned to address corrections | 6/16/2021 | RARES BODEA |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| Applicant returned to address corrections | 12/15/2021 | RARES BODEA |
| Applicant returned to address corrections | 3/30/2022 | RARES BODEA |
| Plan Check Approved | 4/20/2022 | RARES BODEA |
| Issued | 5/11/2022 | APPLICANT |
| TCO Issued (Expire Date: 07-01-2025) | 1/2/2025 | DAVID TSAU |
| CofO in Progress | 5/28/2025 | DERRICK SPENCER |
| Permit Finaled | 5/28/2025 | HENRY BAGHDASSARIAN |
| CofO Issued | 5/28/2025 | HENRY BAGHDASSARIAN |
| Permit Finaled | 5/28/2025 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2020 | ERIK BEASLEY |
| Highway dedication | Cleared | 2/3/2020 | ERIK BEASLEY |
| Permit | Cleared | 2/3/2020 | ERIK BEASLEY |
| Miscellaneous | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| ZA Case | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| ZA Case | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| ZA Case | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| ZA Case | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| ZA Case | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| ZA Case | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| ZA Case | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| ZA Case | Cleared | 2/4/2020 | JOSE ROMERO-NAVARRO |
| Sewer availability | Cleared | 6/30/2021 | DENNIS BRAGIN |
| Trees in Parkway | Cleared | 7/1/2021 | JOHN KIM |
| Green Code | Cleared | 8/5/2021 | MICHAEL AYERS |
| ZA Case | Cleared | 11/15/2021 | KENTON TRINH |
| Miscellaneous | Cleared | 11/16/2021 | JASON CHAN |
| DAS Clearance | Cleared | 12/9/2021 | HAYATO TSUCHIYA |
| Low Impact Development | Cleared | 12/23/2021 | JORGE MEJIA LEMUS |
| Building over 3-story or 36-ft | Cleared | 1/3/2022 | CALOSHA APPROVED |
| Excavation more than 5-ft deep | Cleared | 1/3/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/3/2022 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 1/3/2022 | RARES BODEA |
| Specific Plan | Cleared | 1/11/2022 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 1/14/2022 | SAUL GARCIA |
| Work Adjacent to Public Way | Cleared | 2/23/2022 | SAUL GARCIA |
| Prkng lot landscape/Water mgmt | Cleared | 3/14/2022 | KENTON TRINH |
Contact Information
| Architect | Mayne,, Thomas; Lic. No.: C15972 | 3440 WESLEY STREET CULVER CITY, CA 90232 |
| Contractor | Near-Cal Corp; Lic. No.: 230077-B | 512 CHANEY STREET LAKE ELSINORE, CA 92530 |
| Engineer | Tang,, Stanley Siu Kei; Lic. No.: C56178 | 1105 N AVON STREET BURBANK, CA 91505 |
| Engineer | Timmers,, Matthew Allan; Lic. No.: S5560 | 950 S. GRAND AVE 4TH FLR LOS ANGELES, CA 90015 |
Inspector Information
| VASIL MIHALEV, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/16/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 5/17/2022 | Approved | NICK LAROCCA |
| Deputy Grading | 5/18/2022 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 12/20/2022 | Partial Inspection | NICK LAROCCA |
| Pre-Inspection | 1/25/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/15/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/15/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/21/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/21/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/22/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/27/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 3/6/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Shotcrete | 3/13/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 4/5/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Deputy Shotcrete | 4/10/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 4/10/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 4/11/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 4/12/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 4/13/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/14/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 4/14/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 4/18/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/19/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/20/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 4/20/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/21/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 4/24/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 4/25/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 4/26/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 5/1/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/1/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Deputy Shotcrete | 5/2/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 5/3/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 5/3/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Shotcrete | 5/8/2023 | Conditional Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/8/2023 | Partial Approval | NICK LAROCCA |
| Masonry Wall/Backfill | 5/10/2023 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Masonry | 5/11/2023 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 5/17/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 5/17/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/17/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/22/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 5/24/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 6/1/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/1/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Shotcrete | 6/7/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 6/7/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Shotcrete | 6/8/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Shotcrete | 6/9/2023 | Approved | NICK LAROCCA |
| Deputy Reinf. Masonry | 6/12/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Shotcrete | 6/12/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Reinf. Masonry | 6/13/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 6/13/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 6/14/2023 | Approved | DERRICK SPENCER |
| Green Building Rough | 6/14/2023 | Not Ready for Inspection | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 6/14/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 6/14/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Masonry | 6/15/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 6/15/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/5/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 7/10/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 7/11/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 7/12/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/8/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 8/9/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/10/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/16/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Shotcrete | 8/30/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/30/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 8/31/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 9/1/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Shotcrete | 9/20/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 9/20/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Masonry | 9/21/2023 | Approved | DERRICK SPENCER |
| Pre-Inspection | 9/21/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 9/26/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/2/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/10/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 10/12/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/16/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/19/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 10/25/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 11/20/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 11/21/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 11/22/2023 | Approved | DERRICK SPENCER |
| Green Building Rough | 12/4/2023 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 12/4/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 12/6/2023 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 12/14/2023 | Partial Approval | DERRICK SPENCER |
| Masonry Wall/Backfill | 12/19/2023 | Partial Approval | GRANT WOODS |
| Footing/Foundation/Slab | 1/3/2024 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Masonry | 1/4/2024 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 1/10/2024 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 1/18/2024 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 1/24/2024 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 1/24/2024 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 1/25/2024 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/1/2024 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/2/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 2/2/2024 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/13/2024 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/21/2024 | Partial Approval | DERRICK SPENCER |
| Deputy Shotcrete | 2/22/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 2/22/2024 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 2/27/2024 | Approved | DERRICK SPENCER |
| Masonry Wall/Backfill | 2/28/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 3/11/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 3/28/2024 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 3/29/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 4/4/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 4/10/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 4/22/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 5/2/2024 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 5/9/2024 | Partial Approval | NICK LAROCCA |
| Pre-Inspection | 5/23/2024 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 6/10/2024 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 6/24/2024 | Approved | DERRICK SPENCER |
| Insulation | 6/24/2024 | Partial Approval | DERRICK SPENCER |
| Insulation | 6/26/2024 | Approved | DERRICK SPENCER |
| Wall Anchors | 6/26/2024 | Approved | DERRICK SPENCER |
| Drywall Nailing | 7/22/2024 | Approved | DERRICK SPENCER |
| Interior/Exterior Lathing | 8/21/2024 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 9/19/2024 | Approved | DERRICK SPENCER |
| Deputy Grading | 10/17/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 10/22/2024 | Approved | DERRICK SPENCER |
| Deputy Grading | 10/29/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Grading | 11/12/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/10/2024 | Approved | DERRICK SPENCER |
| Final | 12/16/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 12/16/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/16/2024 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 12/16/2024 | Approved | DERRICK SPENCER |
| Reinforced Masonry Frame | 12/16/2024 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 12/16/2024 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 12/16/2024 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 12/16/2024 | Approved | DERRICK SPENCER |
| Wood Frame | 12/16/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/17/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/19/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/23/2024 | Approved | DERRICK SPENCER |
| Pre-Inspection | 12/26/2024 | Partial Inspection | DANIEL VARNUM |
| Pre-Inspection | 12/30/2024 | Approved | DERRICK SPENCER |
| Final | 12/31/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Pre-Inspection | 1/13/2025 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/14/2025 | Approved | DERRICK SPENCER |
| Final | 5/20/2025 | OK to Issue CofO | DERRICK SPENCER |
| Pre-Inspection | 5/21/2025 | Approved | DERRICK SPENCER |