20327 W ABERDEEN LANE 91326

Certificate Information: 20327 W ABERDEEN LANE 91326

Application / Permit
19010-20000-05706
Plan Check / Job No.
B19VN21745
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(TRACT 50509-01) PROPOSE THREE STORY SFD WITH ATTACH 3 CAR GARAGE_ STANDARD PLAN # 648 _ PLAN 1XC_BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D.
Permit Issued
Issued on 12/29/2020
Issuing Office
Current Status
CofO Issued on 3/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2019 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 DAWN MC NULTY
Corrections Issued 1/13/2020 DAWN MC NULTY
Green Plans Picked Up 1/28/2020 APPLICANT
Quality Review Completed 1/29/2020 CHON CHIO KUO
Building Plans Picked Up 1/30/2020 APPLICANT
Plan Check Approved 12/18/2020 DAWN MC NULTY
Issued 12/29/2020 APPLICANT
CofO in Progress 3/10/2022 SEAN WIRCH
Permit Finaled 3/10/2022 MICHAEL SMITH
CofO Issued 3/10/2022 MICHAEL SMITH
Permit Finaled 3/10/2022 MICHAEL SMITH

Permit Application Clearance Information

"T" removal Cleared 9/23/2020 DENZEL HENDERSON
Address approval Cleared 9/23/2020 LEE GUILBEAUX
CPC Cleared 9/23/2020 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 9/23/2020 LEE GUILBEAUX
Miscellaneous Cleared 9/23/2020 DENZEL HENDERSON
Miscellaneous Cleared 9/23/2020 DENZEL HENDERSON
Miscellaneous Cleared 9/23/2020 DENZEL HENDERSON
Miscellaneous Cleared 9/23/2020 DENZEL HENDERSON
Permit Cleared 9/23/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/23/2020 LEE GUILBEAUX
Sewer availability Cleared 9/23/2020 LEE GUILBEAUX
Specific Plan Cleared 9/23/2020 DENZEL HENDERSON
Tract Map conditions Cleared 9/23/2020 DENZEL HENDERSON
Tract Map conditions Cleared 9/23/2020 DENZEL HENDERSON
ZA Case Cleared 9/23/2020 DENZEL HENDERSON
ZA Case Cleared 9/23/2020 DENZEL HENDERSON
Public Works-Highway Ded. Cleared 9/23/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 11/24/2020 MATTHEW CRAIG
Green Code Cleared 12/1/2020 MICHAEL AYERS
Low Impact Development Cleared 12/2/2020 AMMAR ELTAWIL

Contact Information

Contractor Shapell Homes Inc; Lic. No.: 1001034-B 250 GIBRALTAR RD   ATTN: GATES/LEGAL    HORSHAM, PA 19044
Engineer Miller, Karen Lynn; Lic. No.: GE2257 5364 DORIS WY      TORRANCE, CA 90505
Engineer Wong, Ramon Roman Ii; Lic. No.: S2345 1800 E. 16TH STREET      SANTA ANA, CA 92701

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/23/2021 Not Ready for Inspection SEAN WIRCH
Footing/Foundation/Slab 4/26/2021 Approved SEAN WIRCH
Deputy Reinf. Concrete 4/27/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval SEAN WIRCH
Sewer 5/20/2021 Approved SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/6/2021 Approved SEAN WIRCH
ELECTRICAL-Rough 11/3/2021 Approved SEAN WIRCH
HVAC-Rough 11/3/2021 Approved SEAN WIRCH
PLUMBING-Rough 11/3/2021 Approved SEAN WIRCH
BUILDING-Rough-Frame 11/5/2021 Approved SEAN WIRCH
Green Building Rough 11/5/2021 Approved SEAN WIRCH
Verify Sprinkler Sign Off 11/5/2021 Approved SEAN WIRCH
Drywall Nailing 11/30/2021 Approved HENRY KIM
Interior/Exterior Lathing 11/30/2021 Partial Approval HENRY KIM
Gas Test 1/12/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 1/12/2022 Approved SEAN WIRCH
Service/Power Release 1/28/2022 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved SEAN WIRCH
Underground Mechanical 2/25/2022 Approved SEAN WIRCH
ELECTRICAL-Final 3/4/2022 Approved SEAN WIRCH
HVAC-Final 3/4/2022 Approved SEAN WIRCH
PLUMBING-Final 3/4/2022 Approved SEAN WIRCH
Final 3/9/2022 OK to Issue CofO SEAN WIRCH
Green Building Final 3/9/2022 Approved SEAN WIRCH
Smoke Detectors 3/9/2022 Approved SEAN WIRCH