425 N BOWLING GREEN WAY 90049
Certificate Information: 425 N BOWLING GREEN WAY 90049
- Application / Permit
- 19010-20000-05460
- Plan Check / Job No.
- B19VN21122
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 13' X 18' DETACHED CABANA PER ENGINEERING
- Permit Issued
- Issued on 6/22/2020
- Issuing Office
- Current Status
- CofO Issued on 6/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | JENNIFER LEE |
| Corrections Issued | 12/17/2019 | JENNIFER LEE |
| Quality Review Completed | 12/19/2019 | STEVEN KIM |
| Building Plans Picked Up | 12/20/2019 | APPLICANT |
| Green Plans Picked Up | 12/20/2019 | APPLICANT |
| Applicant returned to address corrections | 6/10/2020 | JENNIFER LEE |
| Plan Check Approved | 6/22/2020 | JENNIFER LEE |
| Issued | 6/22/2020 | APPLICANT |
| CofO in Progress | 6/13/2022 | MICHAEL PELHAM |
| Permit Finaled | 6/13/2022 | DANIEL ORRANTE |
| CofO Issued | 6/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 12/17/2019 | JENNIFER LEE |
| Grading Pre-Inspection | Cleared | 12/17/2019 | JENNIFER LEE |
| BHO/Hillside ordinance | Cleared | 1/14/2020 | APEKSHYA BAJRACHARYA |
| BHO/Hillside ordinance | Cleared | 1/14/2020 | APEKSHYA BAJRACHARYA |
| BHO/Hillside ordinance | Cleared | 1/14/2020 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2020 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 1/14/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/14/2020 | APEKSHYA BAJRACHARYA |
| Green Code | Cleared | 1/28/2020 | MICHAEL AYERS |
| Drainage to Storm Drain | Cleared | 6/1/2020 | MAHELET GEBEYHU |
| Miscellaneous | Cleared | 6/2/2020 | NIKTA MOUSAVI |
Contact Information
| Contractor | L A Home Construction Inc; Lic. No.: 1032013-B | 18530 HATTERAS ST #310 TARZANA, CA 91356 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/26/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/27/2020 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/3/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/23/2020 | SGSOV Not Ready | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 12/2/2020 | SGSOV Not Ready | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Approved | CARLOS MATAMOROS |
| Wood Frame | 12/16/2020 | Partial Approval | CARLOS MATAMOROS |
| Pre-Inspection | 1/20/2021 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Rough | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Wood Frame | 3/14/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Drywall Nailing | 3/16/2022 | Approved | CARLOS MATAMOROS |
| Final | 3/16/2022 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 3/16/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 3/16/2022 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/16/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 3/16/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 3/16/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 3/16/2022 | Partial Approval | CARLOS MATAMOROS |
| Final | 5/25/2022 | Corrections Issued | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 5/25/2022 | Approved | CARLOS MATAMOROS |
| Wood Frame | 5/25/2022 | Approved | CARLOS MATAMOROS |
| Final | 6/10/2022 | Partial Approval | CARLOS MATAMOROS |