4926 N PETIT AVE 91436

Certificate Information: 4926 N PETIT AVE 91436

Application / Permit
19010-20000-05393
Plan Check / Job No.
B19VN20967
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW(68'-8"x 43'-0") TWO-STORY SINGLE FAMILY DWELLING AND ATT. 2-CAR GARAGE NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 3/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 TROY DEGUZMAN
Corrections Issued 12/14/2019 TROY DEGUZMAN
Quality Review Completed 12/27/2019 CHON CHIO KUO
Building Plans Picked Up 1/2/2020 APPLICANT
Green Plans Picked Up 1/2/2020 APPLICANT
Plan Check Approved 3/11/2020 TROY DEGUZMAN
Issued 3/13/2020 LADBS
CofO in Progress 12/9/2020 RONALD COWAN
Permit Finaled 12/11/2020 DONALD SUNSERI
CofO Issued 12/11/2020 DONALD SUNSERI
Permit Finaled 12/11/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 1/23/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/23/2020 ADRIAN CASTRO
Sewer availability Cleared 1/23/2020 ADRIAN CASTRO
Low Impact Development Cleared 1/30/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 2/11/2020 LEE GUILBEAUX
Green Code Cleared 2/13/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 2/13/2020 GEORGE SUCHAND
Trees in Parkway Cleared 2/21/2020 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/3/2020 Partial Approval RONALD COWAN
Excavation/Setback/Form/Re-Bar 4/24/2020 Approved RONALD COWAN
Footing/Foundation/Slab 4/24/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 5/1/2020 Approved RONALD COWAN
Wood Frame 5/7/2020 Not Ready for Inspection RONALD COWAN
Wood Frame 5/18/2020 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 5/20/2020 Partial Approval RONALD COWAN
Wood Frame 5/20/2020 Approved RONALD COWAN
PLUMBING-Rough 5/27/2020 Approved RONALD COWAN
ELECTRICAL-Rough 6/3/2020 Approved RONALD COWAN
Shower Pan 6/3/2020 Corrections Issued RONALD COWAN
HVAC-Rough 6/4/2020 Approved RONALD COWAN
HVAC-Rough 6/18/2020 Approved RONALD COWAN
Shower Pan 6/18/2020 Approved RONALD COWAN
Wood Frame 6/18/2020 Not Ready for Inspection RONALD COWAN
Interior/Exterior Lathing 6/25/2020 Partial Approval RONALD COWAN
Deputy Wood Construction 6/30/2020 Approved DONALD SUNSERI
BUILDING-Rough-Frame 7/6/2020 Partial Approval RONALD COWAN
Wood Frame 7/6/2020 Approved RONALD COWAN
Drywall Nailing 7/14/2020 Approved JOSEPH SAGEN
Green Building Rough 7/14/2020 Approved JOSEPH SAGEN
Interior/Exterior Lathing 7/14/2020 Approved JOSEPH SAGEN
Pre-Inspection 10/14/2020 Corrections Issued RONALD COWAN
ELECTRICAL-Final 11/4/2020 Corrections Issued RONALD COWAN
BUILDING-Rough-Frame 11/17/2020 Approved RONALD COWAN
ELECTRICAL-Final 11/17/2020 Corrections Issued RONALD COWAN
Final 11/17/2020 Corrections Issued RONALD COWAN
Green Building Final 11/17/2020 Approved RONALD COWAN
HVAC-Final 11/17/2020 Corrections Issued RONALD COWAN
PLUMBING-Final 11/17/2020 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 11/17/2020 SGSOV Approved RONALD COWAN
Service/Power Release 11/17/2020 Corrections Issued RONALD COWAN
Smoke Detectors 11/17/2020 Approved RONALD COWAN
Verify Sprinkler Sign Off 11/17/2020 Approved RONALD COWAN
ELECTRICAL-Final 12/4/2020 Approved RONALD COWAN
Final 12/4/2020 OK to Issue CofO RONALD COWAN
Gas Test 12/4/2020 Approved RONALD COWAN
HVAC-Final 12/4/2020 Approved RONALD COWAN
PLUMBING-Final 12/4/2020 Approved RONALD COWAN
Service/Power Release 12/4/2020 Approved RONALD COWAN