5540 W SMILEY DR 90016

Certificate Information: 5540 W SMILEY DR 90016

Application / Permit
19010-20000-05476
Plan Check / Job No.
B19VN21179
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (20'-0"x 25'-0") DETACHED TWO-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER.
Permit Issued
Issued on 6/24/2020
Issuing Office
Valley
Current Status
Issued on 6/24/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 TROY DEGUZMAN
Corrections Issued 1/10/2020 TROY DEGUZMAN
Green Plans Picked Up 1/10/2020 APPLICANT
Quality Review Completed 1/13/2020 CHON CHIO KUO
Building Plans Picked Up 1/13/2020 APPLICANT
Applicant returned to address corrections 4/6/2020 TROY DEGUZMAN
Applicant returned to address corrections 4/10/2020 TROY DEGUZMAN
Plan Check Approved 5/31/2020 TROY DEGUZMAN
Issued 6/24/2020 LADBS

Permit Application Clearance Information

Address approval Cleared 3/9/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/9/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 3/9/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/9/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 3/10/2020 ROBERT DUFF
Green Code Cleared 3/18/2020 TROY DEGUZMAN
Sewer availability Cleared 3/25/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Aten Enterprises; Lic. No.: 782418-B 900 WHITE KNOLL      LOS ANGELES, CA 90012
Engineer Morales,, Carlos A; Lic. No.: C69972 38100 SAN MATEO AVE      PALMDALE, CA 93551

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/6/2020 Corrections Issued DAVID CHAN
Deputy Reinf. Concrete 7/15/2020 Approved DAVID CHAN
Footing/Foundation/Slab 7/15/2020 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 7/21/2020 Approved DAVID CHAN
Special/Order Compliance 7/21/2020 Corrections Issued DAVID CHAN
Wood Frame 8/25/2020 Partial Approval DAVID CHAN
Interior/Exterior Lathing 9/16/2020 Approved DAVID CHAN
PLUMBING-Rough 9/16/2020 Corrections Issued DAVID CHAN
SGSOV-Seismic Gas S/O Valve 9/16/2020 SGSOV Not Ready DAVID CHAN
ELECTRICAL-Rough 9/18/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 9/18/2020 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Rough 9/23/2020 Approved DAVID CHAN
PLUMBING-Rough 9/23/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 9/28/2020 Approved DAVID CHAN
Green Building Rough 9/28/2020 Approved DAVID CHAN
Insulation 9/28/2020 Approved DAVID CHAN
Verify Sprinkler Sign Off 9/28/2020 Approved DAVID CHAN
Drywall Nailing 9/30/2020 Approved JOSEPH MCGARRY
Service/Power Release 1/8/2021 Corrections Issued DAVID CHAN
Service/Power Release 1/15/2021 Not Ready for Inspection DAVID CHAN
Final 3/17/2021 Not Ready for Inspection DAVID FEILER
Green Building Final 3/17/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Not Ready DAVID FEILER
Service/Power Release 3/17/2021 Not Ready for Inspection DAVID FEILER
Smoke Detectors 3/17/2021 Not Ready for Inspection DAVID FEILER
Special/Order Compliance 3/17/2021 No Access for Inspection HORACE FULTZ
Final 3/25/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Final 3/25/2021 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 3/25/2021 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 3/25/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 4/7/2021 Not Ready for Inspection RUBEN SALAS
Final 4/7/2021 Corrections Issued RUBEN SALAS
Green Building Final 4/7/2021 Approved RUBEN SALAS
HVAC-Final 4/7/2021 Not Ready for Inspection RUBEN SALAS
PLUMBING-Final 4/7/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 4/7/2021 SGSOV Not Ready RUBEN SALAS
Service/Power Release 4/7/2021 Not Ready for Inspection RUBEN SALAS
Smoke Detectors 4/7/2021 Approved RUBEN SALAS
ELECTRICAL-Final 4/14/2021 Approved RUBEN SALAS
Final 4/14/2021 Conditional Approval RUBEN SALAS
HVAC-Final 4/14/2021 Approved RUBEN SALAS
PLUMBING-Final 4/14/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 4/14/2021 SGSOV Approved RUBEN SALAS
Service/Power Release 4/14/2021 Approved RUBEN SALAS