6334 N ORION AVE 91411

Certificate Information: 6334 N ORION AVE 91411

Application / Permit
19010-20000-05610
Plan Check / Job No.
B19VN21569
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 3/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/12/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2019 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 SELLA BENYAMIN
Corrections Issued 1/22/2020 SELLA BENYAMIN
Green Plans Picked Up 1/23/2020 APPLICANT
Quality Review Completed 1/24/2020 STEVEN KIM
Building Plans Picked Up 1/24/2020 APPLICANT
Plan Check Approved 3/6/2020 SELLA BENYAMIN
Issued 3/6/2020 LADBS
CofO in Progress 12/4/2020 MICHAEL TEMPLE
Permit Finaled 12/12/2020 MICHAEL SMITH
CofO Issued 12/12/2020 MICHAEL SMITH
Permit Finaled 12/12/2020 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 1/22/2020 MITESH PATEL
Address approval Cleared 1/23/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 1/23/2020 JOHN LIN
Roof/Waste drainage to street Cleared 1/23/2020 JOHN LIN
Sewer availability Cleared 1/23/2020 JOHN LIN
Green Code Cleared 2/3/2020 DAVID MATSON
Hydrant and Access approval Cleared 2/5/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Sayah,, Daniel Hoshyar; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/29/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 5/12/2020 Partial Approval MISAEL ESPARZA
Green Building Rough 5/12/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/12/2020 Partial Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 5/12/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/26/2020 Approved MISAEL ESPARZA
ELECTRICAL-Rough 7/2/2020 Approved MISAEL ESPARZA
Gas Test 7/2/2020 Partial Approval MISAEL ESPARZA
HVAC-Rough 7/2/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/2/2020 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 7/2/2020 Approved MISAEL ESPARZA
Sewer 7/8/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 7/15/2020 Conditional Approval MISAEL ESPARZA
Insulation 7/15/2020 Approved MISAEL ESPARZA
Drywall Nailing 7/21/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 7/27/2020 Approved WILLIAM KUEHN
Sewer 7/27/2020 Approved WILLIAM KUEHN
Shower Pan 7/27/2020 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 9/28/2020 No Access for Inspection WILLIAM KUEHN
ELECTRICAL-Final 9/28/2020 No Access for Inspection WILLIAM KUEHN
Final 9/28/2020 No Access for Inspection WILLIAM KUEHN
Footing/Foundation/Slab 9/28/2020 Not Ready for Inspection WILLIAM KUEHN
Green Building Final 9/28/2020 No Access for Inspection WILLIAM KUEHN
Green Building Rough 9/28/2020 No Access for Inspection WILLIAM KUEHN
HVAC-Final 9/28/2020 No Access for Inspection WILLIAM KUEHN
PLUMBING-Final 9/28/2020 No Access for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 9/28/2020 SGSOV Not Ready WILLIAM KUEHN
Service/Power Release 9/28/2020 No Access for Inspection WILLIAM KUEHN
Smoke Detectors 9/28/2020 No Access for Inspection WILLIAM KUEHN
Verify Sprinkler Sign Off 9/28/2020 No Access for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 10/6/2020 Approved WILLIAM KUEHN
ELECTRICAL-Final 10/6/2020 Approved WILLIAM KUEHN
Final 10/6/2020 Corrections Issued WILLIAM KUEHN
Footing/Foundation/Slab 10/6/2020 Approved WILLIAM KUEHN
Green Building Final 10/6/2020 Approved WILLIAM KUEHN
Green Building Rough 10/6/2020 Approved WILLIAM KUEHN
HVAC-Final 10/6/2020 Approved WILLIAM KUEHN
PLUMBING-Final 10/6/2020 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 10/6/2020 SGSOV Not Ready WILLIAM KUEHN
Service/Power Release 10/6/2020 Not Required WILLIAM KUEHN
Smoke Detectors 10/6/2020 Approved WILLIAM KUEHN
Verify Sprinkler Sign Off 10/6/2020 Approved WILLIAM KUEHN
ELECTRICAL-Final 10/14/2020 Approved MATTHEW NELSON
Final 10/14/2020 OK to Issue CofO MATTHEW NELSON
HVAC-Final 10/14/2020 Approved MATTHEW NELSON
PLUMBING-Final 10/14/2020 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/14/2020 SGSOV Approved MATTHEW NELSON
Service/Power Release 10/14/2020 Approved MATTHEW NELSON