4261 N DENNY AVE 91602

Certificate Information: 4261 N DENNY AVE 91602

Application / Permit
19010-20000-05403
Plan Check / Job No.
B19VN20975
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 18'9" X 15'5" IRREGULAR SHAPED DETACHED RECREATION ROOM, ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 RARES BODEA
Corrections Issued 12/18/2019 RARES BODEA
Quality Review Completed 12/20/2019 GUANG MIN TUNG
Building Plans Picked Up 1/14/2020 APPLICANT
Green Plans Picked Up 1/14/2020 APPLICANT
Applicant returned to address corrections 9/24/2020 RARES BODEA
Applicant returned to address corrections 10/7/2020 RARES BODEA
Plan Check Approved 10/15/2020 RARES BODEA
Issued 10/16/2020 APPLICANT
CofO in Progress 9/7/2021 THOMAS FINNILA
CofO Issued 11/1/2021 MICHAEL SMITH
Permit Finaled 11/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 6/12/2020 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 6/24/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 6/24/2020 GABRIEL ROBLES
Tract Map conditions Cleared 8/3/2020 GRISELDA GONZALEZ
Construction near power lines Cleared 8/6/2020 WALTER RAMIREZ
Construction within easement Cleared 8/6/2020 WALTER RAMIREZ
Trees in Parkway Cleared 8/17/2020 JOHN KIM
Hydrant and Access approval Cleared 8/24/2020 MATTHEW CRAIG
ZI Cleared 8/24/2020 HERMINIGILDO AGUSTIN
Green Code Cleared 9/4/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/28/2020 Corrections Issued THOMAS FINNILA
Deputy Reinf. Concrete 11/5/2020 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 11/9/2020 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 12/28/2020 Approved THOMAS FINNILA
PLUMBING-Rough 12/28/2020 Approved THOMAS FINNILA
ELECTRICAL-Rough 1/6/2021 Approved THOMAS FINNILA
Wood Frame 2/12/2021 Not Ready for Inspection THOMAS FINNILA
Wood Frame 2/18/2021 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 2/23/2021 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 2/26/2021 Approved THOMAS FINNILA
Green Building Rough 2/26/2021 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 2/26/2021 Approved THOMAS FINNILA
Insulation 3/3/2021 Not Ready for Inspection THOMAS FINNILA
Drywall Nailing 3/18/2021 Approved THOMAS FINNILA
Underground Mechanical 4/6/2021 Approved JOHN HAYES
ELECTRICAL-Final 8/5/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 8/6/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 8/9/2021 Approved THOMAS FINNILA
Final 9/1/2021 Partial Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/1/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 9/1/2021 Approved THOMAS FINNILA
Final 9/7/2021 OK to Issue CofO THOMAS FINNILA
Green Building Final 9/7/2021 Approved THOMAS FINNILA
Service/Power Release 9/7/2021 Approved THOMAS FINNILA