17615 W STARE ST 91325
Certificate Information: 17615 W STARE ST 91325
- Application / Permit
- 19010-20000-05661
- Plan Check / Job No.
- B19VN21687
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED 1-STORY ACCESSORY DWELLING UNIT PER LAMC12.22A33(c)(d) & WFPP
- Permit Issued
- Issued on 1/26/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/8/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/10/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 1/10/2020 | APPLICANT |
| Green Plans Picked Up | 1/23/2020 | APPLICANT |
| Plan Check Approved | 9/28/2021 | NILOOFAR MEHRAIN |
| Issued | 1/26/2022 | APPLICANT |
| CofO in Progress | 12/2/2022 | JAVIER RAMOS JR |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/13/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2020 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 1/13/2020 | GEORGE SUCHAND |
| Permit | Cleared | 1/13/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 1/13/2020 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 3/6/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/6/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/20/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/21/2021 | CARLOS AGUILERA |
| Green Code | Cleared | 9/28/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Ketterling Construction; Lic. No.: 725126-B | 17601 MAYALL STREET NORTHRIDGE, CA 91325 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Shotcrete | 2/15/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 2/15/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 2/15/2022 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 3/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Underground Mechanical | 3/29/2022 | Partial Approval | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 3/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Sewer | 4/5/2022 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 4/11/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/11/2022 | Partial Approval | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 4/11/2022 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 4/13/2022 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/13/2022 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/19/2022 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 4/19/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 4/19/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 4/19/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/29/2022 | Approved | JAVIER RAMOS JR |
| Shower Pan | 4/29/2022 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/1/2022 | Approved | JAVIER RAMOS JR |
| Final | 7/1/2022 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 7/1/2022 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 7/1/2022 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/1/2022 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 9/15/2022 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 9/15/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/30/2022 | Approved | JAVIER RAMOS JR |
| Final | 11/30/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 11/30/2022 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 11/30/2022 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 11/30/2022 | Approved | JAVIER RAMOS JR |
| Final | 12/2/2022 | OK to Issue CofO | JAVIER RAMOS JR |