22847 W SATICOY ST 91304
Certificate Information: 22847 W SATICOY ST 91304
- Application / Permit
- 19010-20000-05656
- Plan Check / Job No.
- B19VN21667
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW(31'-7"x 33'-6") DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/12/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | TROY DEGUZMAN |
| Corrections Issued | 1/16/2020 | TROY DEGUZMAN |
| Quality Review Completed | 1/16/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/21/2020 | APPLICANT |
| Green Plans Picked Up | 1/22/2020 | APPLICANT |
| Applicant returned to address corrections | 2/12/2020 | TROY DEGUZMAN |
| Plan Check Approved | 2/13/2020 | TROY DEGUZMAN |
| Issued | 2/13/2020 | LADBS |
| CofO in Progress | 8/6/2020 | DAVID STEPANYAN |
| Permit Finaled | 8/12/2020 | DONALD SUNSERI |
| CofO Issued | 8/12/2020 | DONALD SUNSERI |
| Permit Finaled | 8/12/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/21/2020 | GABRIEL ROBLES |
| Hydrant and Access approval | Cleared | 1/22/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 1/22/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 1/22/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 2/6/2020 | TROY DEGUZMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Guivatchian,, Mohammad; Lic. No.: C36510 | 4720 DEGOVIA AVENUE WOODLAND HILLS, CA 91364 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/7/2020 | Not Ready for Inspection | RAYMOND KEHOE |
| Underground Mechanical | 3/7/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Rough | 3/9/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 3/16/2020 | Corrections Issued | DAVID STEPANYAN |
| Underground Mechanical | 3/16/2020 | Partial Approval | DAVID STEPANYAN |
| Underground Mechanical | 3/24/2020 | Partial Approval | DAVID STEPANYAN |
| Excavation/Setback/Form/Re-Bar | 3/31/2020 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 3/31/2020 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/3/2020 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 4/9/2020 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 4/24/2020 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/7/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 5/7/2020 | Corrections Issued | DAVID STEPANYAN |
| Deputy Drilled-In Anchors | 5/12/2020 | Conditional Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 5/14/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 5/14/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 5/14/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| ELECTRICAL-Rough | 5/27/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 5/27/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 5/27/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 5/27/2020 | Corrections Issued | DAVID STEPANYAN |
| Verify Sprinkler Sign Off | 5/27/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/4/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 6/4/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 6/4/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 6/4/2020 | Approved | DAVID STEPANYAN |
| Insulation | 6/9/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 6/15/2020 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 7/10/2020 | Approved | DAVID STEPANYAN |
| Final | 7/10/2020 | Corrections Issued | DAVID STEPANYAN |
| Green Building Final | 7/10/2020 | Approved | DAVID STEPANYAN |
| HVAC-Final | 7/10/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 7/10/2020 | Corrections Issued | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2020 | SGSOV Not Ready | DAVID STEPANYAN |
| Service/Power Release | 7/10/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Smoke Detectors | 7/10/2020 | Approved | DAVID STEPANYAN |
| PLUMBING-Final | 7/15/2020 | Approved | DAVID STEPANYAN |
| Final | 8/6/2020 | OK to Issue CofO | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2020 | SGSOV Approved | DAVID STEPANYAN |
| Service/Power Release | 8/6/2020 | Approved | DAVID STEPANYAN |