17252 W RAYMER ST 91325

Certificate Information: 17252 W RAYMER ST 91325

Application / Permit
19010-20000-05613
Plan Check / Job No.
B19VN21583
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 68'-9" X 39'-6" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED GARAGE
Permit Issued
Issued on 2/26/2021
Issuing Office
Current Status
CofO Issued on 12/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 SELLA BENYAMIN
Corrections Issued 1/15/2020 SELLA BENYAMIN
Quality Review Completed 1/16/2020 STEVEN KIM
Building Plans Picked Up 1/21/2020 APPLICANT
Green Plans Picked Up 1/31/2020 APPLICANT
Plan Check Approved 9/25/2020 SELLA BENYAMIN
Issued 2/26/2021 APPLICANT
CofO in Progress 9/3/2024 JAVIER RAMOS JR
CofO in Progress 9/3/2024 JAVIER RAMOS JR
CofO in Progress 9/20/2024 JAVIER RAMOS JR
No Progress 10/22/2024 ROBERT GOLD
CofO in Progress 10/22/2024 ROBERT GOLD
No Progress 10/28/2024 ROBERT GOLD
CofO in Progress 10/28/2024 ROBERT GOLD
No Progress 12/17/2024 ROBERT GOLD
CofO in Progress 12/17/2024 ROBERT GOLD
Permit Finaled 12/19/2024 RUBEN SALAS
CofO Issued 12/19/2024 RUBEN SALAS
Permit Finaled 12/19/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/29/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/31/2020 GUILLERMO PETRA
Sewer availability Cleared 8/3/2020 GABRIEL ROBLES
Low Impact Development Cleared 8/25/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 8/27/2020 GABRIEL ROBLES
Green Code Cleared 9/15/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/8/2021 Partial Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 3/12/2021 Not Ready for Inspection MARK JOHNSON
Excavation/Setback/Form/Re-Bar 3/17/2021 Approved MARK JOHNSON
PLUMBING-Rough 5/24/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 6/8/2021 Approved MARK JOHNSON
HVAC-Rough 6/8/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/28/2021 Not Ready for Inspection MARK JOHNSON
Green Building Rough 6/28/2021 Not Ready for Inspection MARK JOHNSON
Verify Sprinkler Sign Off 6/28/2021 Approved MARK JOHNSON
Deputy Wood Construction 7/15/2021 No Access for Inspection MARK JOHNSON
BUILDING-Rough-Frame 7/19/2021 Partial Approval MARK JOHNSON
Green Building Rough 7/19/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 7/26/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 7/26/2021 Partial Approval MARK JOHNSON
Pre-Inspection 7/26/2021 Partial Inspection MARK JOHNSON
Interior/Exterior Lathing 7/28/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
Gas Test 8/20/2021 Not Ready for Inspection MARK JOHNSON
Insulation 8/20/2021 Approved MARK JOHNSON
Shower Pan 8/20/2021 Not Ready for Inspection MARK JOHNSON
Gas Test 8/24/2021 Not Ready for Inspection MARK JOHNSON
Shower Pan 8/24/2021 Approved MARK JOHNSON
Drywall Nailing 8/27/2021 Approved MARK JOHNSON
Gas Test 9/1/2021 Not Ready for Inspection MARK JOHNSON
Interior/Exterior Lathing 9/3/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 9/9/2021 Approved ADAM ESCOTO
Sewer 8/3/2022 Not Ready for Inspection JAVIER RAMOS JR
Sewer 8/8/2022 Approved JAVIER RAMOS JR
Underground Mechanical 8/15/2022 Approved JAVIER RAMOS JR
Pre-Inspection 9/26/2022 Approved JAVIER RAMOS JR
Gas Test 4/2/2024 Approved MATTHEW NELSON
Pre-Inspection 5/16/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 8/19/2024 Corrections Issued SALVADOR MARTINEZ
HVAC-Final 8/19/2024 Approved SALVADOR MARTINEZ
PLUMBING-Final 8/19/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 8/23/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 8/23/2024 Approved JAVIER RAMOS JR
Final 8/30/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 8/30/2024 Approved JAVIER RAMOS JR
Green Building Final 8/30/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/30/2024 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 8/30/2024 Approved JAVIER RAMOS JR
Smoke Detectors 8/30/2024 Approved JAVIER RAMOS JR
Final 9/20/2024 OK to Issue CofO JAVIER RAMOS JR