- Permit Issued
- Issued on 6/24/2020
- Issuing Office
- Valley
- Current Status
- Issued on 6/24/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | TROY DEGUZMAN |
| Corrections Issued | 1/10/2020 | TROY DEGUZMAN |
| Green Plans Picked Up | 1/10/2020 | APPLICANT |
| Quality Review Completed | 1/13/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/13/2020 | APPLICANT |
| Applicant returned to address corrections | 4/6/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 4/10/2020 | TROY DEGUZMAN |
| Plan Check Approved | 5/31/2020 | TROY DEGUZMAN |
| Issued | 6/24/2020 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 3/9/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 3/10/2020 | ROBERT DUFF |
| Green Code | Cleared | 3/18/2020 | TROY DEGUZMAN |
| Sewer availability | Cleared | 3/25/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Aten Enterprises; Lic. No.: 782418-B | 900 WHITE KNOLL LOS ANGELES, CA 90012 |
| Engineer | Morales,, Carlos A; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/6/2020 | Corrections Issued | DAVID CHAN |
| Deputy Reinf. Concrete | 7/15/2020 | Approved | DAVID CHAN |
| Footing/Foundation/Slab | 7/15/2020 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 7/21/2020 | Approved | DAVID CHAN |
| Special/Order Compliance | 7/21/2020 | Corrections Issued | DAVID CHAN |
| Wood Frame | 8/25/2020 | Partial Approval | DAVID CHAN |
| Interior/Exterior Lathing | 9/16/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 9/16/2020 | Corrections Issued | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 9/16/2020 | SGSOV Not Ready | DAVID CHAN |
| ELECTRICAL-Rough | 9/18/2020 | Corrections Issued | DAVID CHAN |
| PLUMBING-Rough | 9/18/2020 | Not Ready for Inspection | DAVID CHAN |
| ELECTRICAL-Rough | 9/23/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 9/23/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 9/28/2020 | Approved | DAVID CHAN |
| Green Building Rough | 9/28/2020 | Approved | DAVID CHAN |
| Insulation | 9/28/2020 | Approved | DAVID CHAN |
| Verify Sprinkler Sign Off | 9/28/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 9/30/2020 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 1/8/2021 | Corrections Issued | DAVID CHAN |
| Service/Power Release | 1/15/2021 | Not Ready for Inspection | DAVID CHAN |
| Final | 3/17/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Final | 3/17/2021 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 3/17/2021 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 3/17/2021 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 3/17/2021 | Not Ready for Inspection | DAVID FEILER |
| Special/Order Compliance | 3/17/2021 | No Access for Inspection | HORACE FULTZ |
| Final | 3/25/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 3/25/2021 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 3/25/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 3/25/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 4/7/2021 | Not Ready for Inspection | RUBEN SALAS |
| Final | 4/7/2021 | Corrections Issued | RUBEN SALAS |
| Green Building Final | 4/7/2021 | Approved | RUBEN SALAS |
| HVAC-Final | 4/7/2021 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Final | 4/7/2021 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 4/7/2021 | SGSOV Not Ready | RUBEN SALAS |
| Service/Power Release | 4/7/2021 | Not Ready for Inspection | RUBEN SALAS |
| Smoke Detectors | 4/7/2021 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 4/14/2021 | Approved | RUBEN SALAS |
| Final | 4/14/2021 | Conditional Approval | RUBEN SALAS |
| HVAC-Final | 4/14/2021 | Approved | RUBEN SALAS |
| PLUMBING-Final | 4/14/2021 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 4/14/2021 | SGSOV Approved | RUBEN SALAS |
| Service/Power Release | 4/14/2021 | Approved | RUBEN SALAS |