NEW 20' x 20' detached GARAGE.
Permit Issued
Issued on 2/18/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 LUIS RINCON
Corrections Issued 7/22/2019 LUIS RINCON
Quality Review Completed 7/26/2019 OMID HEDAYAT
Building Plans Picked Up 7/31/2019 APPLICANT
Green Plans Picked Up 7/31/2019 APPLICANT
Plan Check Approved 2/14/2020 LUIS RINCON
Issued 2/18/2020 LADBS
CofO in Progress 8/17/2021 RUBEN SALAS
CofO Issued 8/17/2021 DEROLD HAUFF
Permit Finaled 8/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 2/3/2020 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 2/14/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 2/14/2020 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 1551 RANDALL ST      GLENDALE, CA 91201

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/24/2020 Partial Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 3/9/2020 Corrections Issued DAVID CHAN
Excavation/Setback/Form/Re-Bar 3/12/2020 Corrections Issued DAVID CHAN
Excavation/Setback/Form/Re-Bar 3/17/2020 Partial Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 3/19/2020 Approved MATTHEW NUCKOLLS
Wood Frame 5/4/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 6/5/2020 Approved DAVID CHAN
Wood Frame 6/5/2020 Corrections Issued DAVID CHAN
Wood Frame 6/15/2020 Approved DAVID CHAN
Drywall Nailing 8/28/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 8/28/2020 Approved RUBEN SALAS
BUILDING-Rough-Frame 9/29/2020 Approved DAVID CHAN
Final 9/29/2020 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 9/29/2020 Approved DAVID CHAN
METHANE-Barrier 9/29/2020 Approved DAVID CHAN
METHANE-Final 9/29/2020 Approved DAVID CHAN
METHANE-Rough 9/29/2020 Approved DAVID CHAN
METHANE-Subgrade 9/29/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 9/29/2020 SGSOV Not Ready DAVID CHAN
Smoke Detectors 9/29/2020 Approved DAVID CHAN
Final 10/16/2020 Partial Inspection DAVID CHAN
SGSOV-Seismic Gas S/O Valve 10/16/2020 SGSOV Approved DAVID CHAN
Final 3/17/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Service/Power Release 3/17/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Final 5/13/2021 Not Ready for Inspection DAVID FEILER
Service/Power Release 5/13/2021 Not Ready for Inspection DAVID FEILER
Final 7/26/2021 Not Ready for Inspection RUBEN SALAS
Service/Power Release 7/26/2021 Not Ready for Inspection RUBEN SALAS
Final 8/17/2021 OK to Issue CofO RUBEN SALAS
Service/Power Release 8/17/2021 Approved RUBEN SALAS