10579 N TAMARACK AVE 91331

Certificate Information: 10579 N TAMARACK AVE 91331

Application / Permit
19010-20000-05344
Plan Check / Job No.
B19VN20749
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW (36'9"x 34'-0") IRR. SHAPE DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER LA STD WFPP.
Permit Issued
Issued on 1/24/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 TROY DEGUZMAN
Corrections Issued 12/7/2019 TROY DEGUZMAN
Quality Review Completed 12/10/2019 GUANG MIN TUNG
Building Plans Picked Up 12/10/2019 APPLICANT
Green Plans Picked Up 12/10/2019 APPLICANT
Plan Check Approved 12/20/2019 TROY DEGUZMAN
Issued 1/24/2020 LADBS
CofO in Progress 5/22/2020 MICHEL ABAJAN
CofO Issued 7/20/2020 MICHAEL SMITH
Permit Finaled 7/20/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/13/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/13/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 12/13/2019 GEORGE SUCHAND
Sewer availability Cleared 12/13/2019 ADRIAN CASTRO
Low Impact Development Cleared 12/18/2019 ORVAL HERNANDEZ-MARCIAL
Green Code Cleared 12/19/2019 TROY DEGUZMAN
Roof/Waste drainage to street Cleared 12/19/2019 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/3/2020 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 2/6/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Barrier 2/6/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Subgrade 2/6/2020 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 2/11/2020 Approved MICHEL ABAJAN
METHANE-Barrier 2/11/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 2/11/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/20/2020 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 2/20/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 2/20/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 2/20/2020 Not Ready for Inspection MICHEL ABAJAN
Sewer 2/20/2020 Partial Approval MICHEL ABAJAN
Underground Mechanical 2/20/2020 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 2/20/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/24/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 2/24/2020 Approved MICHEL ABAJAN
METHANE-Rough 2/24/2020 Approved MICHEL ABAJAN
Insulation 2/27/2020 Approved MICHEL ABAJAN
Drywall Nailing 3/2/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/2/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 3/12/2020 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 5/13/2020 Approved MICHEL ABAJAN
Final 5/13/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 5/13/2020 Approved MICHEL ABAJAN
HVAC-Final 5/13/2020 Approved MICHEL ABAJAN
PLUMBING-Final 5/13/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/13/2020 SGSOV Approved MICHEL ABAJAN
Service/Power Release 5/13/2020 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 5/13/2020 Approved MICHEL ABAJAN
Final 5/22/2020 OK to Issue CofO MICHEL ABAJAN
Service/Power Release 5/22/2020 Approved MICHEL ABAJAN