14825 W DELANO ST 91411

Certificate Information: 14825 W DELANO ST 91411

Application / Permit
19010-20000-05468
Plan Check / Job No.
B19VN21149
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
APARTMENT HOUSE ( WITH 4 UNITS RESERVED FOR EXTREMELY LOW INCOME) OVER BASEMENT GARAGE
Permit Issued
Issued on 8/19/2021
Issuing Office
Valley
Current Status
CofO Corrected on 5/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 RUDOLF KINAR MELIKOFF
Corrections Issued 12/16/2019 RUDOLF KINAR MELIKOFF
Quality Review Completed 12/17/2019 STEVEN KIM
Disabled Access Plans Picked Up 12/23/2019 APPLICANT
Building Plans Picked Up 1/8/2020 APPLICANT
Green Plans Picked Up 1/24/2020 APPLICANT
Applicant returned to address corrections 3/18/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 6/2/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 6/29/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/20/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/22/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 12/29/2020 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 3/16/2021 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 4/14/2021 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 4/15/2021 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 6/4/2021 RUDOLF KINAR MELIKOFF
Applicant returned to address corrections 7/29/2021 RUDOLF KINAR MELIKOFF
Plan Check Approved 8/16/2021 JON BLAINE
Issued 8/19/2021 APPLICANT
CofO in Progress 7/17/2023 CAMERON CHABAN
CofO Issued-Status Void 7/24/2023 RICKEY JACKSON
Permit Finaled-Status Void 7/24/2023 RICKEY JACKSON
Re-Activate Permit 5/1/2024 RICKEY JACKSON
Permit Finaled 5/8/2024 RICKEY JACKSON
CofO Corrected 5/8/2024 RICKEY JACKSON
Permit Finaled 5/8/2024 RICKEY JACKSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/24/2020 APEKSHYA BAJRACHARYA
Address approval Cleared 2/11/2020 JOHN TRIANTAFYLLOS
Driveway location Cleared 5/7/2020 ALBERT ISAGULIAN
Highway dedication Cleared 6/3/2020 LEE GUILBEAUX
Permit Cleared 6/3/2020 LEE GUILBEAUX
Sewer availability Cleared 6/10/2020 LEE GUILBEAUX
Trees in Parkway Cleared 7/7/2020 JOHN KIM
Building over 3-story or 36-ft Cleared 10/5/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 10/5/2020 CALOSHA APPROVED
Density Bonus 12.22.A.31 Cleared 10/13/2020 KENNETH LE
Disturb/Remove Protected Trees Cleared 11/6/2020 STEPHEN DUPREY
Hydrant and Access approval Cleared 11/17/2020 MATTHEW CRAIG
Green Code Cleared 12/8/2020 MICHAEL AYERS
"Q" conditions Cleared 2/26/2021 LAUREN PADICK
CPC Cleared 2/26/2021 LAUREN PADICK
Frnt yard landscape/Water mgmt Cleared 2/26/2021 LAUREN PADICK
Miscellaneous Cleared 2/26/2021 LAUREN PADICK
ZA Case Cleared 2/26/2021 LAUREN PADICK
ZA Case Cleared 2/26/2021 LAUREN PADICK
ZA Case Cleared 2/26/2021 LAUREN PADICK
ZA Case Cleared 2/26/2021 LAUREN PADICK
Construction near power lines Cleared 3/4/2021 WALTER RAMIREZ
DAS Clearance Cleared 3/4/2021 RUDOLF KINAR MELIKOFF
Fire Marshall Fire Life Safety Cleared 3/4/2021 OSCAR SALGADO JR
Low Impact Development Cleared 3/4/2021 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 3/4/2021 GUILLERMO PETRA

Contact Information

Contractor G N L Development Inc; Lic. No.: 981677-B 5939 TOPEKA DRIVE      TARZANA, CA 91356
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 9/7/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 9/7/2021 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 9/7/2021 Partial Inspection CAMERON CHABAN
Deputy Reinf. Concrete 9/8/2021 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 9/8/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/9/2021 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 9/9/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/10/2021 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 9/10/2021 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/13/2021 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 9/13/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/14/2021 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 9/14/2021 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 9/15/2021 Conditional Approval CAMERON CHABAN
Deputy Shotcrete 9/15/2021 Conditional Approval CAMERON CHABAN
Green Building Rough 9/15/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 9/15/2021 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 9/15/2021 Partial Inspection CAMERON CHABAN
Deputy Reinf. Concrete 9/16/2021 Conditional Approval JOHN KITCKO
Deputy Shotcrete 9/16/2021 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 9/21/2021 Conditional Approval JOHN KITCKO
Deputy Shotcrete 9/21/2021 Conditional Approval JOHN KITCKO
Green Building Rough 9/21/2021 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 9/21/2021 Partial Approval DANIEL VARNUM
Verify Sprinkler Sign Off 9/21/2021 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 9/22/2021 Conditional Approval JOHN KITCKO
Deputy Shotcrete 9/22/2021 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 9/23/2021 Conditional Approval RICKEY JACKSON
Deputy Shotcrete 9/23/2021 Conditional Approval RICKEY JACKSON
Deputy Reinf. Concrete 9/24/2021 Conditional Approval RICKEY JACKSON
Deputy Shotcrete 9/24/2021 Conditional Approval RICKEY JACKSON
Footing/Foundation/Slab 10/4/2021 Partial Approval JOHN KITCKO
Grading Pre-Inspection 10/4/2021 Approved JOHN KITCKO
Pre-Inspection 10/6/2021 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 10/26/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 10/27/2021 Conditional Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 12/3/2021 Partial Approval CAMERON CHABAN
Green Building Rough 12/3/2021 Partial Inspection CAMERON CHABAN
Reinforced Concrete Frame 12/3/2021 Partial Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 12/3/2021 Partial Inspection CAMERON CHABAN
Green Building Rough 1/14/2022 Partial Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 1/14/2022 Partial Inspection CAMERON CHABAN
Wood Frame 1/14/2022 Partial Approval CAMERON CHABAN
Masonry Wall/Backfill 2/1/2022 Partial Approval CAMERON CHABAN
Deputy Wood Construction 2/2/2022 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2022 Partial Approval CAMERON CHABAN
Green Building Rough 2/3/2022 Partial Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 2/3/2022 Partial Inspection CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval CAMERON CHABAN
Green Building Rough 2/23/2022 Partial Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 2/23/2022 Partial Inspection CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2022 Partial Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval CAMERON CHABAN
Insulation 3/23/2022 Partial Approval CAMERON CHABAN
Insulation 5/3/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 5/24/2022 Partial Approval CAMERON CHABAN
Green Building Rough 5/24/2022 Partial Inspection CAMERON CHABAN
Insulation 6/2/2022 Partial Approval CAMERON CHABAN
Insulation 7/6/2022 Partial Approval CAMERON CHABAN
Insulation 7/8/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 8/9/2022 Approved CAMERON CHABAN
Green Building Rough 8/9/2022 Approved CAMERON CHABAN
Interior/Exterior Lathing 8/25/2022 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 10/24/2022 Conditional Approval CAMERON CHABAN
Special/Order Compliance 3/14/2023 Partial Inspection CAMERON CHABAN
Special/Order Compliance 5/2/2023 Partial Inspection CAMERON CHABAN
Final 5/31/2023 Not Ready for Inspection CAMERON CHABAN
Footing/Foundation/Slab 5/31/2023 Approved CAMERON CHABAN
Green Building Final 5/31/2023 Not Ready for Inspection CAMERON CHABAN
Reinforced Concrete Frame 5/31/2023 Conditional Approval CAMERON CHABAN
Reinforced Masonry Frame 5/31/2023 Conditional Approval CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 5/31/2023 SGSOV Approved CAMERON CHABAN
Smoke Detectors 5/31/2023 Partial Approval CAMERON CHABAN
Verify Sprinkler Sign Off 5/31/2023 Not Ready for Inspection CAMERON CHABAN
Wood Frame 5/31/2023 Conditional Approval CAMERON CHABAN
Final 6/15/2023 Partial Inspection CAMERON CHABAN
Green Building Final 6/15/2023 Not Ready for Inspection CAMERON CHABAN
Reinforced Concrete Frame 6/15/2023 Conditional Approval CAMERON CHABAN
Reinforced Masonry Frame 6/15/2023 Conditional Approval CAMERON CHABAN
Smoke Detectors 6/15/2023 Not Ready for Inspection CAMERON CHABAN
Verify Sprinkler Sign Off 6/15/2023 Partial Inspection CAMERON CHABAN
Wood Frame 6/15/2023 Conditional Approval CAMERON CHABAN
Final 6/29/2023 Partial Inspection CAMERON CHABAN
Green Building Final 6/29/2023 Approved CAMERON CHABAN
Reinforced Concrete Frame 6/29/2023 Approved CAMERON CHABAN
Reinforced Masonry Frame 6/29/2023 Approved CAMERON CHABAN
Smoke Detectors 6/29/2023 Approved CAMERON CHABAN
Verify Sprinkler Sign Off 6/29/2023 Approved CAMERON CHABAN
Wood Frame 6/29/2023 Approved CAMERON CHABAN
Final 7/5/2023 Not Ready for Inspection CAMERON CHABAN
Final 7/14/2023 OK to Issue CofO CAMERON CHABAN