4377 N CHARLEMONT AVE 91364
Certificate Information: 4377 N CHARLEMONT AVE 91364
- Application / Permit
- 19010-20000-05395
- Plan Check / Job No.
- B19VN20968
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 30'-0"X 25'-0" DET. TWO STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | PARISA ZAHABI |
| Corrections Issued | 1/6/2020 | PARISA ZAHABI |
| Quality Review Completed | 1/14/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 1/16/2020 | APPLICANT |
| Green Plans Picked Up | 2/10/2020 | APPLICANT |
| Applicant returned to address corrections | 12/19/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/5/2023 | MOHAMMAD ESMAILI |
| Issued | 6/5/2023 | APPLICANT |
| CofO in Progress | 2/7/2025 | JOHN HAYES |
| CofO Issued | 3/14/2025 | DANIEL ORRANTE |
| Permit Finaled | 3/14/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/26/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 5/26/2020 | GABRIEL ROBLES |
| BHO/Hillside ordinance | Cleared | 5/26/2020 | GABRIEL ROBLES |
| Address approval | Cleared | 7/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/9/2022 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2022 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 11/15/2022 | NOAH MCCOY |
| Distance to fire station | Cleared | 11/18/2022 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 11/18/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/16/2022 | CHRIS VONG |
| GPI Written Notices | Cleared | 12/19/2022 | PARISA ZAHABI |
| Grading Pre-Inspection | Cleared | 12/19/2022 | PARISA ZAHABI |
| Roof/Waste drainage to street | Cleared | 1/19/2023 | CARLOS AGUILERA |
| Green Code | Cleared | 6/5/2023 | MICHAEL AYERS |
| Miscellaneous | Cleared | 6/5/2023 | NELSON RODRIGUEZ |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/24/2023 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 10/24/2023 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 11/9/2023 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2023 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 11/20/2023 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 12/18/2023 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2024 | Partial Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/30/2024 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 2/22/2024 | Approved | MORRIS JACKSON |
| Green Building Rough | 2/22/2024 | Approved | MORRIS JACKSON |
| HVAC-Rough | 2/22/2024 | Approved | MORRIS JACKSON |
| Verify Sprinkler Sign Off | 2/22/2024 | Approved | MORRIS JACKSON |
| Insulation | 3/4/2024 | Approved | MORRIS JACKSON |
| Drywall Nailing | 3/15/2024 | No Access for Inspection | KRISTEN CAUSEY |
| Shower Pan | 4/18/2024 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 4/24/2024 | Approved | MORRIS JACKSON |
| Sewer | 4/24/2024 | Approved | MORRIS JACKSON |
| Pre-Inspection | 5/6/2024 | Partial Approval | JEFFREY HARTLINE |
| Underground Mechanical | 5/14/2024 | Partial Inspection | JOHN HAYES |
| Underground Mechanical | 5/22/2024 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Corrections Issued | JOHN HAYES |
| HVAC-Rough | 10/11/2024 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 10/16/2024 | Partial Inspection | JOHN HAYES |
| HVAC-Rough | 10/16/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 12/23/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 12/23/2024 | Approved | JOHN HAYES |
| Final | 12/23/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/23/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 12/23/2024 | Approved | JOHN HAYES |
| PLUMBING-Final | 12/23/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/23/2024 | SGSOV Approved | JOHN HAYES |
| Service/Power Release | 12/23/2024 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 12/23/2024 | Approved | JOHN HAYES |
| Final | 2/6/2025 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 2/6/2025 | Approved | JOHN HAYES |
| Service/Power Release | 2/6/2025 | Approved | JOHN HAYES |
| Special/Order Compliance | 2/21/2025 | Corrections Issued | JOHN HAYES |