11260 W OSBORNE ST 91342
Certificate Information: 11260 W OSBORNE ST 91342
- Application / Permit
- 19010-20000-05618
- Plan Check / Job No.
- B19VN21605
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (60'-0"x 20'-0") DETACHED 1-STORY ACCESSORY DWELLING UNIT W/ (15'-0"x 5'-0") COV PORCH PER AB 494 AND SB 229. PER LA STD WFPP. NFPA-13D FIRE SPRINKLER THROUGHOUT. "COMPLY WITH DEPARTMENT ORDER effective date 01/16/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 6/3/2021
- Issuing Office
- Current Status
- CofO Issued on 4/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | TROY DEGUZMAN |
| Corrections Issued | 1/8/2020 | TROY DEGUZMAN |
| Quality Review Completed | 1/9/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/10/2020 | APPLICANT |
| Green Plans Picked Up | 1/22/2020 | APPLICANT |
| Applicant returned to address corrections | 6/2/2021 | TROY DEGUZMAN |
| Plan Check Approved | 6/3/2021 | TROY DEGUZMAN |
| Issued | 6/3/2021 | APPLICANT |
| CofO in Progress | 2/8/2024 | AGUSTIN ALVAREZMORALES |
| Permit Finaled | 4/5/2024 | DAVID JAMES |
| CofO Issued | 4/5/2024 | DAVID JAMES |
| Permit Finaled | 4/5/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/19/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 1/19/2021 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 2/26/2021 | SARAH YOUSSEF |
| Specific Plan | Cleared | 3/10/2021 | PEGGY MALONE-BROWN |
| ZI | Cleared | 3/10/2021 | PEGGY MALONE-BROWN |
| Roof/Waste drainage to street | Cleared | 3/22/2021 | ADRIAN CASTRO |
| Green Code | Cleared | 5/7/2021 | DAVID MATSON |
Contact Information
| No Data Available. |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/16/2021 | Approved | JASON BRANNON |
| Excavation/Setback/Form/Re-Bar | 8/3/2021 | Not Ready for Inspection | JASON BRANNON |
| Pre-Inspection | 8/3/2021 | Approved | JASON BRANNON |
| Excavation/Setback/Form/Re-Bar | 11/2/2021 | Partial Inspection | JASON BRANNON |
| Sewer | 1/25/2022 | Approved | JASON BRANNON |
| Underground Mechanical | 1/25/2022 | Approved | JASON BRANNON |
| Footing/Foundation/Slab | 3/31/2022 | Approved | JASON BRANNON |
| Deputy Drilled-In Anchors | 4/20/2022 | Approved | JASON BRANNON |
| BUILDING-Rough-Frame | 4/13/2023 | Partial Inspection | JASON BRANNON |
| ELECTRICAL-Rough | 4/13/2023 | Approved | JASON BRANNON |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Approved | JASON BRANNON |
| Green Building Rough | 4/13/2023 | Approved | JASON BRANNON |
| HVAC-Rough | 4/13/2023 | Approved | JASON BRANNON |
| MERV13>=Rough | 4/13/2023 | Approved | JASON BRANNON |
| PLUMBING-Rough | 4/13/2023 | Approved | JASON BRANNON |
| Verify Sprinkler Sign Off | 4/13/2023 | Not Ready for Inspection | JASON BRANNON |
| Wood Frame | 6/12/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Insulation | 6/14/2023 | Approved | JASON BRANNON |
| Drywall Nailing | 6/20/2023 | Partial Inspection | JASON BRANNON |
| Interior/Exterior Lathing | 6/29/2023 | Approved | AGUSTIN ALVAREZMORALES |
| BUILDING-Rough-Frame | 9/14/2023 | Partial Approval | AGUSTIN ALVAREZMORALES |
| Drywall Nailing | 9/14/2023 | Approved | AGUSTIN ALVAREZMORALES |
| ELECTRICAL-Final | 9/14/2023 | Partial Approval | AGUSTIN ALVAREZMORALES |
| Final | 9/14/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Green Building Final | 9/14/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| HVAC-Final | 9/14/2023 | Approved | AGUSTIN ALVAREZMORALES |
| MERV13>=Final | 9/14/2023 | Approved | AGUSTIN ALVAREZMORALES |
| PLUMBING-Final | 9/14/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| SGSOV-Seismic Gas S/O Valve | 9/14/2023 | SGSOV Not Ready | AGUSTIN ALVAREZMORALES |
| Service/Power Release | 9/14/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Smoke Detectors | 9/14/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Verify Sprinkler Sign Off | 9/14/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| BUILDING-Rough-Frame | 9/19/2023 | Partial Inspection | AGUSTIN ALVAREZMORALES |
| ELECTRICAL-Final | 9/19/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Final | 9/19/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Green Building Final | 9/19/2023 | Corrections Issued | AGUSTIN ALVAREZMORALES |
| HVAC-Final | 9/19/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| PLUMBING-Final | 9/19/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Not Ready | AGUSTIN ALVAREZMORALES |
| Service/Power Release | 9/19/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Verify Sprinkler Sign Off | 9/19/2023 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | AGUSTIN ALVAREZMORALES |
| ELECTRICAL-Final | 11/3/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 11/3/2023 | Conditional Approval | AGUSTIN ALVAREZMORALES |
| Green Building Final | 11/3/2023 | Approved | AGUSTIN ALVAREZMORALES |
| HVAC-Final | 11/3/2023 | Approved | AGUSTIN ALVAREZMORALES |
| PLUMBING-Final | 11/3/2023 | Approved | AGUSTIN ALVAREZMORALES |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Approved | AGUSTIN ALVAREZMORALES |
| Service/Power Release | 11/3/2023 | Approved | AGUSTIN ALVAREZMORALES |
| Verify Sprinkler Sign Off | 11/3/2023 | Approved | AGUSTIN ALVAREZMORALES |