18600 W LANARK ST 91335

Certificate Information: 18600 W LANARK ST 91335

Application / Permit
19010-20000-05678
Plan Check / Job No.
B19VN21718
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(18) Charter School - middle
Work Description
(N) 2-STORY TYPE V-A SCHOOL BUILDING FOR GRADES 6-8 & PARKING LOT PER CPC-2019-6269-CU-ZAA-ACI (NFPA-13 FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 10/4/2021
Issuing Office
Current Status
CofO Issued on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2019 APPLICANT
Assigned to Plan Check Engineer 12/24/2019 NILOOFAR MEHRAIN
Corrections Issued 12/30/2019 NILOOFAR MEHRAIN
Quality Review Completed 1/2/2020 GUANG MIN TUNG
Disabled Access Plans Picked Up 1/2/2020 APPLICANT
Green Plans Picked Up 1/2/2020 APPLICANT
Building Plans Picked Up 1/16/2020 APPLICANT
Applicant returned to address corrections 6/17/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 6/18/2021 NILOOFAR MEHRAIN
Applicant returned to address corrections 8/11/2021 NILOOFAR MEHRAIN
Plan Check Approved 9/21/2021 NILOOFAR MEHRAIN
Issued 10/4/2021 APPLICANT
TCO Issued (Expire Date: 01-30-2023) 8/3/2022 JEFFREY DURAN
CofO in Progress 11/14/2022 DANNY RODRIGUEZ
CofO Issued 11/30/2022 RICKEY JACKSON
Permit Finaled 11/30/2022 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 11/19/2020 LEE GUILBEAUX
Highway dedication Cleared 11/19/2020 LEE GUILBEAUX
Permit Cleared 11/19/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/17/2021 LEE GUILBEAUX
Sewer availability Cleared 5/18/2021 LEE GUILBEAUX
Green Code Cleared 5/26/2021 AARON COSTA
Internal circulation Cleared 6/3/2021 SHEILA AHORAIAN
Trees in Parkway Cleared 6/8/2021 JOHN KIM
"T" removal Cleared 7/29/2021 DANG NGUYEN
CPC Cleared 7/29/2021 DANG NGUYEN
DAS Clearance Cleared 7/29/2021 NILOOFAR MEHRAIN
Frnt yard landscape/Water mgmt Cleared 7/29/2021 DANG NGUYEN
Prkng lot landscape/Water mgmt Cleared 7/29/2021 DANG NGUYEN
Tract Map conditions Cleared 7/29/2021 DANG NGUYEN
Tract Map conditions Cleared 7/29/2021 DANG NGUYEN
ZA Case Cleared 7/29/2021 DANG NGUYEN
Hydrant and Access approval Cleared 7/31/2021 ROBERT DUFF
Fire Marshall Fire Life Safety Cleared 8/3/2021 VIDAL GARCIA
Low Impact Development Cleared 9/9/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/9/2021 CARLOS AGUILERA

Contact Information

Contractor E P I Construction Inc; Lic. No.: 865616-B 12345 VENTURA BLVD SUITE H      STUDIO CITY, CA 91604
Engineer Baroonian,, Armen; Lic. No.: S4227 867 N FAIR OAKS AVE 100      PASADENA, CA 91103

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2021 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/18/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/21/2021 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 10/22/2021 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/2/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 11/2/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/4/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/4/2021 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Concrete 11/8/2021 Conditional Approval KENNETH ROBERTS
Footing/Foundation/Slab 11/9/2021 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 11/12/2021 No Access for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 11/16/2021 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/17/2021 Approved DANNY RODRIGUEZ
Footing/Foundation/Slab 11/17/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/19/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/22/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 11/23/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 11/24/2021 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 12/20/2021 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 12/21/2021 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 1/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 1/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 1/10/2022 Partial Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/11/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/12/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/13/2022 Approved DANNY RODRIGUEZ
Deputy Steel/Welding 1/14/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Steel/Welding 1/18/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 1/31/2022 Approved DANNY RODRIGUEZ
Green Building Rough 2/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 2/1/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 2/1/2022 Partial Inspection DANNY RODRIGUEZ
Deputy Wood Construction 2/4/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Wood Construction 2/8/2022 Conditional Approval DANNY RODRIGUEZ
Green Building Rough 2/8/2022 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 2/8/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 2/8/2022 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 2/14/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/15/2022 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 2/17/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 2/22/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 2/23/2022 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 2/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 2/25/2022 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 2/28/2022 Conditional Approval DANNY RODRIGUEZ
Drywall Nailing 3/1/2022 Partial Approval JEFFREY DURAN
Green Building Rough 3/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/7/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/7/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/8/2022 Partial Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 3/9/2022 Partial Inspection DANNY RODRIGUEZ
Green Building Rough 3/10/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/10/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/10/2022 Corrections Issued DANNY RODRIGUEZ
Insulation 3/11/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 3/14/2022 Partial Approval DANIEL VARNUM
Green Building Rough 3/14/2022 Not Ready for Inspection DANIEL VARNUM
Verify Sprinkler Sign Off 3/14/2022 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 3/15/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 3/16/2022 Approved DANNY RODRIGUEZ
Insulation 3/16/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 3/17/2022 Approved DANNY RODRIGUEZ
Insulation 3/17/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 3/18/2022 Approved DANNY RODRIGUEZ
Drywall Nailing 3/18/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 3/21/2022 Partial Approval DANNY RODRIGUEZ
Structural Steel Frame 3/21/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 3/22/2022 Approved DANNY RODRIGUEZ
Drywall Nailing 3/22/2022 Partial Approval DANNY RODRIGUEZ
Insulation 3/22/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 3/23/2022 Approved DANNY RODRIGUEZ
Drywall Nailing 3/23/2022 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval DANNY RODRIGUEZ
Deputy Wood Construction 3/24/2022 Approved DANNY RODRIGUEZ
Green Building Rough 3/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 3/24/2022 Partial Inspection DANNY RODRIGUEZ
Wood Frame 3/24/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Wood Construction 3/29/2022 Approved DANNY RODRIGUEZ
Drywall Nailing 3/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Insulation 3/29/2022 Not Ready for Inspection DANNY RODRIGUEZ
Wood Frame 3/29/2022 Partial Approval DANNY RODRIGUEZ
Wood Frame 3/30/2022 Partial Approval DANNY RODRIGUEZ
Insulation 4/1/2022 Partial Approval DANNY RODRIGUEZ
Insulation 4/4/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/5/2022 Partial Approval DANNY RODRIGUEZ
Insulation 4/5/2022 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 4/7/2022 Partial Approval CAMERON CHABAN
Green Building Rough 4/7/2022 Not Ready for Inspection CAMERON CHABAN
Insulation 4/7/2022 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 4/7/2022 Not Ready for Inspection CAMERON CHABAN
Drywall Nailing 4/11/2022 Partial Approval DANNY RODRIGUEZ
Green Building Rough 4/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 4/14/2022 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/14/2022 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 4/18/2022 Partial Approval ROBERT DAVIS
Light Gage Steel Frame 4/18/2022 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 4/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 4/25/2022 Not Ready for Inspection DANNY RODRIGUEZ
Light Gage Steel Frame 4/25/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 4/25/2022 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 4/27/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 5/2/2022 Partial Approval DANNY RODRIGUEZ
Insulation 5/4/2022 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/6/2022 Partial Approval DANNY RODRIGUEZ
Insulation 5/6/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 5/6/2022 Partial Approval DANNY RODRIGUEZ
T-Bar Ceiling 5/9/2022 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 5/10/2022 Partial Approval DANNY RODRIGUEZ
Insulation 5/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Drywall Nailing 5/16/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 5/17/2022 Approved DANNY RODRIGUEZ
Light Gage Steel Frame 5/17/2022 Partial Approval DANNY RODRIGUEZ
Verify Sprinkler Sign Off 5/17/2022 Partial Inspection DANNY RODRIGUEZ
Drywall Nailing 5/20/2022 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 6/3/2022 Not Ready for Inspection ANDREW DORSO
Footing/Foundation/Slab 6/10/2022 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 6/10/2022 Not Ready for Inspection JEFFREY FULTON
T-Bar Ceiling 6/13/2022 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/14/2022 Conditional Approval DANNY RODRIGUEZ
Masonry Wall/Backfill 6/15/2022 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 6/15/2022 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 6/16/2022 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/22/2022 Conditional Approval JEFFREY DURAN
Masonry Wall/Backfill 6/23/2022 Corrections Issued DANNY RODRIGUEZ
T-Bar Ceiling 6/23/2022 Corrections Issued DANNY RODRIGUEZ
Masonry Wall/Backfill 6/28/2022 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 7/5/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 7/11/2022 Not Ready for Inspection JEFFREY FULTON
Insulation 7/12/2022 Partial Inspection JEFFREY FULTON
Drywall Nailing 7/14/2022 Partial Inspection JEFFREY FULTON
Final 7/28/2022 Partial Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 7/28/2022 Approved DANNY RODRIGUEZ
Green Building Final 7/28/2022 Approved DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/28/2022 SGSOV Not Ready DANNY RODRIGUEZ
Smoke Detectors 7/28/2022 Approved DANNY RODRIGUEZ
Verify Sprinkler Sign Off 7/28/2022 Approved DANNY RODRIGUEZ
Wood Frame 7/28/2022 Approved DANNY RODRIGUEZ
Final 8/1/2022 Partial Inspection DANNY RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved DANNY RODRIGUEZ
Final 10/17/2022 OK to Issue CofO DANNY RODRIGUEZ