4565 N ENCINO AVE 91316
Certificate Information: 4565 N ENCINO AVE 91316
- Application / Permit
- 19010-20000-05526
- Plan Check / Job No.
- B19VN21277
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 26' X 28' ACCESSORY LIVING QUARTERS; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/2/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | SELLA BENYAMIN |
| Corrections Issued | 12/16/2019 | SELLA BENYAMIN |
| Quality Review Completed | 12/17/2019 | STEVEN KIM |
| Building Plans Picked Up | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 1/14/2020 | APPLICANT |
| Plan Check Approved | 1/22/2020 | SELLA BENYAMIN |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 10/5/2021 | RONALD COWAN |
| Permit Finaled | 5/2/2022 | RONALD MYRICK |
| CofO Issued | 5/2/2022 | RONALD MYRICK |
| Permit Finaled | 5/2/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Low Impact Development | Cleared | 1/13/2020 | ORVAL HERNANDEZ-MARCIAL |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 1/14/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 1/14/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 1/15/2020 | AARON COSTA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/25/2020 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 8/27/2020 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 9/1/2020 | Approved | RONALD COWAN |
| Deputy Steel/Welding | 9/18/2020 | Approved | DONALD SUNSERI |
| Deputy Wood Construction | 10/26/2020 | Approved | RONALD COWAN |
| Wood Frame | 11/23/2020 | Partial Approval | RONALD COWAN |
| BUILDING-Rough-Frame | 11/24/2020 | Partial Approval | RONALD COWAN |
| Green Building Rough | 11/24/2020 | Approved | RONALD COWAN |
| PLUMBING-Rough | 11/24/2020 | Approved | RONALD COWAN |
| Verify Sprinkler Sign Off | 11/24/2020 | Not Ready for Inspection | RONALD COWAN |
| Wood Frame | 11/24/2020 | Partial Approval | RONALD COWAN |
| BUILDING-Rough-Frame | 2/1/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 2/1/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2021 | Approved | RONALD COWAN |
| Gas Test | 2/1/2021 | Approved | RONALD COWAN |
| HVAC-Rough | 2/1/2021 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 2/1/2021 | Approved | RONALD COWAN |
| PLUMBING-Rough | 2/1/2021 | Approved | RONALD COWAN |
| Rough-Elec/Plmb/HVAC | 2/1/2021 | Approved | RONALD COWAN |
| Sewer | 2/1/2021 | Approved | RONALD COWAN |
| Shower Pan | 2/1/2021 | Approved | RONALD COWAN |
| Verify Sprinkler Sign Off | 2/1/2021 | Approved | RONALD COWAN |
| Insulation | 2/11/2021 | Partial Approval | RONALD COWAN |
| ELECTRICAL-Final | 9/14/2021 | Approved | RONALD COWAN |
| Final | 9/14/2021 | Corrections Issued | RONALD COWAN |
| Green Building Final | 9/14/2021 | Approved | RONALD COWAN |
| HVAC-Final | 9/14/2021 | Approved | RONALD COWAN |
| PLUMBING-Final | 9/14/2021 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 9/14/2021 | SGSOV Not Ready | RONALD COWAN |
| Service/Power Release | 9/14/2021 | Not Required | RONALD COWAN |
| Smoke Detectors | 9/14/2021 | Approved | RONALD COWAN |
| Final | 9/29/2021 | OK to Issue CofO | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 9/29/2021 | SGSOV Approved | RONALD COWAN |