8063 N VANTAGE AVE 91605

Certificate Information: 8063 N VANTAGE AVE 91605

Application / Permit
19010-20000-05691
Plan Check / Job No.
B19VN21725
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'x34'-9", TWO STORY, ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 5/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 SEAN SHAHMIRI
Corrections Issued 1/13/2020 SEAN SHAHMIRI
Green Plans Picked Up 1/24/2020 APPLICANT
Quality Review Completed 2/3/2020 OMID HEDAYAT
Building Plans Picked Up 2/6/2020 APPLICANT
Applicant returned to address corrections 4/22/2020 SEAN SHAHMIRI
Plan Check Approved 4/22/2020 SEAN SHAHMIRI
Plan Check Approved 4/22/2020 JOSE VELAZQUEZ
Issued 5/19/2020 LADBS
CofO in Progress 3/12/2021 JOHN HAYES
CofO Issued 6/26/2021 MICHAEL SMITH
Permit Finaled 6/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/21/2020 GUILLERMO PETRA
Low Impact Development Cleared 3/11/2020 AMMAR ELTAWIL
Eng Process Fee Ord 176,300 Cleared 3/13/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/13/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/13/2020 JOHN TRIANTAFYLLOS
Construction near power lines Cleared 3/19/2020 RIDWAN HARDY
Green Code Cleared 3/27/2020 SEAN SHAHMIRI
Hydrant and Access approval Cleared 4/16/2020 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/7/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 7/8/2020 Partial Approval JOHN HAYES
Underground Mechanical 7/9/2020 Approved JOHN HAYES
Footing/Foundation/Slab 7/13/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 7/15/2020 Approved JOHN HAYES
Wood Frame 7/28/2020 Partial Inspection MATTHEW NELSON
ELECTRICAL-Rough 9/15/2020 Partial Approval DAVID MATSON
HVAC-Rough 9/15/2020 Partial Approval DAVID MATSON
PLUMBING-Rough 9/15/2020 Partial Approval DAVID MATSON
Wood Frame 9/15/2020 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 9/18/2020 Approved DAVID MATSON
ELECTRICAL-Rough 9/18/2020 Approved DAVID MATSON
Green Building Rough 9/18/2020 Approved DAVID MATSON
PLUMBING-Rough 9/18/2020 Approved DAVID MATSON
Underground Mechanical 9/18/2020 Approved DAVID MATSON
Verify Sprinkler Sign Off 9/18/2020 Approved DAVID MATSON
Insulation 10/2/2020 Approved JOHN HAYES
Interior/Exterior Lathing 10/2/2020 Partial Approval JOHN HAYES
Shower Pan 10/2/2020 Approved JOHN HAYES
Underground Mechanical 10/6/2020 Approved JOHN HAYES
Drywall Nailing 10/15/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/15/2020 Approved MATTHEW NELSON
Final 2/23/2021 Corrections Issued JOHN HAYES
Green Building Final 2/23/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 2/23/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 2/23/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 2/23/2021 Not Ready for Inspection JOHN HAYES
Final 3/11/2021 OK to Issue CofO JOHN HAYES
Green Building Final 3/11/2021 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Approved JOHN HAYES
Service/Power Release 3/11/2021 Approved JOHN HAYES
Smoke Detectors 3/11/2021 Approved JOHN HAYES