22847 W SATICOY ST 91304

Certificate Information: 22847 W SATICOY ST 91304

Application / Permit
19010-20000-05656
Plan Check / Job No.
B19VN21667
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW(31'-7"x 33'-6") DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER.
Permit Issued
Issued on 2/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2019 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 TROY DEGUZMAN
Corrections Issued 1/16/2020 TROY DEGUZMAN
Quality Review Completed 1/16/2020 CHON CHIO KUO
Building Plans Picked Up 1/21/2020 APPLICANT
Green Plans Picked Up 1/22/2020 APPLICANT
Applicant returned to address corrections 2/12/2020 TROY DEGUZMAN
Plan Check Approved 2/13/2020 TROY DEGUZMAN
Issued 2/13/2020 LADBS
CofO in Progress 8/6/2020 DAVID STEPANYAN
Permit Finaled 8/12/2020 DONALD SUNSERI
CofO Issued 8/12/2020 DONALD SUNSERI
Permit Finaled 8/12/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 1/21/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/21/2020 GABRIEL ROBLES
Sewer availability Cleared 1/21/2020 GABRIEL ROBLES
Hydrant and Access approval Cleared 1/22/2020 JEREMY CARTER
Low Impact Development Cleared 1/22/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/22/2020 EMIL KYUPELYAN
Green Code Cleared 2/6/2020 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Guivatchian,, Mohammad; Lic. No.: C36510 4720 DEGOVIA AVENUE      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/7/2020 Not Ready for Inspection RAYMOND KEHOE
Underground Mechanical 3/7/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 3/9/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 3/16/2020 Corrections Issued DAVID STEPANYAN
Underground Mechanical 3/16/2020 Partial Approval DAVID STEPANYAN
Underground Mechanical 3/24/2020 Partial Approval DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 3/31/2020 Approved JOHN KIDWELL
Footing/Foundation/Slab 3/31/2020 Approved JOHN KIDWELL
Footing/Foundation/Slab 4/3/2020 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 4/9/2020 Conditional Approval HENRY KIM
Footing/Foundation/Slab 4/24/2020 Approved JOHN KIDWELL
BUILDING-Rough-Frame 5/7/2020 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 5/7/2020 Corrections Issued DAVID STEPANYAN
Deputy Drilled-In Anchors 5/12/2020 Conditional Approval DAVID STEPANYAN
BUILDING-Rough-Frame 5/14/2020 Partial Approval DAVID STEPANYAN
Green Building Rough 5/14/2020 Not Ready for Inspection DAVID STEPANYAN
Verify Sprinkler Sign Off 5/14/2020 Not Ready for Inspection DAVID STEPANYAN
ELECTRICAL-Rough 5/27/2020 Approved DAVID STEPANYAN
Green Building Rough 5/27/2020 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 5/27/2020 Corrections Issued DAVID STEPANYAN
PLUMBING-Rough 5/27/2020 Approved DAVID STEPANYAN
Underground Mechanical 5/27/2020 Corrections Issued DAVID STEPANYAN
Verify Sprinkler Sign Off 5/27/2020 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 6/4/2020 Approved DAVID STEPANYAN
Green Building Rough 6/4/2020 Approved DAVID STEPANYAN
HVAC-Rough 6/4/2020 Approved DAVID STEPANYAN
Underground Mechanical 6/4/2020 Approved DAVID STEPANYAN
Insulation 6/9/2020 Approved DAVID STEPANYAN
Drywall Nailing 6/15/2020 Approved DAVID STEPANYAN
ELECTRICAL-Final 7/10/2020 Approved DAVID STEPANYAN
Final 7/10/2020 Corrections Issued DAVID STEPANYAN
Green Building Final 7/10/2020 Approved DAVID STEPANYAN
HVAC-Final 7/10/2020 Approved DAVID STEPANYAN
PLUMBING-Final 7/10/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 7/10/2020 SGSOV Not Ready DAVID STEPANYAN
Service/Power Release 7/10/2020 Not Ready for Inspection DAVID STEPANYAN
Smoke Detectors 7/10/2020 Approved DAVID STEPANYAN
PLUMBING-Final 7/15/2020 Approved DAVID STEPANYAN
Final 8/6/2020 OK to Issue CofO DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 8/6/2020 SGSOV Approved DAVID STEPANYAN
Service/Power Release 8/6/2020 Approved DAVID STEPANYAN