6334 N ORION AVE 91411
Certificate Information: 6334 N ORION AVE 91411
- Application / Permit
- 19010-20000-05610
- Plan Check / Job No.
- B19VN21569
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/12/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2020 | SELLA BENYAMIN |
| Corrections Issued | 1/22/2020 | SELLA BENYAMIN |
| Green Plans Picked Up | 1/23/2020 | APPLICANT |
| Quality Review Completed | 1/24/2020 | STEVEN KIM |
| Building Plans Picked Up | 1/24/2020 | APPLICANT |
| Plan Check Approved | 3/6/2020 | SELLA BENYAMIN |
| Issued | 3/6/2020 | LADBS |
| CofO in Progress | 12/4/2020 | MICHAEL TEMPLE |
| Permit Finaled | 12/12/2020 | MICHAEL SMITH |
| CofO Issued | 12/12/2020 | MICHAEL SMITH |
| Permit Finaled | 12/12/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/22/2020 | MITESH PATEL |
| Address approval | Cleared | 1/23/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/23/2020 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 1/23/2020 | JOHN LIN |
| Sewer availability | Cleared | 1/23/2020 | JOHN LIN |
| Green Code | Cleared | 2/3/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 2/5/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel Hoshyar; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/29/2020 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/12/2020 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 5/12/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 5/12/2020 | Partial Approval | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 5/12/2020 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 7/2/2020 | Approved | MISAEL ESPARZA |
| Gas Test | 7/2/2020 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 7/2/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/2/2020 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 7/2/2020 | Approved | MISAEL ESPARZA |
| Sewer | 7/8/2020 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 7/15/2020 | Conditional Approval | MISAEL ESPARZA |
| Insulation | 7/15/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 7/21/2020 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 7/27/2020 | Approved | WILLIAM KUEHN |
| Sewer | 7/27/2020 | Approved | WILLIAM KUEHN |
| Shower Pan | 7/27/2020 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| ELECTRICAL-Final | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| Final | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| Footing/Foundation/Slab | 9/28/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Final | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| Green Building Rough | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| HVAC-Final | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| PLUMBING-Final | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 9/28/2020 | SGSOV Not Ready | WILLIAM KUEHN |
| Service/Power Release | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| Smoke Detectors | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 9/28/2020 | No Access for Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/6/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 10/6/2020 | Approved | WILLIAM KUEHN |
| Final | 10/6/2020 | Corrections Issued | WILLIAM KUEHN |
| Footing/Foundation/Slab | 10/6/2020 | Approved | WILLIAM KUEHN |
| Green Building Final | 10/6/2020 | Approved | WILLIAM KUEHN |
| Green Building Rough | 10/6/2020 | Approved | WILLIAM KUEHN |
| HVAC-Final | 10/6/2020 | Approved | WILLIAM KUEHN |
| PLUMBING-Final | 10/6/2020 | Approved | WILLIAM KUEHN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2020 | SGSOV Not Ready | WILLIAM KUEHN |
| Service/Power Release | 10/6/2020 | Not Required | WILLIAM KUEHN |
| Smoke Detectors | 10/6/2020 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 10/6/2020 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Final | 10/14/2020 | Approved | MATTHEW NELSON |
| Final | 10/14/2020 | OK to Issue CofO | MATTHEW NELSON |
| HVAC-Final | 10/14/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 10/14/2020 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 10/14/2020 | Approved | MATTHEW NELSON |