12436 W MILBANK ST 91604

Certificate Information: 12436 W MILBANK ST 91604

Application / Permit
19010-20000-05612
Plan Check / Job No.
B19VN21579
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 91'-6" x 42'-1" irregular shape Fully Sprinklered (NFPA-13D) Two-Story Single Family Dwelling with Basement & attached Two-Car Garage.
Permit Issued
Issued on 5/29/2020
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 1/6/2020 OMID HEDAYAT
Corrections Issued 1/16/2020 OMID HEDAYAT
Quality Review Completed 1/16/2020 STEVEN KIM
Building Plans Picked Up 1/21/2020 APPLICANT
Green Plans Picked Up 1/21/2020 APPLICANT
Applicant returned to address corrections 1/30/2020 OMID HEDAYAT
Applicant returned to address corrections 4/2/2020 OMID HEDAYAT
Applicant returned to address corrections 4/27/2020 OMID HEDAYAT
Plan Check Approved 4/28/2020 OMID HEDAYAT
Issued 5/29/2020 APPLICANT
CofO in Progress 11/29/2021 ARAM AVEDISIAN
Permit Finaled 1/29/2022 MICHAEL SMITH
CofO Issued 1/29/2022 MICHAEL SMITH
Permit Finaled 1/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/23/2020 GEORGE SUCHAND
Address approval Cleared 1/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/24/2020 ADRIAN CASTRO
Permit Cleared 1/24/2020 ADRIAN CASTRO
Sewer availability Cleared 1/24/2020 ADRIAN CASTRO
Trees in Parkway Cleared 1/27/2020 JOHN KIM
Low Impact Development Cleared 3/3/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 3/3/2020 ADRIAN CASTRO
Green Code Cleared 3/17/2020 MICHAEL AYERS
ZI Cleared 4/13/2020 PABLO ESTRADA
Hold Cleared 6/24/2020 JASON SHEETS

Contact Information

Contractor Eldav Construction & Development Inc; Lic. No.: 949125-B 19562 VENTURA BLVD #223      TARZANA, CA 91356
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 1722 CEDAR STREET APT G      ALHAMBRA, CA 91801
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/7/2020 Partial Approval JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/11/2020 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 8/11/2020 Partial Approval ARAM AVEDISIAN
Deputy Drilled-In Anchors 9/24/2020 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 9/30/2020 Partial Approval DAVID MATSON
Footing/Foundation/Slab 10/8/2020 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 10/13/2020 Approved ARAM AVEDISIAN
Deputy Steel/Welding 10/20/2020 Conditional Approval ARAM AVEDISIAN
Deputy Steel/Welding 10/23/2020 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Partial Approval ARAM AVEDISIAN
Deputy Steel/Welding 10/30/2020 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 12/23/2020 Approved ARAM AVEDISIAN
HVAC-Rough 1/12/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 1/12/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 2/12/2021 Partial Approval ARAM AVEDISIAN
Insulation 2/19/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 2/25/2021 Approved ARAM AVEDISIAN
Drywall Nailing 2/25/2021 Approved ARAM AVEDISIAN
Green Building Rough 2/25/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 2/25/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 3/10/2021 Approved JOHN HAYES
Shower Pan 3/10/2021 Approved JOHN HAYES
Final 9/20/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 9/20/2021 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 9/20/2021 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 9/20/2021 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Final 9/24/2021 Approved ARAM AVEDISIAN
Final 11/4/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 11/4/2021 Approved ARAM AVEDISIAN
Smoke Detectors 11/4/2021 Approved ARAM AVEDISIAN
Final 11/29/2021 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 11/29/2021 Approved ARAM AVEDISIAN