11618 N FENTON AVE 91342
Certificate Information: 11618 N FENTON AVE 91342
- Application / Permit
- 19010-20000-05363
- Plan Check / Job No.
- B19VN20809
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 25'-0" X 19'-8" DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
- Permit Issued
- Issued on 2/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 12/8/2019 | ARTIN ZARUKIAN |
| Quality Review Completed | 12/10/2019 | GUANG MIN TUNG |
| Green Plans Picked Up | 12/10/2019 | APPLICANT |
| Building Plans Picked Up | 12/11/2019 | APPLICANT |
| Plan Check Approved | 2/10/2020 | ARTIN ZARUKIAN |
| Issued | 2/12/2020 | LADBS |
| CofO in Progress | 11/14/2022 | MICHEL ABAJAN |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/29/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 1/30/2020 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 2/4/2020 | JOHN LIN |
| Hydrant and Access approval | Cleared | 2/4/2020 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 2/4/2020 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 2/10/2020 | ARTIN ZARUKIAN |
Contact Information
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19558 GAULT ST RESEDA, CA 91335 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/6/2020 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/5/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/9/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/22/2020 | Not Ready for Inspection | ROBERT MINASSIANS |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2020 | Corrections Issued | ROBERT MINASSIANS |
| Green Building Rough | 6/22/2020 | Not Ready for Inspection | ROBERT MINASSIANS |
| Verify Sprinkler Sign Off | 6/22/2020 | Not Ready for Inspection | ROBERT MINASSIANS |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/26/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/26/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Rough | 6/26/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 6/26/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 6/26/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 6/26/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/29/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/29/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/29/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/1/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/1/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/1/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Insulation | 7/8/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/8/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/14/2020 | Approved | MICHEL ABAJAN |
| Sewer | 2/25/2021 | Approved | CHARLES POWELL |
| Underground Mechanical | 4/27/2021 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 5/12/2021 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/2/2021 | Partial Inspection | MICHEL ABAJAN |
| Final | 9/2/2021 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 9/2/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 9/2/2021 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 9/2/2021 | Partial Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/2/2021 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 9/2/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 9/2/2021 | Approved | MICHEL ABAJAN |
| Final | 9/26/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 9/26/2022 | Approved | MICHEL ABAJAN |
| Service/Power Release | 9/26/2022 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/7/2022 | Approved | MICHEL ABAJAN |
| Final | 11/7/2022 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 11/7/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/7/2022 | Approved | MICHEL ABAJAN |
| Service/Power Release | 11/7/2022 | Approved | MICHEL ABAJAN |